265 projects on file, including joint ventures this contractor is part of.
Total projects
265
Total budget
₱11.1B
Average progress
87.4%
Completion rate
72.1%
Average risk score
52.2
Medium risk on average, out of 100
Flagged as unusual
11
4.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 207 | ₱9.9B | 53.2 | 9 | 89.3% |
| National Capital Region | 57 | ₱1.1B | 48.8 | 2 | 80.3% |
| Region IV-B | 1 | ₱99M | 53.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 85 | ₱3.5B | 49.9 | 0 | 85.8% |
| Buildings and Facilities | 83 | ₱2.1B | 49.5 | 4 | 88.9% |
| Flood Control and Drainage | 78 | ₱4.8B | 53.9 | 2 | 88.8% |
| OTHER | 6 | ₱114.1M | 70.3 | 2 | 90.7% |
| GAA 2025 OO-2 | 4 | ₱355.1M | 92.5 | 0 | 74.8% |
| GAA 2025 SSP | 3 | ₱34M | 90.5 | 2 | 38.8% |
| Water Provision and Storage | 3 | ₱6.6M | 22.0 | 0 | 100.0% |
| Bridges, Roads | 2 | ₱53.3M | 49.9 | 0 | 100.0% |
| Bridges | 1 | ₱28.7M | 51.8 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DF0169ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONSTRUCTION OF REVETMENT ALONG CANAS RIVER | Region IV-A | Cavite 1st DEO | On-Going | ₱93.5M | 28% | High risk93 | —-0.009 |
| 25DF0030ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONST OF REVETMENT ALONG ILANG-ILANG RIVER, BRGY NAVARRO, GEN | Region IV-A | Cavite 1st DEO | On-Going | ₱95.5M | 95% | High risk93 | —-0.022 |
| 25OI0063REHABILITATION OF ROAD INCLUDING DRAINAGE, PAMPLONA 3, LAS PINAS CITY LONE DISTRICT | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱17.5M | 0% | High risk92 | Flagged0.030 |
| 25DQ0012CONSTRUCTION OF REVETMENT ALONG CARMONA RIVER, PHASE 1, BARANGAY CABILANG BAYBAY, CARMONA CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱83M | 88% | High risk92 | —-0.026 |
| 25DQ0015CONSTRUCTION OF REVETMENT ALONG CARMONA RIVER, PHASE 2, BARANGAY CABILANG BAYBAY, CARMONA CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱83M | 88% | High risk92 | —-0.026 |
| 25OI0081CONSTRUCTION OF ROAD INCLUDING DRAINAGE AT BARANGAY PULANGLUPA 1, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱6.8M | 96% | High risk91 | —-0.000 |
| 25OI0067REHABILITATION OF ROAD INCLUDING DRAINAGE, TALON 5, LAS PINAS CITY LONE DISTRICT | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱9.7M | 20% | High risk89 | Flagged0.025 |
| 20DF0220CONSTRUCTION /IMPROVEMENT/REHABILITATION OF MULTI-PURPOSE BUILDING AND BARANGAY HALL, BRGY. MANGGAHAN, GENERAL TRIAS; CONSTRUCTION/IMPROVEMENT/REHABILITATION OF COVERED COURT, WELLINGTON PLACE, PHASE 6, BRGY. PASONG CAMACHILE II, GENERAL TRIAS; CONSTRUCTI | Region IV-A | Cavite 1st DEO | Completed | ₱11.6M | 100% | High risk80 | Flagged0.002 |
| 25D00171CONSTRUCTION OF MULTI-PURPOSE BUILDING LAND TRANSPORTATION REGIONAL OFFICE - REGION 4A, LIPA CITY, BATANGAS | Region IV-A | Region IV-A | On-Going | ₱140.3M | 21% | High risk79 | Flagged0.002 |
| 24DQ0120CONSTRUCTION OF REVETMENT INCLUDING OTHER IMPROVEMENTS ALONG CARMONA-BIÑAN RIVER, PHASE III, BRGY. LANTIC, CARMONA CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱95.1M | 46% | High risk78 | Flagged0.047 |
| 19D00063PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE VII, WEST SIDE, CARMONA, CAVITE | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk77 | Flagged0.015 |
| 25DF0134CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF DON PLACIDO CAMPOS AVE., | Region IV-A | Cavite 1st DEO | On-Going | ₱93.6M | 2% | High risk73 | —-0.015 |
| 25DQ0111CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱9.8M | 16% | High risk72 | —-0.016 |
| 25DQ0091CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MOLINO 4, BACOOR CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱6.9M | 0% | High risk72 | —-0.009 |
| 21DF0146LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMBUILDINGS AND OTHER STRUCTURESMULTIPURPOSE/FACILITIESCONSTRUCTION/ REHABILITATION OF MULTI-PURPOSEBUILDING AT ANABU I, IMUS AND CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING AT ANABU,IMUS, CAV | Region IV-A | Cavite 1st DEO | Completed | ₱8.4M | 100% | High risk69 | —-0.042 |
