8 projects on file, including joint ventures this contractor is part of.
Total projects
8
Total budget
₱659.9M
Average progress
92.1%
Completion rate
62.5%
Below 70%
Average risk score
54.9
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 8 | ₱659.9M | 54.9 | 0 | 92.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 6 | ₱517.3M | 54.2 | 0 | 89.5% |
| OTHER | 1 | ₱93.6M | 73.1 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱49M | 41.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23CB0063CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONSTRUCTION OF ROAD LEADING TO MT. SAMAT NATIONAL SHRINE PROJECT IN PILAR, BATAAN (PHASE III) | Region III | Bataan 2nd DEO | Completed | ₱93.6M | 100% | High risk73 | —-0.028 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 23CB0063CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONSTRUCTION OF ROAD LEADING TO MT. SAMAT NATIONAL SHRINE PROJECT IN PILAR, BATAAN (PHASE III) | Region III | Bataan 2nd DEO | Completed | ₱93.6M | 100% | High risk73 | —-0.028 |
| 2 | 25CO0068ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - ROMAN EXPRESSWAY - MARIVELES, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱95.8M | 100% | Medium risk60 | —-0.064 |
| 3 | 23C00264CONVERGENCE AND SPECIAL SUPPORT PROG- BASIC INFRASTRUCTURE PROG- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - REHABILITATION OF ROADS WITH SLIP SLOPES, COLLAPSE, AND LANDSLIDE, BAGAC AND MARIVELES, BATAAN | Region III | Region III | On-Going | ₱99M | 100% | Medium risk58 | —-0.053 |
| 4 | 22CB0092CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - IMPROVEMENT OF ROAD LEADING TO MT. SAMAL NATIONAL SHRINE PROJECT, BATAAN | Region III | Bataan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk57 | —-0.085 |
| 5 | 24CB0096PREVENTIVE MAINTENANCE - SECONDARY ROADS - ROMAN EXPRESSWAY - KO120+688-KO121+200, KO121+400-KO121+855, KO122+946-KO122+1007, BATAAN 2ND DISTRICT | Region III | Bataan 2nd DEO | Completed | ₱98M | 100% | Medium risk56 | —-0.087 |
| 6 | 24CB0121ROAD WIDENING - SECONDARY ROADS - ROMAN EXPRESSWAY - KO138+120-KO138+860, KO139+335-KO139+800, KO141+472-KO141+902, BATAAN 2ND DISTRICT | Region III | Bataan 2nd DEO | On-Going | ₱79M | 37% | Medium risk49 | —-0.048 |
| 7 | 24CB0109PREVENTIVE MAINTENANCE - TERTIARY ROADS - ENRIQUE A. GARCIA AVE - (SO1421LZ) KO124+242-KO125+338, (SO1422LZ) KO125+(-332)-KO125+764, BATAAN 2ND DISTRICT | Region III | Bataan 2nd DEO | Completed | ₱49M | 100% | Medium risk46 | —-0.099 |
| 8 | 22CB0074CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PANTINGAN RIVER PHASE 1, BRGY. PANTINGAN, PILAR, BATAAN | Region III | Bataan 2nd DEO | Completed | ₱49M | 100% | Medium risk41 | —-0.084 |