Contractor dossier
343 projects on file, including joint ventures this contractor is part of.
Total projects
343
Total budget
₱29.6B
Average progress
98.5%
Completion rate
97.4%
Average risk score
55.0
Medium risk on average, out of 100
Flagged as unusual
10
2.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 235 | ₱19.9B | 55.1 | 3 | 99.8% |
| Region IV-A | 34 | ₱3.2B | 63.3 | 0 | 100.0% |
| Region II | 23 | ₱883.6M | 50.9 | 5 | 88.3% |
| Region I | 19 | ₱2.7B | 57.3 | 2 | 89.5% |
| Region XIII | 10 | ₱851M | 46.1 | 0 | 100.0% |
| Region IV-B | 8 | ₱885M | 53.9 | 0 | 100.0% |
| Region XI | 7 | ₱909.8M | 62.0 | 0 | 100.0% |
| Region VII | 4 | ₱22.7M | 23.6 | 0 | 100.0% |
| Region XII | 3 | ₱242.8M | 35.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 225 | ₱22.4B | 55.8 | 2 | 99.4% |
| Bridges | 59 | ₱3.9B | 55.6 | 5 | 97.0% |
| Buildings and Facilities | 26 | ₱429M | 38.3 | 1 | 96.2% |
| Flood Control and Drainage | 24 | ₱2.2B | 56.3 | 0 | 100.0% |
| OTHER | 9 | ₱578.2M | 76.9 | 2 | 88.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24A00673ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, AGOO-BAGUIO CITY ROAD - K0244 + 605 - K0247 + 435 (PACKAGE 05) | Region I | Region I | On-Going | ₱81.2M | 0% | High risk87 | Flagged0.083 |
| 25BK0088CONCRETING OF GAMIS - TRES REYES FMR, BRGY. GAMIS - TRES REYES, SAGUDAY, QUIRINO | Region II | Quirino DEO | Completed | ₱14.7M | 100% | High risk85 | Flagged0.013 |
| 21DK0060REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS, WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES, FAMY-REAL-INFANTA-DINAHICAN PORT ROAD, K0112+790-K0112+850, REAL, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱96.5M | 100% | High risk76 | —-0.029 |
| 21DK0059REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS, WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDES, FAMY-REAL-INFANTA-DINAHICAN PORT ROAD, K0112+730-K0112+790, REAL, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱96.5M | 100% | High risk76 | —-0.029 |
| 21DK0058REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS, WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDES, FAMY-REAL-INFANTA-DINAHICAN PORT ROAD, K0112+670-K0112+730, REAL, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱96.5M | 100% | High risk76 | —-0.029 |
| 20DK0085RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES ALONG MARIKINA-INFANTA ROAD (PACKAGE B) INFANTA, QUEZON, K0116+642-K0116+950 | Region IV-A | Quezon 1st DEO | Completed | ₱47.9M | 100% | High risk73 | —-0.037 |
| 20DK0084RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES ALONG MARIKINA-INFANTA ROAD (PACKAGE A) INFANTA, QUEZON, K0116+102-K0116+293 | Region IV-A | Quezon 1st DEO | Completed | ₱47.5M | 100% | High risk73 | —-0.038 |
| 20DK0086RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSEAND LANDSLIDES ALONG MARIKINA-INFANTA ROAD (PACKAGE C) INFANTA, QUEZON, K0117+308-K0177+680 | Region IV-A | Quezon 1st DEO | Completed | ₱48.8M | 100% | High risk72 | —-0.038 |
| 20DK0087RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES ALONG MARIKINA-INFANTA ROAD (PACKAGE D) INFANTA, QUEZON, K0118+230-K0118+500 | Region IV-A | Quezon 1st DEO | Completed | ₱48.6M | 100% | High risk72 | —-0.037 |
| 24A00674ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, AGOO-BAGUIO CITY ROAD - K0247 + 435 - K0250 + 265 (PACKAGE 06) | Region I | Region I | On-Going | ₱79.6M | 0% | High risk69 | Flagged0.062 |
| 23E00163SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF DIKE ALONG DULANGAN RIVER, SITIO BAYANAN, NAUJAN, OR. MINDORO | Region IV-B | Region IV-B | Completed | ₱241.2M | 100% | High risk68 | —-0.039 |
