Contractor dossier
82 projects on file, including joint ventures this contractor is part of.
Total projects
82
Total budget
₱11.5B
Average progress
96.2%
Completion rate
85.4%
Average risk score
57.0
Medium risk on average, out of 100
Flagged as unusual
6
7.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 18 | ₱2.6B | 60.6 | 1 | 96.8% |
| Region X | 18 | ₱2.9B | 58.6 | 1 | 100.0% |
| Region VIII | 12 | ₱1.1B | 54.5 | 1 | 99.7% |
| Region XIII | 11 | ₱729M | 48.0 | 0 | 100.0% |
| Region IV-A | 8 | ₱798.2M | 53.8 | 1 | 81.3% |
| Region IV-B | 5 | ₱580.9M | 53.6 | 0 | 100.0% |
| National Capital Region | 4 | ₱1.6B | 68.1 | 2 | 74.0% |
| Region VII | 2 | ₱593.6M | 63.5 | 0 | 100.0% |
| Region III | 2 | ₱311M | 54.3 | 0 | 100.0% |
| Central Office | 1 | ₱187.5M | 76.6 | 0 | 100.0% |
| Cordillera Administrative Region | 1 | ₱141.8M | 62.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 46 | ₱5.9B | 54.5 | 2 | 97.5% |
| Flood Control and Drainage | 16 | ₱2.6B | 58.4 | 2 | 90.4% |
| Bridges | 9 | ₱889.2M | 55.8 | 1 | 100.0% |
| Bridges, Roads | 7 | ₱1.1B | 64.4 | 1 | 93.3% |
| OTHER | 2 | ₱288.7M | 76.8 | 0 | 100.0% |
| Buildings and Facilities | 2 | ₱688.3M | 63.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17N00079COMPLETION OF THE EAST-WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/AGUSAN DEL NORTE TO BUKIDNON SAMPAGUITA - MAKILOS (AGUSAN DEL SUR/BUKIDNON BOUNDARY, INCLUDING BRIDGE, AGUSAN DEL SUR 2ND LD, PACKAGE 2, AGUSAN DEL SUR | Region XIII | Region XIII | Completed | ₱144M | 100% | High risk77 | —-0.002 |
| 18C00052DREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGA | Central Office | Flood Control Management Cluster | Completed | ₱187.5M | 100% | High risk77 | —-0.034 |
| 17N00081COMPLETION OF THE EAST-WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/AGUSAN DEL NORTE TO BUKIDNON SAMPAGUITA-MAKILOS (AGUSAN DEL SUR/BUKINON BOUNDARY INCLUDING BRIDGE, AGUSAN DEL SUR 2ND LD, PACKAGE 4, AGUSAN DEL SUR | Region XIII | Region XIII | Completed | ₱144.7M | 100% | High risk76 | —-0.002 |
| 20O00105CONSTRUCTION OF DRAINAGE SYSTEM/OUTFALL EXTENSION AT MANILA BAY | National Capital Region | National Capital Region | On-Going | ₱258.6M | 77% | High risk74 | Flagged0.057 |
| 18L00187CONSTRUCTION OF GRAVEL ROAD-MAWAB-MARAGUSAN-CARAGA ROAD, PACKAGE B, INCLUDING ROW, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱142.7M | 53% | High risk68 | Flagged0.020 |
| 23D00198CONSTRUCTION OF FLOOD CONTROL ANDBANK PROTECTION STRUCTURES ALONGLUKUTANG MALAKI RIVER, BARANGAY SANISIDRO, RODRIGUEZ, RIZAL - PACKAGE 1 | Region IV-A | Region IV-A | On-Going | ₱190.1M | 81% | High risk67 | —-0.008 |
| 18L00139BUKIDNON-COMPOSTELA VALLEY RD (BRGY. NAMNAM,SAN FERNANDO,BUKIDNON-LAAK,COMPOSTELA VALLEY),PACKAGE 5, | Region XI | Region XI | Completed | ₱282.2M | 100% | High risk67 | —-0.019 |
| 21O00104ORGANIZATIONAL OUTCOME 2 PROTECT LIVES AND PROPERTIES AGAINST FLOOD: CONSTRUCTION OF MAYTUNAS PUMPING STATION AND IMPROVEMENT OF MAYTUNAS CREEK AND ITS VICINITY, MANDALUYONG CITY | National Capital Region | National Capital Region | On-Going | ₱519.4M | 19% | High risk67 | Flagged0.024 |
| 18O00021ORGANIZATIONAL OUTCOME 2 - PROTECT LIVES AND PROPERTIES AGAINST FLOODS: IMPROVEMENT OF WATERWAYS/RETARDING PONDS OF PUMPING STATIONS AT WEST OF MANGGAHAN FLOODWAY, C-6 ROAD, WEST MANGGAHAN RD., TAGUIG CITY, METRO MANILA | National Capital Region | National Capital Region | Completed | ₱596.9M | 100% | High risk67 | —-0.033 |
