Opening the dossier…
Opening the dossier…
Contractor dossier
92 projects on file, including joint ventures this contractor is part of.
Total projects
92
Total budget
₱1.9B
Average progress
99.9%
Completion rate
98.9%
Average risk score
42.8
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 89 | ₱1.9B | 42.9 | 0 | 99.9% |
| Region IV-B | 2 | ₱19.7M | 37.4 | 0 | 100.0% |
| Negros Island Region | 1 | ₱11.2M | 38.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 49 | ₱939M | 42.2 | 0 | 100.0% |
| Buildings and Facilities | 16 | ₱185M | 34.1 | 0 | 100.0% |
| Bridges | 11 | ₱257.7M | 47.1 | 0 | 99.1% |
| Flood Control and Drainage | 11 | ₱398.1M | 46.1 | 0 | 100.0% |
| Water Provision and Storage | 3 | ₱23.3M | 45.6 | 0 | 100.0% |
| OTHER | 2 | ₱103.2M | 78.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20GI0017ACCESS ROAD INCLUDING ALTERNATE ROUTE LEADING TO SEVEN CITIES AGRI TOURISM SITE, ALIMODIAN, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱75.3M | 100% | High risk81 | —-0.019 |
| 19GG0043CONSTRUCTION OF CONCRETE ROAD AND CONSTRUCTION OF BRIDGE OF JCT. ILOILO EAST COAST - CAPIZ ROAD - JCT. PASSI - SAN RAFAEL - LEMERY - SARA ROAD LEADING TO BANATE PORT, BANATE, ILOILO, K009 + 122.45 - K009 + 380.45 & K0013 + 400 - K0014 +268 | Region VI | Iloilo 2nd DEO | Completed | ₱27.9M | 100% | High risk76 | —-0.029 |
| 17GI0013REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE, JCT BANCAL-LEON-ANTIQUE BDRY RD - K0038+1118 - K0039+005, K0047+794 - K0047+829 | Region VI | Iloilo 4th DEO | Completed | ₱9.1M | 100% | High risk66 | —-0.056 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 20EH0080CONSTRUCTION OF SEAWALL, BRGY. MASUDSUD, CONCEPCION, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱14.8M | 100% | Medium risk37 | —-0.075 |
| 77 | 19GG0125CONCRETING OF BRGY. MAPILI FMR, BRGY. MAPILI, SAN ENRIQUE, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱4.7M | 100% | Medium risk37 | —-0.036 |
| 78 | 18GG0103CONCRETING OF SAN ANTONIO FMR, SAN ENRIQUE, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱4.7M | 100% | Medium risk36 | —-0.034 |
| 79 | 17GI0014REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE, GUIMBAL-IGBARAS-TUBUNGAN-LEON RD - K0064+-325 - K0064+-299 | Region VI | Iloilo 4th DEO | Completed | ₱1.1M | 100% | Low risk27 | —-0.054 |
| 80 | 18GG0086REHABILITATION OF LOCAL ROAD AT DORILLO ST., BRGY. POBLACION, ILAYA - ILAWOD, PASSI CITY, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱4.7M | 100% | Low risk27 | —-0.084 |
| 81 | 19GH0055CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BANCAL, CARLES, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱2.9M | 100% | Low risk26 | —-0.081 |
| 82 | 18GG0085CONCRETING OF ABACA PROPER - SITIO IMBAQUIRAN - BARANGAY BRAULAN ROAD, SAN ENRIQUE, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱4.7M | 100% | Low risk25 | —-0.087 |
| 83 | 23GA0125CONSTRUCTION (COMPLETION) OF MPB BRGY. OGSIP, LIBACAO, AKLAN | Region VI | Aklan DEO | Completed | ₱2M | 100% | Low risk24 | —-0.083 |
| 84 | 23GA0112COMPLETION OF MULTI-PURPOSE PAVEMENT BARANGAY BONZA, LIBACAO, AKLAN | Region VI | Aklan DEO | Completed | ₱2.5M | 100% | Low risk24 | —-0.085 |
| 85 | 18GG0076CONCRETING OF DACAL TO SITIO FACULTAD BARANGAY ROAD, SAN ENRIQUE, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱4.7M | 100% | Low risk24 | —-0.085 |
| 86 | 18GG0079CONCRETING OF JNR AGUTAYAN, CUBAY TO SITIO AMONTAY, BARANGAY DUMILES ROAD, SAN ENRIQUE, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱4.7M | 100% | Low risk24 | —-0.085 |
| 87 | 19GI0105CONCRETING OF BARANGAY WARI-WARE AND BARANGAY CABUGAO VIA ECOPARK ROAD, IN BARANGAY WARI-WARE, NEW LUCENA, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱3M | 100% | Low risk24 | —-0.083 |
| 88 | 18GI0009CONCRETING OF ROAD (SITIO SABA), BRGY. JIBAO-AN, STA. BARBARA, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱1.9M | 100% | Low risk17 | —-0.083 |
| 89 | 18GI0028CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 15, SAN MIGUEL, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.084 |
| 90 | 18GI0019CONSTRUCTION OF MULTI-PURPOSE BUILDING (LIVELIHOOD CENTER), BRGY. POBLACION, SAN MIGUEL, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.085 |
| 91 | 19GI0024CONSTRUCTION ( COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. ANONANG, LEON, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱1.5M | 100% | Low risk13 | —-0.084 |
| 92 | 19GI0045CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. OMAMBONG LEON, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱1.5M | 100% | Low risk13 | —-0.084 |