Opening the dossier…
Opening the dossier…
Contractor dossier
251 projects on file, including joint ventures this contractor is part of.
Total projects
251
Total budget
₱6B
Average progress
95.4%
Completion rate
85.3%
Average risk score
42.8
Medium risk on average, out of 100
Flagged as unusual
5
2.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 220 | ₱5.1B | 43.0 | 3 | 95.0% |
| National Capital Region | 18 | ₱498.3M | 42.0 | 0 | 100.0% |
| Region III | 6 | ₱277.7M | 35.8 | 0 | 100.0% |
| Region I | 3 | ₱88.5M | 47.1 | 0 | 100.0% |
| Region V | 2 | ₱55.4M | 53.6 | 2 | 77.5% |
| Region IV-B | 1 | ₱9.2M | 31.7 | 0 | 100.0% |
| Region VI | 1 | ₱951.1K | 19.6 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 147 | ₱2.6B | 38.9 | 2 | 96.6% |
| Roads | 58 | ₱1.7B | 45.8 | 1 | 94.7% |
| Flood Control and Drainage | 26 | ₱1.5B | 50.5 | 0 | 91.0% |
| OTHER | 7 | ₱214.7M | 66.2 | 1 | 92.9% |
| Water Provision and Storage | 7 | ₱21.6M | 30.1 | 0 | 99.0% |
| Bridges | 3 | ₱13M | 31.5 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱48M | 95.2 | 1 | 45.6% |
| GAA 2025 OO-1 | 1 | ₱5.8M | 90.1 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱14.3M | 88.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DH0070CONSTRUCTION OF MULTI-PURPOSE BUILDING, BUILDING 1, PILA, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱48M | 46% | High risk95 | Flagged0.010 |
| 25DH0008ROAD WIDENING-PRIMARY ROADS-CALAMBA-STA. CRUZ-FAMY JCT RD-K0084+723-K0084+794, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱5.8M | 100% | High risk90 | —-0.015 |
| 25DH0015CONSTRUCTION OF FLOOD CONTROL STRUCTURE (TUNGKOD RIVER), PAAGAHAN CIS, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱14.3M | 100% | High risk88 | —-0.033 |
| 24DI0158REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0068 + (-282) - K0069 + 098 | Region IV-A | Laguna 2nd DEO | On-Going | ₱120.5M | 50% | High risk75 | Flagged0.011 |
| 24DH0080CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT) FOR BRGY. SARAY, PAKIL, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱8.7M | 100% | High risk73 | —-0.014 |
| 20DI0139CONSTRUCTION OF MULTI-PURPOSE BUILDING, WOMEN'S DEVELOPMENT CENTER, CABUYAO, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱9.6M | 100% | High risk72 | —-0.015 |
| 21DI0071OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - BAY POBLACION RD - K0067 + 188 - K0067 + 570 | Region IV-A | Laguna 2nd DEO | Completed | ₱14M | 100% | High risk70 | —-0.038 |
| 21DI0076ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - MT. MAKILING ECO GARDEN RD. - K0064+080 - K0064+300, K0064+330 - K0064+440, K0064+500 - K0064+664, K0065+195 - K006 | Region IV-A | Laguna 2nd DEO | Completed | ₱51.2M | 100% | High risk70 | —-0.043 |
| 18DI0078LIP - LOCAL ROADS AND BRIDGES - LOCAL ROADS -CONSTRUCTION OF ROAD, SIDEWALK, CURVES/ GUTTER AND DRAINAGE OF BRGY. PULONG SANTA CRUZ LEADING TO INDUSTRIAL AREAS AND RELOCATION SITES (23MX6MX300M, 24 RCP), BRGY. PULONG STA. CRUZ, SANTA ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱14.9M | 100% | High risk68 | —-0.041 |
| 25DI0064CONSTRUCTION OF REVETMENT ALONG MAYAPA WATERWAYS (SITIO RIVERSIDE) CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.7M | 26% | High risk65 | —-0.025 |
| 25DI0065CONSTRUCTION OF STRUCTURE FOR RIVER PROTECTION AT SAN CRISTOBAL RIVER, BRGY. PACIANO, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.7M | 76% | High risk65 | —-0.039 |
| 25DI0017CONSTRUCTION OF RIVER PROTECTION STRUCTURE, NEAR SAMPIRUHAN, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94M | 75% | High risk65 | —-0.037 |
| 20D00057CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION/IMPROVEMENT OF TRIBUTARY CREEK AS OUTFALL OF THE DETENTION POND AT BRGY. MAMPLASAN LEADING TO CARMONA-BIÑAN RIVER, BIÑAN CITY, LAGUNA | Region IV-A | Region IV-A | Completed | ₱115.7M | 100% | High risk65 | —-0.074 |
