57 projects on file, including joint ventures this contractor is part of.
Total projects
57
Total budget
₱338.1M
Average progress
56.7%
Completion rate
35.1%
Below 70%
Average risk score
51.2
Medium risk on average, out of 100
Flagged as unusual
14
24.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 57 | ₱338.1M | 51.2 | 14 | 56.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 31 | ₱171.4M | 50.8 | 12 | 39.7% |
| Roads | 15 | ₱108.6M | 50.2 | 1 | 74.7% |
| Flood Control and Drainage | 11 | ₱58.1M | 53.6 | 1 | 79.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DC0074CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY CALINGATAN, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 80% | High risk75 | —-0.037 |
| 25DC0192CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE II, BARANGAY MANGAHAN, MATAAS NA KAHOY, BATANG | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | High risk75 | —-0.010 |
| 25DC0073CONVERGENCE AND SPECIAL SUPPORT PROGRAM. BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING (C0VERED COURT), CENTRAL SCHOOL, BARANGAY 4, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱9.7M | 79% | High risk71 | —-0.037 |
| 25DC0063CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF DRAINAGE STRUCTURE, DIMAYUGA STREET, BARANGAY II-A, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | High risk71 | Flagged0.001 |
| 25DC0059CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFASTRUCTURE PROGRAM (BIP) - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, REHABILITATION OF DRAINAGE STRUCTURE, PHASE II, DIMAYUGA STREET, BARANGAY II-A, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 65% | High risk71 | —-0.015 |
| 25DC0057CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP), - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY III, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 84% | High risk70 | —-0.023 |
| 25DC0053CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY BABUYAN, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 98% | High risk68 | —-0.048 |
| 25DC0056CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, PHASE II, PUROK 1, BARANGAY MANGGAHAN, MA | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | High risk67 | —-0.018 |
| 25DC0235OPENING AND CONCRETING OF BRGY. LUMANG LIPA FMR, BRGY. LUMANG LIPA, MATAAS NA KAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱14.5M | 0% | High risk64 | Flagged0.034 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DC0185BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN SEBASTIAN ELEMENTARY SCHOOL, BRGY. SAN SEBASTIAN | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.035 |
| 24DC0186BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN MATAASNAKAHOY SENIOR HIGH SCHOOL, LOCATED AT BRGY. B | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk53 | Flagged0.035 |
| 24DC0194BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN BAYORBOR NATIONAL HIGH SCHOOL, BRGY. BAYORBOR, MATAA | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.035 |
| 24DC0188BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2 -CLASSROOM SCHOOL BUILDING IN PAARALANG ELEMENTARYA NG BAYORBOR, BRGY. BAYORBOR, | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.035 |
| 24DC0195BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN SANTOL-MANGAHAN ELEMENTARY SCHOOL, BRGY. SANTOL, MAT | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.035 |
| 24DC0197BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN UPA PRIMARY SCHOOL, BRGY. UPA, MATAASNAKAHOY, BATANG | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.034 |
| 24DC0193BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN PAARALANG ELEMENTARYA NG LOOB, BRGY. LOOB, MATAASNAK | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.034 |
| 24DC0196BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN BUBUYAN ELEMENTARY SCHOOL, BRGY. BUBUYAN, MATAASNAKA | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.034 |
| 25DC0235OPENING AND CONCRETING OF BRGY. LUMANG LIPA FMR, BRGY. LUMANG LIPA, MATAAS NA KAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱14.5M | 0% | High risk64 | Flagged0.034 |
| 24DC0192BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN PAARALANG ELEMENTARYA NG LUMANGLIPA, BRGY. LUMANGLIP | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk46 | Flagged0.013 |
| 24DC0189BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN PAARALANG ELEMENTARYA NG KINALAGLAGAN, BRGY. KINALAG | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk46 | Flagged0.013 |
| 24DC0190BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN MATAASNAKAHOY NATIONAL HIGH SCHOOL, BRGY. 4, MATAASN | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk46 | Flagged0.013 |
| 24DC0187BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY CLASSROOM 2-CLASSROOM SCHOOL BUILDING IN PAARALANG SENTRAL NG MATAASNAKAHOY, BRGY. | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk46 | Flagged0.013 |
