Contractor dossier
10 projects on file, including joint ventures this contractor is part of.
Total projects
10
Total budget
₱1.2B
Average progress
90.0%
Completion rate
90.0%
Average risk score
58.7
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Central Office | 5 | ₱1.2B | 75.3 | 0 | 100.0% |
| National Capital Region | 5 | ₱37.5M | 42.1 | 0 | 80.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 7 | ₱1.2B | 67.2 | 0 | 100.0% |
| Roads | 3 | ₱18.6M | 38.9 | 0 | 66.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20O00094UPGRADING/REHABILITATION OF NORTH NAVOTAS PUMPING STATION AND REPAIR OF NAVOTAS NAVIGATIONAL GATE (PHASE I) | Central Office | Flood Control Management Cluster | Completed | ₱382.4M | 100% | High risk77 | —-0.035 |
| 19Z00017UPGRADING OF CATMON PUMPING STATION, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱416.4M | 100% | High risk76 | —-0.032 |
| 21O00093UPGRADING OF ESCOLTA PUMPING STATION, MANILA | Central Office | Flood Control Management Cluster | Completed | ₱172.1M | 100% | High risk76 | —-0.051 |
| 21O00124UPGRADING OF MAYPAJO PUMPING STATION, CALOOCAN CITY | Central Office | Flood Control Management Cluster | Completed | ₱93M | 100% | High risk74 | —-0.070 |
| 17O00022VALENZUELA-OBANDO MEYCAUAYAN FLOOD CONTROL PROJECT NAVOTAS-PROVISION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE (CONSTRUCTION OF PUMPING STATION WITH BOX CULVERT ALONG COASTAL DIKE), NAVOTAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱89.8M | 100% | High risk72 | —-0.051 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 20O00094UPGRADING/REHABILITATION OF NORTH NAVOTAS PUMPING STATION AND REPAIR OF NAVOTAS NAVIGATIONAL GATE (PHASE I) | Central Office | Flood Control Management Cluster | Completed | ₱382.4M | 100% | High risk77 | —-0.035 |
| 2 | 19Z00017UPGRADING OF CATMON PUMPING STATION, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱416.4M | 100% | High risk76 | —-0.032 |
| 3 | 21O00093UPGRADING OF ESCOLTA PUMPING STATION, MANILA | Central Office | Flood Control Management Cluster | Completed | ₱172.1M | 100% | High risk76 | —-0.051 |
| 4 | 21O00124UPGRADING OF MAYPAJO PUMPING STATION, CALOOCAN CITY | Central Office | Flood Control Management Cluster | Completed | ₱93M | 100% | High risk74 | —-0.070 |
| 5 | 17O00022VALENZUELA-OBANDO MEYCAUAYAN FLOOD CONTROL PROJECT NAVOTAS-PROVISION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE (CONSTRUCTION OF PUMPING STATION WITH BOX CULVERT ALONG COASTAL DIKE), NAVOTAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱89.8M | 100% | High risk72 | —-0.051 |
| 6 | 17OI0154CONSTRUCTION OF SLOPE PROTECTION ALONG ZAPOTE RIVER, BRGY. TALON 5, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱11.8M | 100% | Medium risk49 | —-0.060 |
| 7 | 21OI0115REPAIR / REHABILITATION OF SLOPE PROTECTION AND OTHER IMPROVEMENTS AT ZAPOTE RIVER DRIVE, PAMPLONA DOS, LAS PIСS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱5.4M | 100% | Medium risk46 | —-0.096 |
| 8 | 19OI0147CONST. OF ROAD INCLUDING OTHER IMPVT ALONG ZAPOTE RIVER, BRGY. TALON 2, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.097 |
| 9 | 23OC0009REHABILITATION OF DRAINAGE SYSTEM ALONG DIAN ST., BUENDIA AVE. AND ITS LATERALS,MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱7.1M | 100% | Medium risk45 | —-0.089 |
| 10 | 24OC0125CONSTRUCTION OF ROAD (FROM MACAPAGAL AVE. EXT. TO BIDGE LPPWP) IN BARANGAY DON GALO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱3.4M | 0% | Low risk25 | —-0.029 |