| 23D00200CONSTRUCTION OF FLOOD CONTROL AND SLOPE PROTECTION STRUCTURES ALONG LUKUTANG MALAKI RIVER, BARANGAY SAN ISIDRO, RODRIGUEZ, RIZAL PACKAGE 3 | Region IV-A | Region IV-A | On-Going | ₱192.2M | 69% | High risk67 | —-0.002 |
| 19L00112CONST. OF GRAVEL ROAD-ISLAND GARDEN CITY OF SAMAL (IGACOS) CIRC. ROAD, (PACKAGE B), DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱125.5M | 100% | High risk66 | —-0.036 |
| 19L00173CONSTRUCTION OF CONCRETE ROAD-MAWAB-MARAGUSAN-CARAGA ROAD, SECTION 2, PACKAGE D, COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱102.2M | 100% | High risk66 | —-0.024 |
| 17K00352CLUSTER B CONST. OF MISSING GAPS CONNECTING NATL ROADS INCL. ROW IN BUKIDNON | Region X | Region X | Completed | ₱272.2M | 100% | High risk65 | —-0.014 |
| 18IL0010CONSTRUCTION OF CONCRETE BRIDGE, LILOAN-SAN RICARDO CIRCUMFERENTIAL ROAD, VIADUCT, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱168.9M | 100% | High risk65 | —-0.014 |
| 23D00201CONSTRUCTION OF PARAWAGAN ROAD INCLUDING DRAINAGE SYSTEMS AND SLOPE PROTECTION STRUCTURES AT BRGY SAN RAFAEL, MONTALBAN, RIZAL (PACKAGE 2) | Region IV-A | Region IV-A | On-Going | ₱292.5M | 0% | High risk65 | Flagged0.004 |
| 18L00186ROAD WIDENING-MAWAB-MACO BYPASS ROAD, INCLUDING ROW, COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱142.1M | 100% | High risk64 | —-0.062 |
| 18L00009CONCRETING OF MAWAB-MARAGUSAN-CARAGA ROAD (SECTION 2), PACKAGE A, INCLUDING ROW, COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱179.8M | 100% | High risk64 | —-0.039 |
| 18K00223CLUSTER 19 CONST./REHAB. OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS&PRINCIPAL RIVERS BUK | Region X | Region X | Completed | ₱174M | 100% | High risk64 | —-0.045 |
| 21O00100PROPOSED MANILA BAY REHABILITATION PROGRAM (BEACH NOURISHMENT, COASTAL RESTORATION AND ENHANCEMENT OF MANILA BAYWALK AREA) PHASE II | National Capital Region | National Capital Region | Completed | ₱263.6M | 100% | High risk64 | —-0.013 |
| 18H00038CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS -PILIPOG-GABI (ROCK CAUSEWAY) COASTAL ROAD LEADING TO GILUTONGAN MARINE SANCTUARY, NALUSUAN MARINE SANTUARY, HOTELS & RESORT, BRGY. | Region VII | Region VII | Completed | ₱168.9M | 100% | High risk64 | —-0.050 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20O00105CONSTRUCTION OF DRAINAGE SYSTEM/OUTFALL EXTENSION AT MANILA BAY | National Capital Region | National Capital Region | On-Going | ₱258.6M | 77% | High risk74 | Flagged0.057 |
| 17KA0220CONSTRUCTION OF PULANGUI BRIDGE AND APPROACHES, SITIO MAHAN-AWIMPASUG-ONG, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱105.4M | 100% | Medium risk53 | Flagged0.027 |
| 21O00104ORGANIZATIONAL OUTCOME 2 PROTECT LIVES AND PROPERTIES AGAINST FLOOD: CONSTRUCTION OF MAYTUNAS PUMPING STATION AND IMPROVEMENT OF MAYTUNAS CREEK AND ITS VICINITY, MANDALUYONG CITY | National Capital Region | National Capital Region | On-Going | ₱519.4M | 19% | High risk67 | Flagged0.024 |
| 18L00187CONSTRUCTION OF GRAVEL ROAD-MAWAB-MARAGUSAN-CARAGA ROAD, PACKAGE B, INCLUDING ROW, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱142.7M | 53% | High risk68 | Flagged0.020 |