| 21D00007PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG CALUMPANG RIVER, BATANGAS | Region IV-A | Region IV-A | Completed | ₱143.9M | 100% | High risk68 | —-0.057 |
| 20P00043ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES SOOT BRIDGE (B00989LZ) ALONG ABRA - ILOCOS NORTE ROAD | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱530.8M | 100% | High risk67 | Flagged0.026 |
| 21D00008PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAMCONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG CALUMPANG RIVER, BATANGAS (PHASE II) | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk67 | —-0.055 |
| 23PA0106SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF DOLORES BRIDGE, CARDONA AND POBLACION, DOLORES, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱124.6M | 100% | High risk66 | —-0.031 |
| 18PA0095DREDGING / RECHANNELING OF ALONG POBLACION-MALABBAGA, LAPAZ, ABRA, LA PAZ, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱95.2M | 100% | High risk66 | —-0.052 |
| 21L00142ROCKFALL NETTING INCLUDING IMPROVEMENT OF CRITICAL INTERSECTION AT JCT. SHRINE HILLS ALONG DAVAO CITY DIVERSION ROAD, MATINA CROSSING, DAVAO CITY | Region XI | Region XI | Completed | ₱333.7M | 100% | High risk66 | —-0.047 |
| 18PA0096DREDGING / RECHANNELING OF ALONG SAN GREGORIO-CANAN, LAPAZ, ABRA, LA PAZ, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱95.4M | 100% | High risk65 | —-0.052 |
| 17B00024BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP)-DESIGN AND BUILD BRIDGES FOR LUZON, LA CONWAP BRIDGE AND APPROACHES PHASE 2 INCLUDING RIGHT OF WAY ACQUISITION ALONG JCT. ABBAG-GUINGIN BOUNDARY ROAD, QUIRINO | Region II | Region II | On-Going | ₱56.6M | 31% | High risk65 | Flagged0.048 |
| 17B00031BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) 1 DESIGN AND BUILD BRIDGES FOR LUZON, NGILINAN BRIDGE AND APPROACHES PHASE 2 INCLUDING RIGHT-OF-WAY ACQUISITION ALONG NRJ VILLA SUR-SAN PEDRO CABUAN-YSMAEL DISIMUNGAL, QURINO LONE DISTRICT, QUIRINO | Region II | Region II | Completed | ₱81.9M | 100% | High risk65 | Flagged0.001 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24A00673ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, AGOO-BAGUIO CITY ROAD - K0244 + 605 - K0247 + 435 (PACKAGE 05) | Region I | Region I | On-Going | ₱81.2M | 0% | High risk87 | Flagged0.083 |
| 24A00674ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, AGOO-BAGUIO CITY ROAD - K0247 + 435 - K0250 + 265 (PACKAGE 06) | Region I | Region I | On-Going | ₱79.6M | 0% | High risk69 | Flagged0.062 |
| 17B00024BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP)-DESIGN AND BUILD BRIDGES FOR LUZON, LA CONWAP BRIDGE AND APPROACHES PHASE 2 INCLUDING RIGHT OF WAY ACQUISITION ALONG JCT. ABBAG-GUINGIN BOUNDARY ROAD, QUIRINO | Region II | Region II | On-Going | ₱56.6M | 31% | High risk65 | Flagged0.048 |
| 20P00043ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES SOOT BRIDGE (B00989LZ) ALONG ABRA - ILOCOS NORTE ROAD | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱530.8M | 100% | High risk67 | Flagged0.026 |
| 24B00159DOH - FY 2024 HEALTH CARE FACILITIES ENHANCEMENT PROGRAM (HFEP): LGU HOSPITALS: LGU HOSPITALS - QUIRINO PROVINCIAL MEDICAL CENTER | Region II | Region II | On-Going | ₱9.8M | 0% | Medium risk43 | Flagged0.020 |
| 25BK0062BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - DECURABAN BR.1 (B03242LZ) ALONG CORDON - AURORA BDRY RD (JCT. DUMABATO - AURORA BDRY), NAGTIPUNAN, QUIRINO | Region II | Quirino DEO | On-Going | ₱30.3M | 0% | Medium risk59 | Flagged0.016 |
