Contractor dossier
75 projects on file, including joint ventures this contractor is part of.
Total projects
75
Total budget
₱3.4B
Average progress
89.9%
Completion rate
80.0%
Average risk score
54.1
Medium risk on average, out of 100
Flagged as unusual
2
2.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 52 | ₱2.4B | 53.5 | 1 | 91.9% |
| Region V | 21 | ₱960.5M | 56.1 | 1 | 83.9% |
| National Capital Region | 2 | ₱33.3M | 45.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 24 | ₱866.5M | 54.5 | 1 | 92.1% |
| Flood Control and Drainage | 23 | ₱1.4B | 53.9 | 0 | 97.7% |
| Roads | 18 | ₱606.8M | 51.8 | 0 | 85.1% |
| Bridges | 8 | ₱308.6M | 51.1 | 1 | 70.3% |
| GAA 2025 OO-2 | 1 | ₱93.6M | 93.8 | 0 | 87.1% |
| OTHER | 1 | ₱96.5M | 72.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DH0011CONSTRUCTION OF RIVER CONTROL STRUCTURE ALONG PAGSANJAN RIVER, BARANGAY PINAGSANJAN, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱93.6M | 87% | High risk94 | —-0.023 |
| 18D00068LOCAL PROGRAMS ONSTRUCTION/REPAIR/ REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS LOCAL ROADS AND BRIDGES / LOCAL ROADS IMPROVEMENT / WIDENING OF DAANG HARI ROAD, BACOOR, CAVITE-CHAINAGE 3960-CHAINAGE 9028, CAVITE | Region IV-A | Region IV-A | Completed | ₱96.5M | 100% | High risk73 | —-0.015 |
| 16D00066CONSTRUCTION OF EVACUATION CENTER AT CARMONA, CAVITE PROVINCE | Region IV-A | Region IV-A | Completed | ₱33.9M | 100% | High risk71 | —-0.061 |
| 17D00063CONSTRUCTION OF EVACUATION CENTER AT TANAUAN CITY, BATANGAS PROVINCE | Region IV-A | Region IV-A | Completed | ₱33.4M | 100% | High risk71 | —-0.069 |
| 16D00061CONSTRUCTION OF EVACUATION CENTER, BRGY. TAGAPO, STA. ROSA CITY, LAGUNA | Region IV-A | Region IV-A | Completed | ₱33.3M | 100% | High risk71 | —-0.065 |
| 18D00010FY 2018 INFRA. PROGRAM, ORGANIZATIONAL OUTCOME 2: PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS; FLOOD MANAGEMENT PROGRAM, CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CARMONA RIVER, BINAN SIDE, BINAN CITY, LAGUNA | Region IV-A | Region IV-A | Completed | ₱139.8M | 100% | High risk67 | —-0.064 |
| 19FA0078CLUSTER 42-REHAB./RESTORATION/EXTENSION/RECONSTRUCTION OF FLOOD CONTROL IN THE FIRST DISTRICT OF ALBAY | Region V | Albay 1st DEO | Completed | ₱91.4M | 100% | High risk66 | —-0.019 |
| 21FC0119CONSTRUCTION OF ROAD WITH SLOPE PROTECTION (CONG. EMING PANOTES BOULEVARD) BARANGAY MANGUISOC, MERCEDES, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱96.5M | 100% | High risk65 | —-0.089 |
| 23DH0014CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF RIVER CONTROL ALONG PAGSANJAN RIVER, LUMBAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱93.6M | 100% | High risk65 | —-0.078 |
| 24FA0040CONCRETING OF BRGY. CALBAYOG-TINABAKOAN FMR, BRGY. CALBAYOG, MALILIPOT, ALBAY | Region V | Albay 1st DEO | Completed | ₱44.8M | 100% | High risk64 | —-0.043 |
| 24DH0035CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALANAC RIVER, BARANGAY SAMPALOC DOS, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.078 |
| 22FB0173CONSTRUCTION OF PAGCOLBON-MALOBAGO INTERIOR ROAD, RAPU-RAPU, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱53.1M | 64% | High risk63 | —-0.035 |
| 17D00061CONSTRUCTION OF EVACUATION CENTER AT MULANAY, QUEZON PROVINCE | Region IV-A | Region IV-A | Completed | ₱34.7M | 100% | High risk63 | —-0.067 |