| 17IH0001REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG CATARMAN-CALBAYOG ROAD, K0753+216-K0753+319, CATARMAN, N. SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱47.9M | 97% | High risk60 | Flagged0.009 |
| 23D00201CONSTRUCTION OF PARAWAGAN ROAD INCLUDING DRAINAGE SYSTEMS AND SLOPE PROTECTION STRUCTURES AT BRGY SAN RAFAEL, MONTALBAN, RIZAL (PACKAGE 2) | Region IV-A | Region IV-A | On-Going | ₱292.5M | 0% | High risk65 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 18P00015ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINK/ NEW ROADS- ASIN-NANGALISAN JCT.-BAYABAS-MONGLO JCT. (SECTION 1 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD) INCLUDING ROW AND BRIDGE | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱141.8M | 100% | High risk63 | —-0.020 |
| 27 | 19L00111CONST. OF CONCRETE ROAD-ISLAND GARDEN CITY OF SAMAL (IGACOS) CIRC. ROAD,(PACKAGE A), DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱125.4M | 100% | High risk63 | —-0.060 |
| 28 | 18KA0050CLUSTER 2 - A. CONST. OF KULAMAN BRIDGE AND APPROACHES,KULAMAN, MALAYBALAY CITY, BUKIDNONB. CONST. OF MALUSIKOB BRIDGE AND APPROACHES,MAPULO, MALAYBALAY CITY, BUKIDNONC. CONST. OF MANGAWAG BRIDGE AND APPROACHES,CABURACANAN, MALAYBALAY CITY, BUKI | Region X | Bukidnon 1st DEO | Completed | ₱174.3M | 100% | High risk62 | —-0.026 |
| 29 | 18K00200CLUSTER 3 CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BUKIDNON | Region X | Region X | Completed | ₱276.4M | 100% | High risk62 | —-0.050 |
| 30 | 18K00147CONST. OF MISSING LINKS/NEW ROADS, COMPLETION OF THE EAST-WEST LATERAL ROAD CONNECTING AGUSAN DEL SU | Region X | Region X | Completed | ₱164.5M | 100% | High risk62 | —-0.065 |
| 31 | 18KA0049CLUSTER 1 - A. CONCRETING OF MALAYBALAY - GINGOOG ROAD,BUSDI SECTION, BUSDI, MALAYBALAY CITYB.CONCRETING OF MALAYBALAY- GINGOOG ROAD,CABURACANAN SECTION, CABURACANAN, MALAYBALAY CITYC. CONCRETING OF MALAYBALAY - GINGOOG ROAD,KULAMAN SECTION, KUL | Region X | Bukidnon 1st DEO | Completed | ₱194.8M | 100% | High risk62 | —-0.056 |
| 32 | 18K00224CLUSTER 20 CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BUKIDNON | Region X | Region X | Completed | ₱457.9M | 100% | High risk61 | —-0.039 |
| 33 | 17I00037ASSET PRESERVATION OF NAT'L. ROADS,REHAB./ RECONST. OF NAT'L. ROADS WITH SLIPS,SLOPE COLLAPSE & LANDSLIDE-PRIMARY CONST. OF ROAD SLOPE PROTECTION STRUCTURE-DAANG MAHARLIKA (SM) (SAN ISIDRO-SAN JUANICO BRIDGE)- KO691+020-KO691...,CALBAYOG CITY,SAMAR 1ST LD | Region VIII | Region VIII | Completed | ₱234.5M | 100% | High risk61 | —-0.016 |
| 34 | 17IH0001REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG CATARMAN-CALBAYOG ROAD, K0753+216-K0753+319, CATARMAN, N. SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱47.9M | 97% | High risk60 | Flagged0.009 |
| 35 | 19K00089CONSTRUCTION OF MISSING LINKS/NEW ROADS, JCT. MARAMAG-MARADUGAO ROAD-JCT. LAMPANUSAN ROAD, PACKAGE 5, BUKIDNON | Region X | Region X | Completed | ₱139M | 100% | High risk60 | —-0.072 |
| 36 | 18E00019ROAD WIDENING OF PTO. PRINCESA NORTH ROAD FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE, KO096+253 TO KO097+766; KO098+000 TO KO098+787, ROXAS, PALAWAN | Region IV-B | Region IV-B | Completed | ₱184.5M | 100% | Medium risk60 | —-0.026 |
| 37 | 19K00121CONSTRUCTION OF MISSING LINKS/NEW ROADS, EAST-WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/AGUSAN DEL NORTE TO BUKIDNON, DAMAY-CALABUGAO-ADTOLAWON ROAD, PACKAGE 16, BUKIDNON | Region X | Region X | Completed | ₱139M | 100% | Medium risk60 | —-0.054 |
