Opening the dossier…
Opening the dossier…
Contractor dossier
24 projects on file, including joint ventures this contractor is part of.
Total projects
24
Total budget
₱265M
Average progress
76.1%
Completion rate
70.8%
Average risk score
47.0
Medium risk on average, out of 100
Flagged as unusual
2
8.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 23 | ₱248.5M | 47.4 | 2 | 75.1% |
| Region IV-B | 1 | ₱16.5M | 36.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 12 | ₱104M | 42.6 | 0 | 66.7% |
| Buildings and Facilities | 9 | ₱145.6M | 48.1 | 1 | 92.5% |
| GAA 2025 OO-1 | 2 | ₱13.5M | 79.2 | 1 | 46.9% |
| OTHER | 1 | ₱1.9M | 25.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OC0062ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS-SOUTH SUPER H-WAY EAST SERVICE RD - K0012 + (-409) - K0012 + (-089)PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱11.6M | 94% | High risk86 | —-0.018 |
| 25OC0046ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS-SOUTH SUPER H-WAY WEST SERVICE RD - K0018 + 370 - K0018 + 461PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱1.9M | 0% | High risk72 | Flagged0.010 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OC0046ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS-SOUTH SUPER H-WAY WEST SERVICE RD - K0018 + 370 - K0018 + 461PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱1.9M | 0% | High risk72 | Flagged0.010 |
| 24OC0140CONSTRUCTION OF 4-STOREY 12-CLASSROOM SCHOOL BUILDING WITH ROOFDECK IN DON BOSCO ELEMENTARY SCHOOL, BARANGAY DON BOSCO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱39.4M | 32% | Medium risk48 | Flagged0.009 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25OC0062ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS-SOUTH SUPER H-WAY EAST SERVICE RD - K0012 + (-409) - K0012 + (-089)PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱11.6M | 94% | High risk86 | —-0.018 |
| 2 | 25OC0046ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS-SOUTH SUPER H-WAY WEST SERVICE RD - K0018 + 370 - K0018 + 461PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱1.9M | 0% | High risk72 | Flagged0.010 |
| 3 | 24OD0230CONSTRUCTION OF MULTI-PURPOSE BUILDING, BUILDING 1, BARANGAY 167, CALOOCAN, MANILA | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.5M | 100% | Medium risk50 | —-0.099 |
| 4 | 23OD0127CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 7, BARANGAY 176, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.4M | 100% | Medium risk49 | —-0.099 |
| 5 | 23OD0113CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 10, PACKAGE 4, BARANGAY 176, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.4M | 100% | Medium risk49 | —-0.100 |
| 6 | 23OD0092CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 160, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱6.8M | 100% | Medium risk48 | —-0.102 |
| 7 | 23OD0081CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 9, BARANGAY 176, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.7M | 100% | Medium risk48 | —-0.102 |
| 8 | 22OC0147REHABILITATION OF MULTI-PURPOSE BUILDING, PHASE 4 MULTINATIONAL, BRGY. MOONWALK,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.101 |
| 9 | 24OD0199CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING AT MCU, PHASE 8 PKG 4, BRGY. 176, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.101 |
| 10 | 24OC0140CONSTRUCTION OF 4-STOREY 12-CLASSROOM SCHOOL BUILDING WITH ROOFDECK IN DON BOSCO ELEMENTARY SCHOOL, BARANGAY DON BOSCO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱39.4M | 32% | Medium risk48 | Flagged0.009 |
| 11 | 25OC0065ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - SOUTH SUPER H-WAY WEST SERVICE RD - K0015 + 330 - K0015 + 711PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱16.6M | 0% | Medium risk46 | —-0.034 |
| 12 | 24OD0096REHABILITATION OF ROAD AND DRAINAGE AT DEPARO SUBDIVISION, BRGY. 168, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.097 |
| 13 | 24OD0054IMPROVEMENT OF ROAD INCLUDING DRAINAGE SYSTEM, BARANGAY 157, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.099 |
| 14 | 24OD0186CONSTRUCTION OF ROAD AND DRAINAGE AT DEL REY VILLE I, BRY. 163, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱5.8M | 100% | Medium risk46 | —-0.099 |
| 15 | 24OD0206CONSTRUCTION OF ROAD, BARANGAY 159, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱11.7M | 100% | Medium risk46 | —-0.100 |
| 16 | 25OC0063ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS-SOUTH SUPER H-WAY EAST SERVICE RD - K0015 + 808 - K0015 + 929PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱5.8M | 0% | Medium risk46 | —-0.034 |
| 17 | 25OC0064ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - SOUTH SUPER H-WAY EAST SERVICE RD - K0015 + 929 - K0015 + 1042PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱8.7M | 0% | Medium risk46 | —-0.035 |
| 18 | 25OC0017ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - SOUTH SUPER H-WAY EAST SERVICE RD - K0013 + 512 - K0013 + 880PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱9.8M | 0% | Medium risk46 | —-0.036 |
| 19 | 18OD0244CONSTRUCTION OF 4 STOREY 8 CLASSROOM SCHOOL BUILDING DEPARO HIGH SCHOOL, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱21.6M | 100% | Medium risk45 | —-0.032 |
| 20 | 24OD0115CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG SANGGUMAY RD., BRGY. 175, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.6M | 100% | Medium risk45 | —-0.099 |
| 21 | 23OD0038CONSTRUCTION OF ROAD (PATHWALKS) WITH DRAINAGE ALONG BARANGAY 176, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱7.8M | 100% | Medium risk45 | —-0.098 |
| 22 | 18EA0119PACKAGE 40- A) CONCRETING OF 1.5 LANE KM. TIBYAYONG-APLAYA ROAD, BARANGAY BUANGAN, TORRIJOS, MARIND | Region IV-B | Marinduque DEO | Completed | ₱16.5M | 100% | Medium risk37 | —-0.091 |
| 23 | 18OD0055CONSTRUCTION OF ROAD BRGY. 185 MALARIA GUMAMELA, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱1.9M | 100% | Low risk26 | —-0.042 |
| 24 | 18OD0054CONSTRUCTION OF ROAD, BRGY. 185, CBY, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱1.9M | 100% | Low risk18 | —-0.096 |