| 20D00041FY 2020 DPWH INFRASTRUCTURE PROJECTS, CONVERGENCE & SPECIAL SUPPORT PROGRAM, CONST./IMPVT. OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY, CONSTRUCTION OF ADMINISTRATION BUILDING HEADQUARTERS, CAMP GUILLERMO NAKAR, LUCENA CITY, QUEZON | Region IV-A | Region IV-A | On-Going | ₱113.9M | 59% | High risk62 | —-0.002 |
| 21D00053CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY CONSTRUCTION OF MULTI - PURPOSE BUILDING (BARRACKS WITH PARKING), CAMP NAKAR, LUCENA CITY, QUEZON | Region IV-A | Region IV-A | Completed | ₱115.2M | 100% | High risk62 | —-0.073 |
| 22FB0138FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILTIES - CONSTRUCTION OF MALOBAGO FLOOD CONTROL SYSTEM INCLUDING ESPLANADE ALONG MALOBAGO-BUSAY RIVER (MAIN), DARAGA, ALBAY | Region V | Albay 2nd DEO | Completed | ₱57.9M | 100% | High risk62 | —-0.086 |
| 24FA0037CONCRETING OF BRGY. HINDI FMR, BRGY. HINDI, BACACAY, ALBAY | Region V | Albay 1st DEO | Completed | ₱29.9M | 100% | High risk61 | —-0.045 |
| 18D00081DORMITORY FOR GRADUATE STUDENTS,UP LOS BAÑOS, LAGUNA | Region IV-A | Region IV-A | Completed | ₱96.5M | 100% | High risk60 | —-0.021 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DF0245CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESREHAB (COMPLETION) OF MULTI PURPOSE BUILDING AT BRGY. BUHAY NA TUBIG, IMUS, CAVITE (CALIFORNIA WEST HILLS) | Region IV-A | Cavite 1st DEO | On-Going | ₱2.9M | 0% | Medium risk56 | Flagged0.001 |
| 23F00250ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-KANPAREL BR. (B00022CN) ALONG CATANDUANES CIR RD, PANGANIBAN, CATANDUANES (LONE DISTRICT) | Region V | Region V | On-Going | ₱23.7M | 3% | Medium risk51 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25DH0011CONSTRUCTION OF RIVER CONTROL STRUCTURE ALONG PAGSANJAN RIVER, BARANGAY PINAGSANJAN, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱93.6M | 87% | High risk94 | —-0.023 |
| 2 | 18D00068LOCAL PROGRAMS ONSTRUCTION/REPAIR/ REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS LOCAL ROADS AND BRIDGES / LOCAL ROADS IMPROVEMENT / WIDENING OF DAANG HARI ROAD, BACOOR, CAVITE-CHAINAGE 3960-CHAINAGE 9028, CAVITE | Region IV-A | Region IV-A | Completed | ₱96.5M | 100% | High risk73 | —-0.015 |
| 3 | 16D00066CONSTRUCTION OF EVACUATION CENTER AT CARMONA, CAVITE PROVINCE | Region IV-A | Region IV-A | Completed | ₱33.9M | 100% | High risk71 | —-0.061 |
| 4 | 17D00063CONSTRUCTION OF EVACUATION CENTER AT TANAUAN CITY, BATANGAS PROVINCE | Region IV-A | Region IV-A | Completed | ₱33.4M | 100% | High risk71 | —-0.069 |
| 5 | 16D00061CONSTRUCTION OF EVACUATION CENTER, BRGY. TAGAPO, STA. ROSA CITY, LAGUNA | Region IV-A | Region IV-A | Completed | ₱33.3M | 100% | High risk71 | —-0.065 |
| 6 | 18D00010FY 2018 INFRA. PROGRAM, ORGANIZATIONAL OUTCOME 2: PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS; FLOOD MANAGEMENT PROGRAM, CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CARMONA RIVER, BINAN SIDE, BINAN CITY, LAGUNA | Region IV-A | Region IV-A | Completed | ₱139.8M | 100% | High risk67 | —-0.064 |
| 7 | 19FA0078CLUSTER 42-REHAB./RESTORATION/EXTENSION/RECONSTRUCTION OF FLOOD CONTROL IN THE FIRST DISTRICT OF ALBAY | Region V | Albay 1st DEO | Completed | ₱91.4M | 100% | High risk66 | —-0.019 |
| 8 | 21FC0119CONSTRUCTION OF ROAD WITH SLOPE PROTECTION (CONG. EMING PANOTES BOULEVARD) BARANGAY MANGUISOC, MERCEDES, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱96.5M | 100% | High risk65 | —-0.089 |
