8 projects on file, including joint ventures this contractor is part of.
Total projects
8
Total budget
₱32.8M
Average progress
97.1%
Completion rate
62.5%
Below 70%
Average risk score
50.8
Medium risk on average, out of 100
Flagged as unusual
2
25.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 8 | ₱32.8M | 50.8 | 2 | 97.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Water Provision and Storage | 4 | ₱17.6M | 34.5 | 0 | 98.0% |
| GAA 2025 SSP | 3 | ₱12.7M | 85.7 | 2 | 95.0% |
| Buildings and Facilities | 1 | ₱2.5M | 11.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NH0107CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY SAN PEDRO, LIANGA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱4.9M | 89% | High risk94 | Flagged0.017 |
| 25NH0109CONSTRUCTION (COMPLETION) OF SOLAR WATER SYSTEM IN SOMO-SOMO, TAGO, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱3.9M | 96% | High risk84 | Flagged0.017 |
| 25NH0110CONSTRUCTION (COMPLETION) OF SOLAR WATER SYSTEM IN MABAHIN, CORTES, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱3.9M | 100% | High risk80 | —-0.011 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NH0109CONSTRUCTION (COMPLETION) OF SOLAR WATER SYSTEM IN SOMO-SOMO, TAGO, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱3.9M | 96% | High risk84 | Flagged0.017 |
| 25NH0107CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY SAN PEDRO, LIANGA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱4.9M | 89% | High risk94 | Flagged0.017 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25NH0107CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY SAN PEDRO, LIANGA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱4.9M | 89% | High risk94 | Flagged0.017 |
| 2 | 25NH0109CONSTRUCTION (COMPLETION) OF SOLAR WATER SYSTEM IN SOMO-SOMO, TAGO, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱3.9M | 96% | High risk84 | Flagged0.017 |
| 3 | 25NH0110CONSTRUCTION (COMPLETION) OF SOLAR WATER SYSTEM IN MABAHIN, CORTES, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱3.9M | 100% | High risk80 | —-0.011 |
| 4 | 25NH0108CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY AMONTAY, MARIHATAG, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱4.9M | 92% | Medium risk42 | —-0.012 |
| 5 | 24NH0094CONSTRUCTION OF POTABLE WATER SYSTEM NEMSU - SAN MIGUEL CAMPUS, SAN MIGUEL, SURIGAO DEL SUR (LEVEL 2) | Region XIII | Surigao del Sur 1st DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.041 |
| 6 | 24NH0099CONSTRUCTION OF WATER SYSTEM (LEVEL II) SITIO GACUB, HINAPOYAN, CARMEN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.044 |
| 7 | 25NH0113CONSTRUCTION OF HABAG WATER SUPPLY, HABAG, LANUZA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱2.9M | 100% | Low risk18 | —-0.040 |
| 8 | 24NI0066CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PUROK BONGGAITAN, BARANGAY MANGAGOY, CITY OF BISLIG, SURIGAO DEL SUR | Region XIII | Surigao del Sur 2nd DEO | Completed | ₱2.5M | 100% | Low risk11 | —-0.070 |