| 22DI0105OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0053+200 - K0054+450, K0055+420 - K0055+744, K0055+750 - K0055+780 | Region IV-A | Laguna 2nd DEO | Completed | ₱40.2M | 100% | High risk69 | —-0.042 |
| 24DF0263ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONSTRUCTION OF REVETMENT ALONG IMUS RIVER, | Region IV-A | Cavite 1st DEO | On-Going | ₱19.4M | 97% | High risk68 | —-0.012 |
| 24D00206CONSTRUCTION OF CARMONA - SILANG DIVERSION ROAD, CAVITE | Region IV-A | Region IV-A | On-Going | ₱24.1M | 47% | High risk68 | Flagged0.002 |
| 19DF0077LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, SCHOOL BUILDING - REHABILITATION/IMPROVEMENT OF CLASSROOM BUILDING, GEN ABADILLA ELEMENTARY SCHOOL ROSARIO; LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTU | Region IV-A | Cavite 1st DEO | Completed | ₱10.4M | 100% | High risk68 | —-0.042 |
| 17DQ0002MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION-MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGESYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BRGY.LANTIC, CARMONA, CAVITE, 5TH LEGISLATIVE DISTRICT | Region IV-A | Cavite 3rd DEO | Completed | ₱19.5M | 100% | High risk67 | —-0.061 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DQ0120CONSTRUCTION OF REVETMENT INCLUDING OTHER IMPROVEMENTS ALONG CARMONA-BIÑAN RIVER, PHASE III, BRGY. LANTIC, CARMONA CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱95.1M | 46% | High risk78 | Flagged0.047 |
| 25OI0063REHABILITATION OF ROAD INCLUDING DRAINAGE, PAMPLONA 3, LAS PINAS CITY LONE DISTRICT | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱17.5M | 0% | High risk92 | Flagged0.030 |
| 24DQ0112CONSTRUCTION OF 4STY8CL, LUCSUHIN ELEMENTARY SCHOOL, SILANG CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱34.5M | 54% | Medium risk44 | Flagged0.026 |
| 25OI0067REHABILITATION OF ROAD INCLUDING DRAINAGE, TALON 5, LAS PINAS CITY LONE DISTRICT | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱9.7M | 20% | High risk89 | Flagged0.025 |
| 23DF0171CONSTRUCTION OF 4STY 12CL SCHOOL BUILDING AT IMUS INTEGRATED SCHOOL, IMUS CITY, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱33.4M | 89% | Medium risk44 | Flagged0.024 |
| 19D00063PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE VII, WEST SIDE, CARMONA, CAVITE | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk77 | Flagged0.015 |
| 24DF0270CONSTRUCTION OF 4-STOREY 12-CLASSROOM SCHOOL BUILDING IN CITY OF IMUS INTEGRATED SCHOOL, BARANGAY PASONG BUAYA, IMUS, CAVITE (PHASE 2) | Region IV-A | Cavite 1st DEO | On-Going | ₱9.8M | 93% | Medium risk44 | Flagged0.009 |
| 23DF0208CONVERGENCE & SPECIAL SUPPORT PROGSUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS RDS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDGS/ FACILITIES CONST OF ROAD W/ DRAINAGE & BR.CONNECTING BRGY MAHARLIKA & ANABU | Region IV-A | Cavite 1st DEO | Completed | ₱28.7M | 100% | Medium risk52 | Flagged0.006 |
| 20DF0220CONSTRUCTION /IMPROVEMENT/REHABILITATION OF MULTI-PURPOSE BUILDING AND BARANGAY HALL, BRGY. MANGGAHAN, GENERAL TRIAS; CONSTRUCTION/IMPROVEMENT/REHABILITATION OF COVERED COURT, WELLINGTON PLACE, PHASE 6, BRGY. PASONG CAMACHILE II, GENERAL TRIAS; CONSTRUCTI | Region IV-A | Cavite 1st DEO | Completed | ₱11.6M | 100% | High risk80 | Flagged0.002 |
| 25D00171CONSTRUCTION OF MULTI-PURPOSE BUILDING LAND TRANSPORTATION REGIONAL OFFICE - REGION 4A, LIPA CITY, BATANGAS | Region IV-A | Region IV-A | On-Going | ₱140.3M | 21% | High risk79 | Flagged0.002 |
| 24D00206CONSTRUCTION OF CARMONA - SILANG DIVERSION ROAD, CAVITE | Region IV-A | Region IV-A | On-Going | ₱24.1M | 47% | High risk68 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 226 | 23OI0044REHABILITATION OF ROAD, PAMPLONA 2, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱7.8M | 100% | Medium risk46 | —-0.097 |
| 227 | 22OI0145CONSTRUCTION OF ROAD INCLUDING DRAINAGE AT BRGY. PILAR, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.096 |
| 228 | 22OI0137REHABILITATION OF ROAD INCLUDING DRAINAGE, TALON 3, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.096 |
