Contractor dossier
7 projects on file, including joint ventures this contractor is part of.
Total projects
7
Total budget
₱736.5M
Average progress
75.3%
Completion rate
28.6%
Below 70%
Average risk score
72.5
High risk on average, out of 100
Flagged as unusual
4
57.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 7 | ₱736.5M | 72.5 | 4 | 75.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 4 | ₱350.8M | 68.2 | 1 | 76.3% |
| Flood Control and Drainage | 2 | ₱254.5M | 75.4 | 2 | 60.8% |
| OTHER | 1 | ₱131.2M | 83.6 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JA0012CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (STA. MARIA SECTION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱131.2M | 100% | High risk84 | Flagged0.024 |
| 18J00010CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - FLOOD CONTROL FOR URBAN CORE AND CENTRAL DISTRICT OF ZAMBOANGA CITY TO INCLUDE PUMPING STATION AND RROW, ZAMBOANGA CITY (PACKAGE I) | Region IX | Region IX | On-Going | ₱141.2M | 61% | High risk76 | Flagged0.027 |
| 22J00078CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION (PACKAGE 1 & 2) | Region IX | Region IX | On-Going | ₱113.2M | 60% | High risk75 | Flagged0.011 |
| 20J00004CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY - PASS ROAD, (CULIANAN - PATALON SECTION), PACKAGE 3, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱141.1M | 100% | High risk74 | —-0.050 |
| 22J00071CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD (WEST COAST SECTION), PHASE I | Region IX | Region IX | On-Going | ₱93.9M | 41% | High risk73 | Flagged0.000 |
| 21J00041CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD, PATALON (WEST), PACKAGE 5, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱84.7M | 64% | High risk66 | —-0.001 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18J00010CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - FLOOD CONTROL FOR URBAN CORE AND CENTRAL DISTRICT OF ZAMBOANGA CITY TO INCLUDE PUMPING STATION AND RROW, ZAMBOANGA CITY (PACKAGE I) | Region IX | Region IX | On-Going | ₱141.2M | 61% | High risk76 | Flagged0.027 |
| 24JA0012CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (STA. MARIA SECTION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱131.2M | 100% | High risk84 | Flagged0.024 |
| 22J00078CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION (PACKAGE 1 & 2) | Region IX | Region IX | On-Going | ₱113.2M | 60% | High risk75 | Flagged0.011 |
| 22J00071CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD (WEST COAST SECTION), PHASE I | Region IX | Region IX | On-Going | ₱93.9M | 41% | High risk73 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24JA0012CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (STA. MARIA SECTION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱131.2M | 100% | High risk84 | Flagged0.024 |
| 2 | 18J00010CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - FLOOD CONTROL FOR URBAN CORE AND CENTRAL DISTRICT OF ZAMBOANGA CITY TO INCLUDE PUMPING STATION AND RROW, ZAMBOANGA CITY (PACKAGE I) | Region IX | Region IX | On-Going | ₱141.2M | 61% | High risk76 | Flagged0.027 |
| 3 | 22J00078CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION (PACKAGE 1 & 2) | Region IX | Region IX | On-Going | ₱113.2M | 60% | High risk75 | Flagged0.011 |
| 4 | 20J00004CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY - PASS ROAD, (CULIANAN - PATALON SECTION), PACKAGE 3, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱141.1M | 100% | High risk74 | —-0.050 |
| 5 | 22J00071CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD (WEST COAST SECTION), PHASE I | Region IX | Region IX | On-Going | ₱93.9M | 41% | High risk73 | Flagged0.000 |
| 6 | 21J00041CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD, PATALON (WEST), PACKAGE 5, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱84.7M | 64% | High risk66 | —-0.001 |
| 7 | 18JA0005NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - GOV. CAMINS ROAD INCLUDING ROAD RIGHT-OF-WAY (S01201MN), CHAINAGE 160 - CHAINAGE 802 | Region IX | Zamboanga City 2nd DEO | Completed | ₱31.2M | 100% | Medium risk59 | —-0.054 |