Contractor dossier
712 projects on file, including joint ventures this contractor is part of.
Total projects
712
Total budget
₱45.9B
Average progress
83.8%
Completion rate
68.7%
Below 70%
Average risk score
54.0
Medium risk on average, out of 100
Flagged as unusual
63
8.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 650 | ₱43.7B | 54.3 | 62 | 82.4% |
| Negros Island Region | 56 | ₱1.7B | 50.3 | 0 | 99.3% |
| Region VIII | 4 | ₱343.4M | 58.0 | 1 | 89.4% |
| Region VI | 1 | ₱96.5M | 63.5 | 0 | 74.1% |
| Region IV-B | 1 | ₱38.7M | 37.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 363 | ₱23.3B | 52.2 | 23 | 83.9% |
| Flood Control and Drainage | 212 | ₱15.2B | 58.3 | 18 | 85.1% |
| Buildings and Facilities | 64 | ₱2.1B | 42.2 | 3 | 86.7% |
| Bridges | 50 | ₱3.3B | 55.4 | 10 | 76.7% |
| OTHER | 17 | ₱1.4B | 69.0 | 5 | 80.4% |
| GAA 2025 SSP | 3 | ₱382.4M | 95.6 | 3 | 69.2% |
| GAA 2025 OO-2 | 1 | ₱64.3M | 92.3 | 1 | 27.1% |
| Bridges, Roads | 1 | ₱97.5M | 65.0 | 0 | 38.2% |
| Water Provision and Storage | 1 | ₱33.8M | 49.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HO0135CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, SITIO CAMBINOCOT TO | Region VII | Cebu 7th DEO | On-Going | ₱141.9M | 38% | High risk96 | Flagged0.040 |
| 25HO0149CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE, PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF BRGY. KANTANGKAS- BRGY. PACULOB ROAD, DUMANJUG, CE | Region VII | Cebu 7th DEO | On-Going | ₱145.5M | 72% | High risk96 | Flagged0.033 |
| 25HO0046CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY COLABTINGON (DOWNSTREAM LEFT SIDE), | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 98% | High risk95 | Flagged0.016 |
| 25HH0138OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BULACAO RIVER, CEBU CITY | Region VII | Cebu City DEO | On-Going | ₱64.3M | 27% | High risk92 | Flagged0.001 |
| 23HO0249CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTSALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. MATALAO (DOWNSTREAM), DUMANJUG, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.081 |
| 23HO0250CONVERGENCE ANDSPECIAL SUPPORT PROGRAM,SUSTAINABLE INFRASTRUCTURE PROJECTSALLEVIATING GAPS, FLOOD MITIGATIONSTRUCTURES PROTECTING PUBLICINFRASTRUCTURES/FACILITIES,CONSTRUCTION OF REVETMENT WALL ATBRGY. KANTANGKAS (DOWNSTREAM),DUMANJUG, CE | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.081 |
| 24HO0169CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF BANK PROTECTION STRUCTURES AT SITIO LALAO, BARANGA | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk87 | Flagged0.072 |
| 23HO0285CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY KANTANGKAS (UPSTREAM), | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.072 |
| 24HO0153CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY MATALAO (UPSTREAM), DUMAN | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.072 |
| 24HO0177CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY COLABTINGON - BARANGAY | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk87 | Flagged0.069 |
| 24HO0176CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY KANTANGKAS - KANG-ACTOL | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk87 | Flagged0.069 |
| 23HO0294CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ALEGRIA SEAWALL PROTECTION STRUCTURE (PACKAGE 2), | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.073 |
| 24I00057NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (S00223LT) - K1014+000 - K1014+727, K1016+865 - K1017+000, K1017+085 - K1018+620 | Region VIII | Region VIII | On-Going | ₱217.5M | 58% | High risk85 | Flagged0.039 |
| 23HO0280CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG DOBDOB SECTION, BADIAN, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱66.5M | 0% | High risk82 | Flagged0.076 |
| 21HO0001REPAIR / REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS AND BRIDGES, FLOOD CONTROL, OTHER PUBLIC | Region VII | Cebu 7th DEO | Completed | ₱250.9M | 100% | High risk79 | —-0.002 |
| 24HO0150CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MANLAPAY - | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk78 | Flagged0.073 |
| 23HO0282CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DALAGUETE-MANTALONGON-BAD | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk78 | Flagged0.073 |
| 24HO0163CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROADWAY LIGHTING ALONG SANTANDER-BARILI-TOLEDO RD, BARANGAY MONTAÑEZA, MALABUYOC, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk78 | Flagged0.074 |
