Opening the dossier…
Opening the dossier…
Contractor dossier
5 projects on file, including joint ventures this contractor is part of.
Total projects
5
Total budget
₱65.3M
Average progress
94.1%
Completion rate
40.0%
Below 70%
Average risk score
54.0
Medium risk on average, out of 100
Flagged as unusual
1
20.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 5 | ₱65.3M | 54.0 | 1 | 94.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 3 | ₱26.3M | 45.8 | 0 | 97.3% |
| OTHER | 1 | ₱19.5M | 86.3 | 1 | 78.5% |
| Bridges | 1 | ₱19.5M | 46.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HN0157CONSTRUCTION OF SCHOOL BUILDING (PHASE 2), CAWHAGAN INTEGRATED SCHOOL, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱19.5M | 79% | High risk86 | Flagged0.052 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HN0157CONSTRUCTION OF SCHOOL BUILDING (PHASE 2), CAWHAGAN INTEGRATED SCHOOL, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱19.5M | 79% | High risk86 | Flagged0.052 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25HN0157CONSTRUCTION OF SCHOOL BUILDING (PHASE 2), CAWHAGAN INTEGRATED SCHOOL, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱19.5M | 79% | High risk86 | Flagged0.052 |
| 2 | 25HN0111SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY POBLACION, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱9.7M | 92% | Medium risk48 | —-0.056 |
| 3 | 25HN0099SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF SEAWALL PROTECTION STRUCTURE, OLANGO ISLAND, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱19.5M | 100% | Medium risk46 | —-0.029 |
| 4 | 24HN0182CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, AT BARANGAY PUNTA ENGANO, LAPU LAPU CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱6.9M | 100% | Medium risk46 | —-0.096 |
| 5 | 23HN0207CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION OF MUTLI-PURPOSE BUILDING (BARANGAY HALL), BRGY. PUNTA ENGANO, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱9.6M | 100% | Medium risk44 | —-0.049 |