| 25BK0088CONCRETING OF GAMIS - TRES REYES FMR, BRGY. GAMIS - TRES REYES, SAGUDAY, QUIRINO | Region II | Quirino DEO | Completed | ₱14.7M | 100% | High risk85 | Flagged0.013 |
| 22P00014ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱287.4M | 61% | Medium risk57 | Flagged0.012 |
| 17B00031BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) 1 DESIGN AND BUILD BRIDGES FOR LUZON, NGILINAN BRIDGE AND APPROACHES PHASE 2 INCLUDING RIGHT-OF-WAY ACQUISITION ALONG NRJ VILLA SUR-SAN PEDRO CABUAN-YSMAEL DISIMUNGAL, QURINO LONE DISTRICT, QUIRINO | Region II | Region II | Completed | ₱81.9M | 100% | High risk65 | Flagged0.001 |
| 22PA0167SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MADEGNAC BRIDGE PHASE II-A, ALAOA, TINEG, ABRA | Cordillera Administrative Region | Abra DEO | On-Going | ₱46.5M | 99% | Medium risk51 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 301 | 18BK0044ASSET PRESERVATION PROGRAM - REHABILITATION/RECONCSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANSLIDE - TERTIARY ROAD JCT. ABBAG - GUINGIN BDRY. RD. K0392+900 - K0393+255, NAGTIPUNAN, QUIRINO | Region II | Quirino DEO | Completed | ₱53.1M | 100% | Medium risk49 | —-0.082 |
| 302 | 21NG0103CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG SURIGAO-AGUSAN WEST COASTAL ROAD STA. 44+170 - STA. 44+262.92, MALIMONO, SURIGAO DEL NORTE/MALIMONO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱92.7M | 100% | Medium risk48 | —-0.063 |
| 303 | 22BK0087BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES - ARFEL BR. ALONG ECHAGUE - JONES - MADDELA RD (VILLA NORTE PANANG SECT) MADDELA, QUIRINO | Region II | Quirino DEO | Completed | ₱49M | 100% | Medium risk48 | —-0.048 |
| 304 | 20HI0057CONCRETING/CONSTRUCTION/IMPROVEMENT/REHABILITATION OF LOCAL ROAD, BRGY. LANIPGA, CARMEN, CEBU | Region VII | Cebu 5th DEO | Completed | ₱14.1M | 100% | Medium risk46 | —-0.095 |
| 305 | 18BK0030BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - LACAB BRIDGE (B02080LZ) ALONG JCT. VICTORIA - MADDELA - ALICIA- KASIBU BDRY RD. (JCT. VICTORIA - KASIBU BDRY.) MADDELA, QUIRINO | Region II | Quirino DEO | Completed | ₱45.2M | 100% | Medium risk46 | —-0.043 |
| 306 | 21BK0023BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - DUMATATA BR. (B01938LZ) ALONG CORDON - AURORA BDRY RD (ISABELA BDRY - JCT DUMABATO) SAGUDAY, QUIRINO | Region II | Quirino DEO | Completed | ₱27.5M | 100% | Medium risk46 | —-0.048 |
| 307 | 23BK0093BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - PALLADAN BR. (B01943LZ) ALONG JCT. MANGANDINGAY - SAGUDAY - ISABELA BDRY RD, SAGUDAY, QUIRINO | Region II | Quirino DEO | Completed | ₱24.5M | 100% | Medium risk46 | —-0.048 |
| 308 | 21BK0022BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - DISINABA BR. (B04906LZ) ALONG CORDON - AURORA BDRY RD (ISABELA BDRY - JCT DUMABATO) DIFFUN, QURINO | Region II | Quirino DEO | Completed | ₱25.4M | 100% | Medium risk46 | —-0.048 |
| 309 | 21BK0021BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - LUKBAN BR. (B04905LZ) ALONG CORDON - AURORA BNDRY RD (ISABELA BDRY - JCT DUMABATO) DIFFUN, QUIRINO | Region II | Quirino DEO | Completed | ₱25.3M | 100% | Medium risk46 | —-0.048 |
| 310 | 19BK0073REPAIR/RESTORATION/IMPROVEMENT ALONG JCT. ABBAG - GUINGIN BDRY. ROAD (S04752LZ), K0392+770 - K0393+350, NAGTIPUNAN, QUIRINO | Region II | Quirino DEO | Completed | ₱41.1M | 100% | Medium risk46 | —-0.026 |