| 229 | 22OI0042REHABILITATION OF ROAD, BARANGAY TALON 3, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.097 |
| 230 | 22OI0014REHABILITATION OF ROAD, BARANGAY ALMANZA 2, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱7.8M | 100% | Medium risk46 | —-0.097 |
| 231 | 22OI0034REHABILITATION OF ROAD, BARANGAY TALON 4, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.097 |
| 232 | 22OI0091REHABILITATION OF ROAD AT BRGY. TALON 3, LAS PINAS CITY (PHASE II) | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.097 |
| 233 | 21OI0043REHABILITATION OF ROAD, BARANGAY TALON 5, LAS PIÑAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱7.5M | 100% | Medium risk46 | —-0.098 |
| 234 | 17DF0143COMPLETION OF 4STY 16CL STAND ALONE SHS 5 - BACOOR ES | Region IV-A | Cavite 1st DEO | Completed | ₱7.6M | 100% | Medium risk45 | —-0.029 |
| 235 | 24DF0270CONSTRUCTION OF 4-STOREY 12-CLASSROOM SCHOOL BUILDING IN CITY OF IMUS INTEGRATED SCHOOL, BARANGAY PASONG BUAYA, IMUS, CAVITE (PHASE 2) | Region IV-A | Cavite 1st DEO | On-Going | ₱9.8M | 93% | Medium risk44 | Flagged0.009 |
| 236 | 17DQ0131CONSTRUCTION OF FOUR (4) STOREY TWENTY (20) CLASSROOM SCHOOLBUILDING AT SAN JOSE ELEMENTARY SCHOOL, GENERAL MARIANO ALVAREZ,CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱40M | 100% | Medium risk44 | —-0.025 |
| 237 | 17DQ0109CONSTRUCTION OF FOUR (4) STOREY TWENTY FOUR (24) CLASSROOM SCHOOLBUILDING AT SAN JOSE COMMUNITY HIGH SCHOOL, GENERAL MARIANOALVAREZ, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱46M | 100% | Medium risk44 | —-0.021 |
| 238 | 24DQ0112CONSTRUCTION OF 4STY8CL, LUCSUHIN ELEMENTARY SCHOOL, SILANG CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱34.5M | 54% | Medium risk44 | Flagged0.026 |
| 239 | 23DF0171CONSTRUCTION OF 4STY 12CL SCHOOL BUILDING AT IMUS INTEGRATED SCHOOL, IMUS CITY, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱33.4M | 89% | Medium risk44 | Flagged0.024 |
| 240 | 17DQ0125CONSTRUCTION OF FOUR (4) STOREY EIGHT (8) CLASSROOM SCHOOL BUILDING AT GEN. VITO BELARMINO NATIONAL HIGH SCHOOL, SILANG, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱17.5M | 100% | Medium risk44 | —-0.032 |
| 241 | 17DQ0097PROPOSED CONSTRUCTION OF (4) STOREY (16) CLASSROOM AT AREA J ELEMENTARY SCHOOL, GENERAL MARIANO ALVAREZ, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱35.7M | 100% | Medium risk43 | —-0.026 |
| 242 | 17DQ0115CONSTRUCTION OF FOUR (4) STOREY SIXTEEN (16) CLASSROOM SCHOOL BUILDING AT PALIPARAN LL NATIONAL HIGH SCHOOL, DASMARINAS CITY, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱35.8M | 100% | Medium risk43 | —-0.026 |
| 243 | 17DQ0113CONSTRUCTION OF FOUR (4) STOREY TWELVE (12) CLASSROOM SCHOOL BUILDING AT PALIPARAN LL, NATIONAL HIGH SCHOOL, DASMARINAS CITY, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱30.5M | 100% | Medium risk43 | —-0.028 |
| 244 | 17DQ0092PROPOSED CONSTRUCTION OF (4) STOREY (12) CLASSROOM AT AREA J ELEMENTARY SCHOOL, SILANG, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱30.4M | 100% | Medium risk43 | —-0.028 |
| 245 | 21OI0047REHABILITATION OF ROAD INCLUDING DRAINAGE, BARANGAY TALON 3, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱4.7M | 100% | Medium risk43 | —-0.096 |
| 246 | 23DQ0139CONSTRUCTION OF 3STY9CL, POOC ELEMENTARY SCHOOL, SILANG, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱25.9M | 100% | Medium risk43 | —-0.029 |
| 247 | 20DQ0144CONCRETING OF BRGY. MALAKING TATIAO FMR, BRGY. MALAKING TATIAO, SILANG, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱9.5M | 100% | Medium risk43 | —-0.054 |
| 248 | 23DQ0136CONSTRUCTION OF 3STY9CL, ANIBAN CENTRAL SCHOOL, BACOOR CITY, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱29.8M | 100% | Medium risk43 | —-0.027 |
| 249 | 23OI0047REHABILITATION OF ROAD, TALON 5, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱4.7M | 100% | Medium risk41 | —-0.096 |
| 250 | 24OI0072REHABILITATION OF ROAD, VERGONVILLE, BRGY. PULANGLUPA 2, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱4.7M | 100% | Medium risk41 | —-0.060 |