Contractor dossier
28 projects on file, including joint ventures this contractor is part of.
Total projects
28
Total budget
₱881M
Average progress
68.8%
Completion rate
46.4%
Below 70%
Average risk score
61.5
High risk on average, out of 100
Flagged as unusual
5
17.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 28 | ₱881M | 61.5 | 5 | 68.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 16 | ₱702.7M | 65.4 | 2 | 56.8% |
| Roads | 8 | ₱125.1M | 58.3 | 2 | 87.5% |
| Buildings and Facilities | 4 | ₱53.2M | 52.7 | 1 | 79.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CC0071CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER AT BARANGAY FRANCES (PUROK 5 TO PUROK 6), CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.8M | 92% | High risk81 | —-0.021 |
| 24CC0070CONSTRUCTION OF REVETMENT AT BARANGAY CALIZON, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 80% | High risk76 | —-0.016 |
| 24CC0071CONSTRUCTION OF REVETMENT AT BARANGAY PALIMBANG-SAN MARCOS-BALITE-SERGIO BAUAN, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱57.9M | 100% | High risk74 | —-0.061 |
| 25CC0358CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN AGUSTIN, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.5M | 55% | High risk74 | —-0.027 |
| 24CC0072CONSTRUCTION OF REVETMENT AT BARANGAY SAN JUAN, HAGONOY - SAN JOSE, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱48.2M | 14% | High risk74 | Flagged0.003 |
| 25CC0298CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, BARANGAY PALIMBANG-BARANGAY SAN MARCOS-BARANGAY BALITE-BARANGAY SERGIO BAYAN-BARANGAY BUGUION, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱50.5M | 0% | High risk74 | —-0.003 |
| 24CC0074CONSTRUCTION OF REVETMENT AT BARANGAY SANTO NINO - PUNGO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱49M | 100% | High risk73 | —-0.062 |
| 24CC0317CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BAANGAY LUGAM, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱6.9M | 100% | High risk73 | —-0.075 |
| 24CC0310REHABILITATION OF ACCESS ROAD LEADING TO FIRST BULACAN INDUSTRIAL CITY AT BARANGAY BANGKAL, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.5M | 100% | High risk70 | —-0.069 |
| 25CC0224CONSTRUCTION OF REVETMENT AT BARANGAY LONGOS, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱28.2M | 0% | High risk70 | —-0.004 |
| 25CC0270CONSTRUCTION OF REVETMENT AT BARANGAY MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱37.6M | 0% | High risk69 | —-0.003 |
| 25CC0222CONSTRUCTION OF REVETMENT AT BARANGAY SAN JOSE, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱37.6M | 41% | High risk69 | —-0.014 |
| 25CC0376CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT ANGAT-MAASIM RIS, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.4M | 43% | High risk69 | —-0.018 |
| 25CC0288CONSTRUCTION OF REVETMENT AT BARANGAY SAN MARCOS-PALIMBANG, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱37.7M | 0% | High risk69 | —-0.003 |
| 25CC0123REHABILITATION OF ROAD, BARANGAY MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱9.7M | 100% | High risk69 | —-0.067 |
| 25CC0297CONSTRUCTION OF REVETMENT AT BARANGAY SANTA LUCIA, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱37.7M | 41% | High risk69 | —-0.014 |
| 25CC0126REHABILITATION OF ROAD, BARANGAY PALIMBANG, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱9.9M | 100% | High risk69 | —-0.069 |
| 24CC0073CONSTRUCTION OF REVETMENT AT BARANGAY SANTO NINO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱39.2M | 100% | High risk69 | —-0.063 |
| 24CC0480CONCRETING OF BRGY. PENABATAN FMR, BRGY. PENABATAN, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱24.9M | 100% | High risk65 | —-0.010 |
| 24CC0476CONCRETING OF BRGY. FRANCES FMR, BRGY. FRANCES, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.9M | 0% | High risk65 | Flagged0.042 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CC0476CONCRETING OF BRGY. FRANCES FMR, BRGY. FRANCES, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.9M | 0% | High risk65 | Flagged0.042 |
| 24CC0537CONSTRUCTION OF 3-STOREY 6-CLASSROOM SCHOOL BUILDING AT CITY OF MALOLOS INTEGRATED SCHOOL, CATMON, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱29.8M | 65% | Medium risk54 | Flagged0.019 |
| 24CC0475CONCRETING OF BRGY. LIGAS FMR, BRGY. LIGAS, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱9.9M | 100% | High risk62 | Flagged0.016 |
| 24CC0661CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TABANG RIVER AT BARANGAY SAN NICOLAS, BULAKAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱70M | 97% | Medium risk51 | Flagged0.007 |