| 38 | 18E00027CONST. OF MISSING LINKS/NEW ROADS - PALAWAN CIRCUMFERENTIAL ROAD (LATUD-CANIPAAN SECTION), PACKAGE A, KO276+000.00 TO KO286+480.00, PALAWAN | Region IV-B | Region IV-B | Completed | ₱143.4M | 100% | Medium risk60 | —-0.030 |
| 39 | 19K00003CONSTRUCTION OF MISSING LINKS/NEW ROADS, MALAYBALAY CITY-GINGOOG ROAD, (KALABUGAO-KALHAAN SECTION), PACKAGE 16, BUKIDNON | Region X | Region X | Completed | ₱139.8M | 100% | Medium risk60 | —-0.038 |
| 40 | 17I00010ASSET PRESERVATION OF NAT'L. ROADS-PREVENTIVE MAINT. BASED ON PAVEMENT MGT. SYSTEM/HIGHWAY DEV'T. & MGT.-4 (HDM-4)-PRIMARY ROADS, ORMOC-BAYBAY-SO. LEYTE BDRY. ROAD, K1038+(-732)-K1053+143; K1059+000-K1060+000 | Region VIII | Region VIII | Completed | ₱168.8M | 100% | Medium risk59 | —-0.036 |
| 41 | 19L00175CONSTRUCTION OF CONCRETE ROAD-MARAGUSAN-PANTUKAN ROAD,(PANTUKAN SECTION),PACKAGE C,COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱90.3M | 100% | Medium risk58 | —-0.052 |
| 42 | 19K00021CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO PROPOSED BUKIDNON AIRPORT (JCT. KKK ROAD/LANGCATAON, PANGANTUCAN-JCT. DON CARLOS-KADINGILAN ROAD/SAN NICOLAS SECTION) PACKAGE 1, BUKIDNON | Region X | Region X | Completed | ₱124.6M | 100% | Medium risk58 | —-0.070 |
| 43 | 20L00014CONSTRUCTION OF CONCRETE ROAD -MAWAB-MACO BYPASS ROAD, PACKAGE A, COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱79.7M | 100% | Medium risk58 | —-0.050 |
| 44 | 19K00120CONSTRUCTION OF MISSING LINKS/NEW ROADS, EAST-WEST LATERAL ROAD CONNECTION AGUSAL DEL SUR/AGUSAN DEL NORTE TO BUKIDNON, DAMAY-CALABUGAO-ADTOLAWON ROAD, PACKAGE 12, BUKIDNON | Region X | Region X | Terminated | ₱93.6M | 100% | Medium risk57 | —-0.022 |
| 45 | 20K00185CONSTRUCTION OF MISSING LINKS/NEW ROADS, COMPLETION OF THE EAST-WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/ AGUSAN DEL NORTE TO BUKIDNON, DAMAY - CALABUGAO - ADTOLAWON ROAD, PACKAGE 18, BUKIDNON | Region X | Region X | Completed | ₱108.2M | 100% | Medium risk56 | —-0.073 |
| 46 | 19K00122CONSTRUCTION OF MISSING LINKS/NEW ROADS, EAST-WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/AGUSAN DEL NORTE TO BUKIDNON, DAMAY-CALABUGAO-ADTOLAWON ROAD, PACKAGE 17, BUKIDNON | Region X | Region X | Completed | ₱101.6M | 100% | Medium risk56 | —-0.062 |
| 47 | 18ID0099REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES CARIGARA BR.(B00493LT)ALONG PALO-CARIGARA-ORMOC ROAD(PHASE 1 & 2) | Region VIII | Leyte 2nd DEO | Completed | ₱75.1M | 100% | Medium risk56 | —-0.052 |
| 48 | 21C00063CONST./IMPR'VT. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY & TRADE INFRASTRUCTURE PROGRAM-ROLL-IT) ACCESS ROAD FROM HERMOSA ECONOMIC & INDUSTRIAL ZONE CONNECTING PALIHAN-MABIGA-SBMA, HERMOSA, BAT | Region III | Region III | Completed | ₱192.3M | 100% | Medium risk56 | —-0.049 |
| 49 | 16N00044CONSTRUCTION OF TINAGO PRE-STRESSED CONCRETE GIRDER BRIDGE WITH RIVER CONTROL AND DREGING (120 LINEAR METERS), MALIMONO, SURIGAO DEL NORTE | Region XIII | Region XIII | Completed | ₱12.3M | 100% | Medium risk56 | —-0.047 |
| 50 | 18IF0075IMPROVEMENT/REHABILITATION/RECHANNELING OF [PAGSANGA-AN RIVER INCLUDING DREDGING AT PAGSANGA-AN RIVER MOUTH A, BRGY. SAN JUAN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱91.6M | 100% | Medium risk56 | —-0.060 |