| 23DD0310CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, DOH REGION IV-A OFFICE, LIPA CITY | Region IV-A | Batangas 4th DEO | Completed | ₱144.1M | 100% | High risk65 | —-0.074 |
| 25DI0066CONSTRUCTION OF STRUCTURE FOR RIVER PROTECTION ALONG SAN JUAN RIVER, BARANDAL SIDE (NEAR HOLY GARDENS), CALAMBA CITY, LAGUNA PHASE 1 | Region IV-A | Laguna 2nd DEO | On-Going | ₱97.1M | 0% | High risk64 | —-0.018 |
| 24DH0040CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ROMELO RIVER, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.075 |
| 24DH0029CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INAWASAN RIVER, FAMY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.078 |
| 23DD0188ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT ALONG MALAKING ILOG RIVER (LIPAHAN SECTION), SA | Region IV-A | Batangas 4th DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.077 |
| 23DD0227ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT ALONG MALAKING ILOG RIVER (TIPAZ SECTION), SAN | Region IV-A | Batangas 4th DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.078 |
| 23DH0079CONSTRUCTION OF MULTI-PURPOSE BUILDING, PILA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱94.3M | 100% | High risk63 | —-0.084 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DD0283LOCALLY-FUNDED PROJECTS, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES, CONSTRUCTION OF DEPARTMENT OF HEALTH REGION 4A REGIONAL OFFICE MARAWOY, LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱140.4M | 12% | High risk63 | Flagged0.038 |
| 24DI0158REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0068 + (-282) - K0069 + 098 | Region IV-A | Laguna 2nd DEO | On-Going | ₱120.5M | 50% | High risk75 | Flagged0.011 |
| 25DH0070CONSTRUCTION OF MULTI-PURPOSE BUILDING, BUILDING 1, PILA, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱48M | 46% | High risk95 | Flagged0.010 |
| 23F00420CONVERGENCE AND SPECIAL SUPPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD AT MARAMBONG, PANDAN, CA | Region V | Region V | On-Going | ₱46.8M | 97% | Medium risk59 | Flagged0.003 |
| 24F00438CAPITAL OUTLAY-DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-LGU HOSPITALS-GIGMOTO DISTRICT HOSPITAL, CATANDUANES, GIGMOTO, CATANDUANES (LONE DISTRICT) | Region V | Region V | On-Going | ₱8.6M | 58% | Medium risk48 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 176 | 17OD0167CONSTRUCTION OF 4-STOREY 20-CLASSROOM SCHOOL BUILDING MAYSAN ES, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱44.6M | 100% | Medium risk35 | —-0.015 |
| 177 | 19CC0068CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER PULILAN SECTION PHASE II PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱74.8M | 100% | Medium risk35 | —-0.086 |
| 178 | 19CC0067CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER PULILAN SECTION PHASE I PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱74M | 100% | Medium risk35 | —-0.086 |
| 179 | 17OD0138CONSTRUCTION OF 4-STOREY 8-CLASSROOM SCHOOL BUILDING MAYSAN ES, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱18.5M | 100% | Medium risk34 | —-0.020 |
| 180 | 18CF0126IMPROVEMENT/REHABILITATION OF SENIOR CITIZENS BUILDING, BRGY. KAPITAN PEPE, CABANATUAN CITY | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.8M | 100% | Medium risk32 | —-0.107 |
| 181 | 18CE0136CONSTRUCTION OF SENIOR CITIZEN BUILDING, BRGY. POBLACION EAST, ALIAGA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱9.6M | 100% | Medium risk32 | —-0.106 |