| 25DC0063CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF DRAINAGE STRUCTURE, DIMAYUGA STREET, BARANGAY II-A, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | High risk71 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25DC0074CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY CALINGATAN, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 80% | High risk75 | —-0.037 |
| 2 | 25DC0192CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE II, BARANGAY MANGAHAN, MATAAS NA KAHOY, BATANG | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | High risk75 | —-0.010 |
| 3 | 25DC0073CONVERGENCE AND SPECIAL SUPPORT PROGRAM. BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING (C0VERED COURT), CENTRAL SCHOOL, BARANGAY 4, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱9.7M | 79% | High risk71 | —-0.037 |
| 4 | 25DC0063CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF DRAINAGE STRUCTURE, DIMAYUGA STREET, BARANGAY II-A, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | High risk71 | Flagged0.001 |
| 5 | 25DC0059CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFASTRUCTURE PROGRAM (BIP) - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, REHABILITATION OF DRAINAGE STRUCTURE, PHASE II, DIMAYUGA STREET, BARANGAY II-A, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 65% | High risk71 | —-0.015 |
| 6 | 25DC0057CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP), - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY III, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 84% | High risk70 | —-0.023 |
| 7 | 25DC0053CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY BABUYAN, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 98% | High risk68 | —-0.048 |
| 8 | 25DC0056CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, PHASE II, PUROK 1, BARANGAY MANGGAHAN, MA | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | High risk67 | —-0.018 |
| 9 | 25DC0235OPENING AND CONCRETING OF BRGY. LUMANG LIPA FMR, BRGY. LUMANG LIPA, MATAAS NA KAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱14.5M | 0% | High risk64 | Flagged0.034 |
| 10 | 24DC0185BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN SEBASTIAN ELEMENTARY SCHOOL, BRGY. SAN SEBASTIAN | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.035 |
| 11 | 24DC0196BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN BUBUYAN ELEMENTARY SCHOOL, BRGY. BUBUYAN, MATAASNAKA | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.034 |
| 12 | 24DC0193BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN PAARALANG ELEMENTARYA NG LOOB, BRGY. LOOB, MATAASNAK | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.034 |
| 13 | 24DC0194BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN BAYORBOR NATIONAL HIGH SCHOOL, BRGY. BAYORBOR, MATAA | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.035 |
| 14 | 24DC0188BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2 -CLASSROOM SCHOOL BUILDING IN PAARALANG ELEMENTARYA NG BAYORBOR, BRGY. BAYORBOR, | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.035 |
| 15 | 24DC0195BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN SANTOL-MANGAHAN ELEMENTARY SCHOOL, BRGY. SANTOL, MAT | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.035 |
| 16 | 24DC0197BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2-STOREY 2-CLASSROOM SCHOOL BUILDING IN UPA PRIMARY SCHOOL, BRGY. UPA, MATAASNAKAHOY, BATANG | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk54 | Flagged0.034 |
| 17 | 24DC0186BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN MATAASNAKAHOY SENIOR HIGH SCHOOL, LOCATED AT BRGY. B | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk53 | Flagged0.035 |
| 18 | 25DC0031CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN AND DAY CARE CENTER BUILDING), BARANGAY DAL | Region IV-A | Batangas 3rd DEO | On-Going | ₱2.9M | 28% | Medium risk52 | —-0.018 |
| 19 | 24DC0036CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BUBUYAN, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.106 |
| 20 | 25DC0021CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PWD BUILDING), BARANGAY POBLACION 5, CUENCA, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | Medium risk51 | —-0.032 |
| 21 | 24DC0038CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MANGGAHAN, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱4.8M | 0% | Medium risk50 | —-0.025 |
| 22 | 25DB0100CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TUMALIM, NASUGBU BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.9M | 71% | Medium risk50 | —-0.054 |
| 23 | 23DC0044CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY LOOB, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱9.9M | 100% | Medium risk49 | —-0.107 |
| 24 | 25DC0079CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY II-A, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱9.7M | 0% | Medium risk49 | —-0.035 |
| 25 | 23DC0055CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) AT BARANGAY 3, MATAASNAKAHOY, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱9.9M | 100% | Medium risk49 | —-0.107 |