60 projects on file, including joint ventures this contractor is part of.
Total projects
60
Total budget
₱298.6M
Average progress
98.1%
Completion rate
88.3%
Average risk score
38.7
Medium risk on average, out of 100
Flagged as unusual
1
1.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 60 | ₱298.6M | 38.7 | 1 | 98.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 32 | ₱138.9M | 34.6 | 0 | 100.0% |
| Roads | 18 | ₱110.9M | 41.5 | 0 | 96.2% |
| Water Provision and Storage | 4 | ₱19.5M | 33.8 | 0 | 100.0% |
| OTHER | 3 | ₱19.4M | 80.4 | 1 | 85.5% |
| Flood Control and Drainage | 3 | ₱9.8M | 30.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23FF0099CONSTRUCTION OF MULTI PURPOSE BUILDING,TINAGO HIGH SCHOOL BRGY. TINAGO NAGA CITY CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱4.8M | 60% | High risk87 | Flagged0.050 |
| 24FF0070CONST. OF MULTI PURPOSE FACILITY,BRGY. TABUCO NAGA CITY CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱4.9M | 96% | High risk78 | —-0.010 |
| 23FF0083CONSTRUCTION /REHAB. OF WATER SUPPLY SEPTAGE & SEWERAGE/RAIN WATER COLLECTORS WATER SUPPLY SYSTEM-CONST. OF SOLAR WATER SYSTEM BRGY. CABARIWAN ,OCAMPO CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱9.7M | 100% | High risk77 | —-0.004 |
| 17FE0042ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE, COLLAPSE AND LANDSLIDE-TERTIARY ROAD, MANGUIRING-CAGSAO-CABANBANAN ROAD | Region V | Camarines Sur 3rd DEO | Completed | ₱9.6M | 100% | High risk65 | —-0.065 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 23FF0099CONSTRUCTION OF MULTI PURPOSE BUILDING,TINAGO HIGH SCHOOL BRGY. TINAGO NAGA CITY CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱4.8M | 60% | High risk87 | Flagged0.050 |
| 2 | 24FF0070CONST. OF MULTI PURPOSE FACILITY,BRGY. TABUCO NAGA CITY CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱4.9M | 96% | High risk78 | —-0.010 |
| 3 | 23FF0083CONSTRUCTION /REHAB. OF WATER SUPPLY SEPTAGE & SEWERAGE/RAIN WATER COLLECTORS WATER SUPPLY SYSTEM-CONST. OF SOLAR WATER SYSTEM BRGY. CABARIWAN ,OCAMPO CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱9.7M | 100% | High risk77 | —-0.004 |
| 4 | 17FE0042ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE, COLLAPSE AND LANDSLIDE-TERTIARY ROAD, MANGUIRING-CAGSAO-CABANBANAN ROAD | Region V | Camarines Sur 3rd DEO | Completed | ₱9.6M | 100% | High risk65 | —-0.065 |
| 5 | 24FF0064BIP;PUBLIC WATER SUPPLY SYSTEM-CONST. OF PUBLIC WATER SUPPLY SYSTEM(WATER SUPPLY/SEPTAGE & SEWERAGE-RAINWATER COLLECTORS) CAWADI, BRGY. PAOLBO CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱9.6M | 100% | Medium risk52 | —-0.034 |
| 6 | 22FN0044CONSTRUCTION OF ROAD INCLUDING DRAINAGE STRUCTURE FROM STA. CLARA - SAGRADA PITO BUHI, CAMARINES SUR | Region V | Camarines Sur 5th DEO | Completed | ₱14.7M | 100% | Medium risk52 | —-0.100 |
| 7 | 21FF0035CONCRETING OF ROAD SITIO TAWANG ZONE 7, BRGY. FABRICA CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱9.9M | 100% | Medium risk51 | —-0.100 |
| 8 | 20FF0068CONSTRUCTION OF BARANGAY ROAD BRGY. FABRICA CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱5.5M | 100% | Medium risk51 | —-0.101 |
| 9 | 23FF0082CONSTRUCTION OF BARAS ACCESS ROAD WITH SLOPE PROTECTION,BRGY. BARAS CANAMAN CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.101 |
| 10 | 22FF0046BIP;ACCESS ROAD &/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING INDIGENEOUS PEOPLE (IP) COMMUNITIES CONSTINUATION OF ACCESS ROAD,BRGY. LINAGA CANAMAN CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.094 |
| 11 | 23FF0021BIP;ACCESS ROAD &/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING FACILITIES-CONST OF ACCESS ROAD SAN FRANCISCO CANAMAN CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.097 |
| 12 | 23FF0039BIP;ACESS ROADS&/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST OF BRGY. ROAD,ZONE 1 SAN ROQUE CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱4.9M | 32% | Medium risk51 | —-0.040 |
| 13 | 24FF0052BIP;ACCESS ROADS &/OR BRIDGES FROM THE NATL. ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES CONST. OF ACCESS ROAD, BRGY. PINIT OCAMPO CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱7.7M | 100% | Medium risk51 | —-0.099 |
| 14 | 24FF0061CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT),BRGY GUINABAN OCAMPO CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.099 |
| 15 | 24FF0014CONST. OF MULTI PURPOSE BUILDING(3RD DISTRICT OFFICE) BARANGAY BALATAS NAGA CITY | Region V | Camarines Sur 3rd DEO | Completed | ₱9.6M | 100% | Medium risk48 | —-0.099 |
| 16 | 24FF0051CONSTRUCTION OF MULTI PURPOSE BUILDING (PANICUASON ELEM. SCHOOL) PANICUASON NAGA CITY CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.099 |
| 17 | 24FF0060CONST. OF MULTI PURPOSE BUILDING ,ALS LEARNING CENTER, CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱4.9M | 100% | Medium risk48 | —-0.062 |
| 18 | 22FF0054BIP:FLOOD MITIGATION STRUCTURE PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES, CONST. OF FLOOD MITIGATION STRUCTURE BRGY. BAGONG SIRANG PILI CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.084 |
| 19 | 22FF0027CONSTRUCTION OF EVACUATION CENTER SITIO CABOCLODAN BARANGAY SAN JOSE PILI CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.099 |
| 20 | 20FF0029CONSTRUCTION OF MULTI-PURPOSE BUILDING, THIRIS, STA.LUCIA, MAGARAO, CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.099 |
| 21 | 22FF0079CONSTRUCTION OF MULTI PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES,(PNP STATION 2 BUILDING) ALMEDA HIGHWAY BRGY. CONCEPCION PEQUENA NAGA CITY CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.099 |
| 22 | 22FF0070CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT), BRGY. LINAGA CANAMAN CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.099 |
| 23 | 24FF0033CONSTRUCTION OF MULTI PURPOSE BUILDING(COVERED COURT) JOSE C. PREVOSA SR. HIGH SCHOOL ) FORMERLY UNION NATIONAL HIGH SCHOOL) BRGY. STO DOMINGO CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱4.9M | 100% | Medium risk47 | —-0.061 |
| 24 | 22FF0074CONSTRUCTION OF MULTI PURPOSE BUILDING, CALABANGA COMMUNITY COLLEGE, CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.099 |
| 25 | 22FF0025CONSTRUCTION OF MULTI PURPOSE BUILDING,NAGA CENTRAL SCHOOL II,NAGA CITY CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.099 |