| 182 | 18EA0191PACKAGE 49 - A) CONCRETING OF BRGY. SUHA FARM TO MARKET ROAD, BRGY. SUHA, B) CONCRETING OF BRGY. MARANLIG FARM TO MARKET ROAD, BRGY. MARANLIG | Region IV-B | Marinduque DEO | Completed | ₱9.2M | 100% | Medium risk32 | —-0.041 |
| 183 | 18CC0339CONSTRUCTION OF TWO STOREY SIX CLASSROOM - BALAGTAS CENTRAL SCHOOL BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱15.4M | 100% | Low risk29 | —-0.053 |
| 184 | 25DD0056CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PINAGSIBAAN ELEMENTARY SCHOOL, BARANGAY PINAGSIBAAN, ROSARIO, | Region IV-A | Batangas 4th DEO | On-Going | ₱3.8M | 100% | Low risk26 | —-0.072 |
| 185 | 20DH0024CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. CABOOAN, STA. MARIA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.6M | 100% | Low risk26 | —-0.104 |
| 186 | 19DI0017BRIDGE PROGRAM -RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES -ANOS BR. (B02507LZ) ALONG CALAMBA- STA. CRUZ- FAMY JCT RD., LOS BAÑOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱3.8M | 100% | Low risk26 | —-0.066 |
| 187 | 21DG0040CONST OF MPB-CONST (COMPLETION) OF MPB (COVERED COURT), BAGONG KALSADA, NAIC, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱3.9M | 100% | Low risk26 | —-0.103 |
| 188 | 18DI0120LIP- BUILDINGS AND OTHER STRUCTURES-CONSTRUCTION OF A MULTI- PURPOSE BUILDING, PDEA REGIONAL OFFICE IV - A, STA. ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱2.9M | 100% | Low risk26 | —-0.104 |
| 189 | 20OI0136REHABILITATION OF ROAD INCLUDING DRAINAGE, BRGY. PAMPLONA 2, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱3.9M | 100% | Low risk26 | —-0.096 |
| 190 | 21DI0079CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY DIEZMO, CABUYAO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.102 |
| 191 | 24DH0093CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM (7 UNITS) 1)BUBUKAL ELEMENTARY SCHOOL, SANTA CRUZ, LAGUNA2)DUHAT ELEMENTARY SCHOOL, SANTA CRUZ, LAGUNA3)PATIMBAO ELEMENTARY SCHOOL, SANTA CRUZ, LAGUNA4)SANTA | Region IV-A | Laguna 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.070 |
| 192 | 20DH0098CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS SYSTEM | Region IV-A | Laguna 1st DEO | Completed | ₱4M | 100% | Low risk25 | —-0.067 |
| 193 | 20DH0068CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI PURPOSE BUILDING, BRGY. BAGOONG POOK, STA. MARIA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.105 |
| 194 | 20DH0079CONCRETING/CONSTRUCTION OF LOCAL ROAD, SITIO BAGONG LIPUNAN, BRGY. DUHAT, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱3.9M | 100% | Low risk25 | —-0.107 |
| 195 | 21DH0070CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL) (PHASE 2), PILA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱3.9M | 100% | Low risk25 | —-0.104 |
| 196 | 18DD0130LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, REHABILITATION/ IMPROVEMENT OF BARANGAY GYM AT BARANGAY RIZAL, LIPA, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱1.9M | 100% | Low risk25 | —-0.103 |
| 197 | 25DD0182CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION/COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MARAWOY, LIPA CITY BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱2.9M | 100% | Low risk25 | —-0.076 |
| 198 | 21DI0054REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GULOD, CABUYAO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱3M | 100% | Low risk25 | —-0.102 |
| 199 | 19DD0384LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, REHABILITATION/ IMPROVEMENT OF MULTI-PURPOSE FACILITIES AT RAFAEL M. LOJO MEMORI | Region IV-A | Batangas 4th DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.105 |
| 200 | 19DH0094CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS SYSTEM | Region IV-A | Laguna 1st DEO | Completed | ₱3.6M | 100% | Low risk25 | —-0.067 |