Contractor dossier
19 projects on file, including joint ventures this contractor is part of.
Total projects
19
Total budget
₱549M
Average progress
87.0%
Completion rate
73.7%
Average risk score
44.0
Medium risk on average, out of 100
Flagged as unusual
1
5.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 18 | ₱547M | 45.6 | 1 | 86.3% |
| Region II | 1 | ₱1.9M | 16.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 10 | ₱286.7M | 45.3 | 1 | 76.1% |
| Flood Control and Drainage | 4 | ₱223.9M | 51.1 | 0 | 97.9% |
| Buildings and Facilities | 4 | ₱36.8M | 39.9 | 0 | 100.0% |
| Bridges | 1 | ₱1.5M | 20.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17PJ0014CONSTRUCTION / IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURIST DESTINATION - KINAKIN - CAMBULO ROAD LEADING TO KINAKIN & CAMBULO NATIVE VILLAGES RICE TERRACES, BANAO RICE TERRACES | Cordillera Administrative Region | Ifugao 2nd DEO | Terminated | ₱60.5M | 0% | High risk63 | Flagged0.002 |
| 24P00030ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DANGGO FLOOD CONTROL (PHASE II) DANGGO, TINOC, IFUGAO | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | High risk61 | —-0.058 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17PJ0014CONSTRUCTION / IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURIST DESTINATION - KINAKIN - CAMBULO ROAD LEADING TO KINAKIN & CAMBULO NATIVE VILLAGES RICE TERRACES, BANAO RICE TERRACES | Cordillera Administrative Region | Ifugao 2nd DEO | Terminated | ₱60.5M | 0% | High risk63 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 17PJ0014CONSTRUCTION / IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURIST DESTINATION - KINAKIN - CAMBULO ROAD LEADING TO KINAKIN & CAMBULO NATIVE VILLAGES RICE TERRACES, BANAO RICE TERRACES | Cordillera Administrative Region | Ifugao 2nd DEO | Terminated | ₱60.5M | 0% | High risk63 | Flagged0.002 |
| 2 | 24P00030ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DANGGO FLOOD CONTROL (PHASE II) DANGGO, TINOC, IFUGAO | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | High risk61 | —-0.058 |
| 3 | 23P00035CONSTRUCTION OF FLOOD CONTROL ALONG TINOC RIVER, STA. 104+400 - STA.105+535 (DANGGO SECTION), TINOC, IFUGAO | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱78.9M | 100% | Medium risk52 | —-0.064 |
| 4 | 23P00065REHABILITATION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG KIANGAN - TINOC - BUGUIAS ROAD, K0354+200 - K0354+500, GUMHANG, TINOC, IFUGAO | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱47.5M | 100% | Medium risk50 | —-0.082 |
| 5 | 23PG0031LAGAWE-HINGYON ROAD VIA BURNAY LEADING TO MT. ATUGO AND OTHER TOURISM DESTINATIONS, LAGAWE AND HINGYON, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.082 |
| 6 | 21P00115CONSTRUCTION OF EVACUATION CENTER, BUTIGUE, PARACELIS, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱9.2M | 100% | Medium risk49 | —-0.087 |
| 7 | 24PG0043CONSTRUCTION OF DPWH IFUGAO 1ST DEO MULTI-PURPOSE BUILDING, LAGAWE, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱10.6M | 100% | Medium risk49 | —-0.080 |
| 8 | 18PG0069CONCRETING AND IMPROVEMENT OF NAMAL-PULA ACCESS ROAD, ASIPULO, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱15.1M | 100% | Medium risk47 | —-0.035 |
| 9 | 22PG0052CONSTRUCTION OF 2STY4CL, DULI ES EXTENSION, ASIPULO, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱16.1M | 100% | Medium risk46 | —-0.040 |
| 10 | 25PG0007CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-NUEVA VIZCAYA-IFUGAO-MT. PROVINCE RD. - K0317+667, LAGAWE, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱40.5M | 36% | Medium risk46 | —-0.040 |
| 11 | 25PG0006CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-NUEVA VIZCAYA-IFUGAO-MT. PROVINCE RD. - K0316+940, K0317+260, K0317+914-K0317+982, LAGAWE, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱33.2M | 44% | Medium risk46 | —-0.043 |
| 12 | 24PG0013CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGAWE RIVER, STA. 5+350.50 - 5+800, BOLIWONG, LAGAWE, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱29.2M | 100% | Medium risk46 | —-0.067 |
| 13 | 24PG0020CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IBULAO RIVER, STA. 342+124 - STA. 342+424, CABA, LAGAWE, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱19.4M | 91% | Medium risk46 | —-0.028 |
| 14 | 23PG0062REHABILITATION OF ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG KIANGAN-TINOC-BUGUIAS ROAD, K0351+800-K0351+900, GUMHANG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱14.2M | 100% | Medium risk45 | —-0.084 |
| 15 | 23PJ003823PJ0038: CONVERGENCE ANDSPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATINGGAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADSCONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES-CONSTRUCTION OFROAD, BARANGAY MONTABIO | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱14.8M | 100% | Medium risk45 | —-0.084 |
| 16 | 24P00043CONSTRUCTION OF MONTABIONG, LAGAWE TO BANAO & ANABA, BANAUE ACCESS ROADTINOC, IFUGAO | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱9.9M | 81% | Medium risk45 | —-0.044 |
| 17 | 16PJ0059REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES, BANAUE BRIDGE ( B02207LZ) ALONG BANAUE- MAYOYAO- ALFONSO LISTA- ISABELA BOUNDARY ROAD | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱1.5M | 100% | Low risk20 | —-0.020 |
| 18 | 17BI0068IMPROVEMENT OF BRGY. SALINGSINGAN FMR, BRGY. SALINGSINGAN, AMBAGUIO, NUEVA VIZCAYA | Region II | Nueva Vizcaya DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.006 |
| 19 | 21P00114SUPPLEMENTARY AND REVISED BASE PLATE AND BRACING AND IMPROVEMENT OF PERMANENT EVACUATION CENTER/ MULTI-PURPOSE COVERED COURT, STA. MARIA, ALFONSO LISTA, IFUGAO | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱875.6K | 100% | Low risk16 | —-0.081 |