| 9 | 23DH0014CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF RIVER CONTROL ALONG PAGSANJAN RIVER, LUMBAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱93.6M | 100% | High risk65 | —-0.078 |
| 10 | 24FA0040CONCRETING OF BRGY. CALBAYOG-TINABAKOAN FMR, BRGY. CALBAYOG, MALILIPOT, ALBAY | Region V | Albay 1st DEO | Completed | ₱44.8M | 100% | High risk64 | —-0.043 |
| 11 | 24DH0035CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALANAC RIVER, BARANGAY SAMPALOC DOS, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.078 |
| 12 | 22FB0173CONSTRUCTION OF PAGCOLBON-MALOBAGO INTERIOR ROAD, RAPU-RAPU, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱53.1M | 64% | High risk63 | —-0.035 |
| 13 | 17D00061CONSTRUCTION OF EVACUATION CENTER AT MULANAY, QUEZON PROVINCE | Region IV-A | Region IV-A | Completed | ₱34.7M | 100% | High risk63 | —-0.067 |
| 14 | 20D00041FY 2020 DPWH INFRASTRUCTURE PROJECTS, CONVERGENCE & SPECIAL SUPPORT PROGRAM, CONST./IMPVT. OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY, CONSTRUCTION OF ADMINISTRATION BUILDING HEADQUARTERS, CAMP GUILLERMO NAKAR, LUCENA CITY, QUEZON | Region IV-A | Region IV-A | On-Going | ₱113.9M | 59% | High risk62 | —-0.002 |
| 15 | 21D00053CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY CONSTRUCTION OF MULTI - PURPOSE BUILDING (BARRACKS WITH PARKING), CAMP NAKAR, LUCENA CITY, QUEZON | Region IV-A | Region IV-A | Completed | ₱115.2M | 100% | High risk62 | —-0.073 |
| 16 | 22FB0138FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILTIES - CONSTRUCTION OF MALOBAGO FLOOD CONTROL SYSTEM INCLUDING ESPLANADE ALONG MALOBAGO-BUSAY RIVER (MAIN), DARAGA, ALBAY | Region V | Albay 2nd DEO | Completed | ₱57.9M | 100% | High risk62 | —-0.086 |
| 17 | 24FA0037CONCRETING OF BRGY. HINDI FMR, BRGY. HINDI, BACACAY, ALBAY | Region V | Albay 1st DEO | Completed | ₱29.9M | 100% | High risk61 | —-0.045 |
| 18 | 18D00081DORMITORY FOR GRADUATE STUDENTS,UP LOS BAÑOS, LAGUNA | Region IV-A | Region IV-A | Completed | ₱96.5M | 100% | High risk60 | —-0.021 |
| 19 | 23F00110CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CARAMORAN POBLACION BYPASS RO | Region V | Region V | On-Going | ₱57.9M | 87% | Medium risk59 | —-0.052 |
| 20 | 21FB0119LIP-FLOOD CONTROL AND DRAINAGE: CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BARANGAY TAMAOYAN, LEGAZPI CITY | Region V | Albay 2nd DEO | Completed | ₱49.5M | 100% | Medium risk58 | —-0.088 |
| 21 | 20FB0037FLOOD CONTROL STRUCTURES/FACILITIES: CONSTRUCTION OF FLOOD MITIGATION SYSTEM ALONG PUROK 2, RAWIS, LEGAZPI CITY (PHASE 2) | Region V | Albay 2nd DEO | Completed | ₱49M | 100% | Medium risk58 | —-0.088 |
| 22 | 19FB0134CONSTRUCTION OF FLOOD MITIGATION SYSTEM ALONG PUROK 1, RAWIS, LEGAZPI CITY | Region V | Albay 2nd DEO | Completed | ₱49M | 100% | Medium risk58 | —-0.088 |
| 23 | 19FB0135CONSTRUCTION OF FLOOD MITIGATION SYSTEM ALONG PUROK 2, RAWIS, LEGAZPI CITY | Region V | Albay 2nd DEO | Completed | ₱37.8M | 100% | Medium risk58 | —-0.088 |
| 24 | 23F00416ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-NEW BAHI BR. (B02809LZ) ALONG DAANG MAHARLIKA (LZ), LUPI, CAMARINES SUR (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱55.4M | 32% | Medium risk57 | —-0.011 |
| 25 | 24DF0245CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESREHAB (COMPLETION) OF MULTI PURPOSE BUILDING AT BRGY. BUHAY NA TUBIG, IMUS, CAVITE (CALIFORNIA WEST HILLS) | Region IV-A | Cavite 1st DEO | On-Going | ₱2.9M | 0% | Medium risk56 | Flagged0.001 |