| 24CC0072CONSTRUCTION OF REVETMENT AT BARANGAY SAN JUAN, HAGONOY - SAN JOSE, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱48.2M | 14% | High risk74 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CC0071CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER AT BARANGAY FRANCES (PUROK 5 TO PUROK 6), CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.8M | 92% | High risk81 | —-0.021 |
| 2 | 24CC0070CONSTRUCTION OF REVETMENT AT BARANGAY CALIZON, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 80% | High risk76 | —-0.016 |
| 3 | 24CC0071CONSTRUCTION OF REVETMENT AT BARANGAY PALIMBANG-SAN MARCOS-BALITE-SERGIO BAUAN, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱57.9M | 100% | High risk74 | —-0.061 |
| 4 | 25CC0358CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN AGUSTIN, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.5M | 55% | High risk74 | —-0.027 |
| 5 | 24CC0072CONSTRUCTION OF REVETMENT AT BARANGAY SAN JUAN, HAGONOY - SAN JOSE, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱48.2M | 14% | High risk74 | Flagged0.003 |
| 6 | 25CC0298CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, BARANGAY PALIMBANG-BARANGAY SAN MARCOS-BARANGAY BALITE-BARANGAY SERGIO BAYAN-BARANGAY BUGUION, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱50.5M | 0% | High risk74 | —-0.003 |
| 7 | 24CC0074CONSTRUCTION OF REVETMENT AT BARANGAY SANTO NINO - PUNGO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱49M | 100% | High risk73 | —-0.062 |
| 8 | 24CC0317CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BAANGAY LUGAM, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱6.9M | 100% | High risk73 | —-0.075 |
| 9 | 24CC0310REHABILITATION OF ACCESS ROAD LEADING TO FIRST BULACAN INDUSTRIAL CITY AT BARANGAY BANGKAL, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.5M | 100% | High risk70 | —-0.069 |
| 10 | 25CC0224CONSTRUCTION OF REVETMENT AT BARANGAY LONGOS, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱28.2M | 0% | High risk70 | —-0.004 |
| 11 | 25CC0270CONSTRUCTION OF REVETMENT AT BARANGAY MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱37.6M | 0% | High risk69 | —-0.003 |
| 12 | 25CC0222CONSTRUCTION OF REVETMENT AT BARANGAY SAN JOSE, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱37.6M | 41% | High risk69 | —-0.014 |
| 13 | 25CC0376CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT ANGAT-MAASIM RIS, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.4M | 43% | High risk69 | —-0.018 |
| 14 | 25CC0288CONSTRUCTION OF REVETMENT AT BARANGAY SAN MARCOS-PALIMBANG, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱37.7M | 0% | High risk69 | —-0.003 |
| 15 | 25CC0123REHABILITATION OF ROAD, BARANGAY MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱9.7M | 100% | High risk69 | —-0.067 |
| 16 | 25CC0297CONSTRUCTION OF REVETMENT AT BARANGAY SANTA LUCIA, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱37.7M | 41% | High risk69 | —-0.014 |
| 17 | 25CC0126REHABILITATION OF ROAD, BARANGAY PALIMBANG, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱9.9M | 100% | High risk69 | —-0.069 |
| 18 | 24CC0073CONSTRUCTION OF REVETMENT AT BARANGAY SANTO NINO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱39.2M | 100% | High risk69 | —-0.063 |
| 19 | 24CC0480CONCRETING OF BRGY. PENABATAN FMR, BRGY. PENABATAN, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱24.9M | 100% | High risk65 | —-0.010 |
| 20 | 24CC0476CONCRETING OF BRGY. FRANCES FMR, BRGY. FRANCES, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.9M | 0% | High risk65 | Flagged0.042 |
| 21 | 24CC0475CONCRETING OF BRGY. LIGAS FMR, BRGY. LIGAS, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱9.9M | 100% | High risk62 | Flagged0.016 |
| 22 | 24CC0537CONSTRUCTION OF 3-STOREY 6-CLASSROOM SCHOOL BUILDING AT CITY OF MALOLOS INTEGRATED SCHOOL, CATMON, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱29.8M | 65% | Medium risk54 | Flagged0.019 |
| 23 | 24CC0661CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TABANG RIVER AT BARANGAY SAN NICOLAS, BULAKAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱70M | 97% | Medium risk51 | Flagged0.007 |
| 24 | 24CC0351REHABILITATION OF HAGONOY-SAN NICOLAS-STO. ROSARIO ACCESS ROAD LEADING TO HAGONOY FISHPORTS, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱29.4M | 100% | Medium risk34 | —-0.103 |
| 25 | 23CC0289UPGRADING OF ROAD INCLUDING DRAINAGE AT BARANGAY STO. ROSARIO, PAOMBONG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱11.9M | 100% | Medium risk31 | —-0.106 |