| 311 | 18BK0025BRIDGE PROGRAM REPLACEMENT OF PERMANENT WEAK BRIDGES DUMADITIM BR. (B01933LZ) ALONG CORDON-AURORA BDRY. RD. (ISABELA BDRY-JCT DUMABATO), DIFFUN, QUIRINO | Region II | Quirino DEO | Completed | ₱45.2M | 100% | Medium risk46 | —-0.048 |
| 312 | 21NG0097CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG SURIGAO-AGUSAN WEST COASTAL ROAD - STA.19+547.54 - STA.19+590, STA.28+930 - STA.29+020, SURIGAO DEL NORTE/SAN FRANCISCO, SURIGAO DEL NORTE, MALIMONO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱78.7M | 100% | Medium risk45 | —-0.069 |
| 313 | 21NG0106CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG SURIGAO-AGUSAN WEST COASTAL ROAD STA. 39+780 - STA. 39+904.38, MALIMONO, SURIGAO DEL NORTE/MALIMONO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱88M | 100% | Medium risk45 | —-0.065 |
| 314 | 21NG0096CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG CAPALAYAN-PLACER ROAD STA.7+090 - STA.7+190 / PLACER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱83.4M | 100% | Medium risk45 | —-0.065 |
| 315 | 19PA0126CONCRETING OF SITIO GRAVELINAS-SITIO TIBTIBING, BARANGAY NAMARABAR FMR, BARANGAY NAMARABAR PENARUBIA, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱5M | 100% | Medium risk45 | —-0.029 |
| 316 | 20NG0061REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SURIGAO-DAVAO COASTAL ROAD, BACUAG SECTION / BRGY. POB., BACUAG, SURIGAO DEL NORTE, K1161+011 - K1161+238 | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱66.4M | 100% | Medium risk44 | —-0.085 |
| 317 | 18BK0052ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS ALONG JCT. VICTORIA - MADDELA - ALICIA - KASIBU BDRY. RD. (JCT. VICTORIA - KASIBU BDRY.) K0368+540 - K0368+565, K0380+755 - K0380+ | Region II | Quirino DEO | Completed | ₱43.1M | 100% | Medium risk44 | —-0.084 |
| 318 | 20PA0109CONCRETING OF BARANGAY TIKITIK FMR, PILAR, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱11.9M | 100% | Medium risk43 | —-0.032 |
| 319 | 20BK0059ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF NATIONA ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - JCT VICTORIA - MADDELA-ALICIA-KASIBU BDRY RD (JCT VICTORIA-KASIBU BDRY) - K0363+555 - K0363+605, K0375+765-K0375+790, K0382+5 | Region II | Quirino DEO | Completed | ₱26.7M | 100% | Medium risk43 | —-0.085 |
| 320 | 20PA0110CONCRETING OF BARANGAY DINTAN FMR, PILAR, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱11.9M | 100% | Medium risk43 | —-0.032 |
| 321 | 20NG0060REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SURIGAO-DAVAO COASTAL ROAD, HAYANGGABON SECTION/BRGY. HAYANGGABON, CLAVER, SURIGAO DEL NORTE, K1195+570 - K1195+747 | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱82.5M | 100% | Medium risk43 | —-0.076 |
| 322 | 20NG0080REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SURIGAO-DAVAO COASTAL ROAD CAGDIANAO SECTION/ BRGY. CAGDIANAO, CLAVER, SURIGAO DEL NORTE K1195+867 - K1196+085 | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱81.4M | 100% | Medium risk43 | —-0.076 |
| 323 | 24B00159DOH - FY 2024 HEALTH CARE FACILITIES ENHANCEMENT PROGRAM (HFEP): LGU HOSPITALS: LGU HOSPITALS - QUIRINO PROVINCIAL MEDICAL CENTER | Region II | Region II | On-Going | ₱9.8M | 0% | Medium risk43 | Flagged0.020 |
| 324 | 17BK0205CONSTRUCTION OF FOUR-STOREY SIXTEEN CLASSROOM SCHOOL BUILDING CABARROGUIS NSAT, CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱39M | 100% | Medium risk43 | —-0.015 |
| 325 | 16BK0155CONSTRUCTION/EXPANSION OF PEDIATRIC WARD AND DIALYSIS BUILDING, QUIRINO PROVINCIAL HOSPITAL (QUIRINO MEDICAL CENTER) CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱29.9M | 100% | Medium risk42 | —-0.018 |