Opening the dossier…
Opening the dossier…
Contractor dossier
163 projects on file, including joint ventures this contractor is part of.
Total projects
163
Total budget
₱8.9B
Average progress
97.2%
Completion rate
91.4%
Average risk score
46.8
Medium risk on average, out of 100
Flagged as unusual
9
5.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 134 | ₱6.5B | 43.5 | 1 | 100.0% |
| Region IX | 22 | ₱1.8B | 64.9 | 8 | 79.2% |
| Region XIII | 5 | ₱357.2M | 51.4 | 0 | 100.0% |
| Region XI | 2 | ₱184M | 57.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 72 | ₱4.3B | 50.0 | 0 | 100.0% |
| Buildings and Facilities | 35 | ₱361.8M | 20.0 | 0 | 100.0% |
| Flood Control and Drainage | 30 | ₱2.4B | 56.4 | 5 | 87.2% |
| OTHER | 17 | ₱1.7B | 76.9 | 4 | 95.7% |
| Bridges | 6 | ₱142M | 45.6 | 0 | 100.0% |
| Water Provision and Storage | 3 | ₱7.4M | 18.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23J00140CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 2, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.2M | 88% | High risk84 | Flagged0.036 |
| 22J00126PREVENTIVE MAINTENANCE - PRIMARY ROADS PAGADIAN CITY - ZAMBOANGA CITY ROAD | Region IX | Region IX | On-Going | ₱98.6M | 76% | High risk82 | Flagged0.038 |
| 24J00304FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUB-LIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUC-TURE, TUMAGA RIVER (TUGBUNGAN SECTION), PACKAGE 3A, ZAM-BOANGA CITY | Region IX | Region IX | On-Going | ₱105.9M | 0% | High risk82 | Flagged0.069 |
| 24J00284CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4 | Region IX | Region IX | On-Going | ₱96.2M | 62% | High risk81 | Flagged0.059 |
| 24JA0174CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUMAGA RIVER (TETUAN SECTION), PACKAGE 3, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱96.6M | 0% | High risk80 | Flagged0.052 |
| 22K00371OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS, SAYRE HIGHWAY K1480 + 940.000 - K1482 + 048.776, K1482 + 911.490 - K1483 +661.420, K1512 + 000 - K1515 + 000 | Region X | Region X | Completed | ₱142.6M | 100% | High risk79 | —-0.011 |
| 22KA0088OFF-CARRIAGEWAY IMPROVEMENT ALONG JCT SH-AGLAYAN-ALANIB-TICALAAN RD (AGLAYAN-BASAK)-K1528+000 - K1536+507, LANTAPAN, BUKIDNON, BANTUANON-BACLAYON, LANTAPAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.021 |
| 23K00185CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT MANTICAO RIVER (DOWNSTREAM OF MANTICAO BRIDGE) MANTICAO, MISAMIS ORIENTAL | Region X | Region X | Completed | ₱198M | 100% | High risk79 | —-0.009 |
| 22K00370ROAD WIDENING-TERTIARY ROADS, JCT. SH AGLAYAN-ZAMBOANGUITA RD.K1520 + 988.549-K1521 + 284.490, K1521 + 325.000-K1522 + 504.000, K1522 + 890.00, K1522 +943.750, K1522+977.000 - K1523 +847.402, K1542 + 500-K1544 + 500 | Region X | Region X | Completed | ₱116M | 100% | High risk78 | —-0.016 |
| 18K00257CLUSTER 57 CONST./IMPRVT. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES & PAVING OF | Region X | Region X | Completed | ₱262.7M | 100% | High risk78 | Flagged0.000 |
| 23J00139CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 1, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.2M | 62% | High risk78 | Flagged0.025 |
| 22NG0091CONSTRUCTION OF ROAD, BARANGAY CAMP EDUARD, ALEGRIA, SURIGAO DEL NORTE / BARANGAY CAMP EDUARD, ALEGRIA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱77.2M | 100% | High risk77 | —-0.012 |
| 23J00138CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.3M | 61% | High risk76 | Flagged0.005 |
| 24J00017CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (TUGBUNGAN SECTION) PHASE II, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱145.4M | 20% | High risk76 | Flagged0.010 |
| 24J00018CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (TUGBUNGAN SECTION) PHASE III, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱145.4M | 72% | High risk76 | —-0.004 |
| 22KB0083CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF MANUTO BRIDGE (B01380MN) ALONG BUKIDNON-DAVAO CITY ROAD, MANUTO BRIDGE, BRGY SALAWAGAN, QUEZON, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱67.6M | 100% | High risk75 | —-0.030 |
| 22KB0086CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF APOLANG BRIDGE (B01389MN) ALONG KIBAWE-KADINGILAN-KALILANGAN ROAD, APOLANG BRIDGE, BRGY WEST KIBAWE, KIBAWE, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱57.9M | 100% | High risk75 | —-0.031 |
| 24K00034CONST. OF BY-PASS AND DIVERSION ROADS,OPOL DIVERSION ROAD(OPOL-CANITOAN), PACKAGE 17, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱47.8M | 100% | High risk75 | —-0.006 |
| 22KB0072CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF RAWARI BRIDGE (B01384MN) ALONG BUKIDNON-DAVAO CITY ROAD, RAWARI BRIDGE, SITIO RAWARI, KITAOTAO, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱67.6M | 100% | High risk75 | —-0.026 |
| 22KB0073CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF SAN MIGUEL BRIDGE (B01432MN) ALONG MARAMAG-MARADUGAO ROAD, SAN MIGUEL BRIDGE, SAN MIGUEL, MARAMAG, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱67.6M | 100% | High risk75 | —-0.032 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24J00304FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUB-LIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUC-TURE, TUMAGA RIVER (TUGBUNGAN SECTION), PACKAGE 3A, ZAM-BOANGA CITY | Region IX | Region IX | On-Going | ₱105.9M | 0% | High risk82 | Flagged0.069 |
| 24J00284CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4 | Region IX | Region IX | On-Going | ₱96.2M | 62% | High risk81 | Flagged0.059 |
| 24JA0174CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUMAGA RIVER (TETUAN SECTION), PACKAGE 3, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱96.6M | 0% | High risk80 | Flagged0.052 |
| 22J00126PREVENTIVE MAINTENANCE - PRIMARY ROADS PAGADIAN CITY - ZAMBOANGA CITY ROAD | Region IX | Region IX | On-Going | ₱98.6M | 76% | High risk82 | Flagged0.038 |
| 23J00140CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 2, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.2M | 88% | High risk84 | Flagged0.036 |
| 23J00139CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 1, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.2M | 62% | High risk78 | Flagged0.025 |
| 24J00017CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (TUGBUNGAN SECTION) PHASE II, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱145.4M | 20% | High risk76 | Flagged0.010 |
| 23J00138CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.3M | 61% | High risk76 | Flagged0.005 |
| 18K00257CLUSTER 57 CONST./IMPRVT. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES & PAVING OF | Region X | Region X | Completed | ₱262.7M | 100% | High risk78 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 17KC0040CONSTRUCTION OF MULTI-PURPOSE BLDG. COVERED COURT PHASE II IMBATUG CENTRAL ELEMENTARY SCHOOL, BAUNGON, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱2M | 100% | Low risk12 | —-0.073 |
| 152 | 21KC0014CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY SUMALSAG, MALITBOG, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱3M | 100% | Low risk11 | —-0.096 |
| 153 | 18KC0090CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, IMBATUG, BAUNGON, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱2.9M | 100% | Low risk11 | —-0.097 |
| 154 | 22KC0027CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING BARANGAY GANDINGAN, PANGANTUCAN, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱2.5M | 100% | Low risk11 | —-0.095 |
| 155 | 18KC0019CONSTRUCTION (COMPLETION) OF NHS COVERED COURT, BRGY. SANKANAN, MANOLO FORTICH, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱1.9M | 100% | Low risk9 | —-0.095 |
| 156 | 18KL0099REPAIR OF HONASAN HALL, PIE-MO, STA. CRUZ, TAGOLOAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱1.2M | 100% | Low risk9 | —-0.097 |
| 157 | 18KC0046CONSTRUCTION OF MULTI-PURPOSE BUILDING (SITIO CENTER), BRGY. SAN LUIS, MALITBOG, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱965.1K | 100% | Low risk8 | —-0.094 |
| 158 | 17KC0076CONSTRUCTION OF 1STY 3CL SCHOOL BUILDING WITH TOILET, MABUHAY ES, SAN LUIS, MALITBOG, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱3.8M | 100% | Low risk3 | —-0.026 |
| 159 | 17KC0081CONSTRUCTION OF 1STY 3CL SCHOOL BUILDING WITH TOILET, ALAE CES, ALAE, MANOLO FORTICH, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱4.2M | 100% | Low risk3 | —-0.026 |
| 160 | 17KC0086CONSTRUCTION OF 1 UNIT UNIQUE WORKSHOP SCHOOL BUILDING (7X22.5), MANOLO FORTICH NHS, TANKULAN, MANOLO FORTICH, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱3M | 100% | Low risk3 | —-0.025 |
| 161 | 17KC0080CONSTRUCTION OF 1STY 2CL SCHOOL BUILDING WITH TOILET, ALAE CES, ALAE, MANOLO FORTICH, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱3.3M | 100% | Low risk3 | —-0.026 |
| 162 | 17KC0084CONSTRUCTION OF 1STY 2CL SCHOOL BUILDING WITH TOILET, LUNOCAN ES, LUNOCAN, MANOLO FORTICH, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱2.7M | 100% | Low risk3 | —-0.026 |
| 163 | 17KC0085CONSTRUCTION OF 1STY 2CL SCHOOL BUILDING WITH TOILET, SAN MIGUEL ES, SAN MIGUEL, MANOLO FORTICH, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱2.8M | 100% | Low risk3 | —-0.026 |