| 23HO0283ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, SANTANDER-BARILI-TOLEDO RD, K0178+000 - K0178+177 | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk78 | Flagged0.073 |
| 23HO0306CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DUMANJUG BY-PASS ROAD (PH | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk78 | Flagged0.064 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23HO0249CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTSALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. MATALAO (DOWNSTREAM), DUMANJUG, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.081 |
| 23HO0250CONVERGENCE ANDSPECIAL SUPPORT PROGRAM,SUSTAINABLE INFRASTRUCTURE PROJECTSALLEVIATING GAPS, FLOOD MITIGATIONSTRUCTURES PROTECTING PUBLICINFRASTRUCTURES/FACILITIES,CONSTRUCTION OF REVETMENT WALL ATBRGY. KANTANGKAS (DOWNSTREAM),DUMANJUG, CE | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.081 |
| 23HO0280CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG DOBDOB SECTION, BADIAN, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱66.5M | 0% | High risk82 | Flagged0.076 |
| 24HO0163CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROADWAY LIGHTING ALONG SANTANDER-BARILI-TOLEDO RD, BARANGAY MONTAÑEZA, MALABUYOC, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk78 | Flagged0.074 |
| 23HO0283ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, SANTANDER-BARILI-TOLEDO RD, K0178+000 - K0178+177 | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk78 | Flagged0.073 |
| 23HO0282CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DALAGUETE-MANTALONGON-BAD | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk78 | Flagged0.073 |
| 24HO0150CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MANLAPAY - | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk78 | Flagged0.073 |
| 23HO0294CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ALEGRIA SEAWALL PROTECTION STRUCTURE (PACKAGE 2), | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.073 |
| 24HO0169CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF BANK PROTECTION STRUCTURES AT SITIO LALAO, BARANGA | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk87 | Flagged0.072 |
| 23HO0285CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY KANTANGKAS (UPSTREAM), | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.072 |
| 24HO0153CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY MATALAO (UPSTREAM), DUMAN | Region VII | Cebu 7th DEO | On-Going | ₱95M | 0% | High risk87 | Flagged0.072 |
| 24HO0177CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY COLABTINGON - BARANGAY | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk87 | Flagged0.069 |
| 24HO0176CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BARANGAY KANTANGKAS - KANG-ACTOL | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk87 | Flagged0.069 |
| 23HO0293CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC), INSTALLATION OF SOLAR LED STREET LIGHTS ALONG SECONDARY ROAD, SANTANDER-BARILI-TOLEDO RD, (RONDA-DUMANJUG SECTION), RONDA, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱118.9M | 0% | High risk76 | Flagged0.067 |
| 24HO0172CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROADWAY LIGHTING ALONG SANTANDER-BARILI-TOLEDO RD, BARANGAY POBLACION- BARANGAY SANTA FILOMENA, ALEGRIA, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk77 | Flagged0.065 |
| 24HO0170CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROADWAY LIGHTING ALONG SANTANDER-BARILI- TOLEDO RD, BARANGAY MALABAGO - BARANGAY HINABLAN, BADIAN, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk77 | Flagged0.065 |
| 24HO0171CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROADWAY LIGHTING ALONG SANTANDER-BARILI-TOLEDO RD, BARANGAY MALHIAO - BARANGAY BUGAS, BADIAN, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 0% | High risk77 | Flagged0.065 |
| 23HO0314CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC), INSTALLATION OF SOLAR LED STREET LIGHTS ALONG SANTANDER-BARILI-TOLEDO RD, BADIAN SECTION, BADIAN, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱94.1M | 0% | High risk77 | Flagged0.065 |
| 23HO0295CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MATALAO - | Region VII | Cebu 7th DEO | On-Going | ₱95.8M | 0% | High risk77 | Flagged0.064 |
| 23HO0307CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MATALAO - | Region VII | Cebu 7th DEO | On-Going | ₱95.8M | 0% | High risk77 | Flagged0.064 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 226 | 25HO0166ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, SANTANDER-BARILI-TOLEDO RD - K0201+148 - K0202+923 | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 27% | High risk61 | —-0.033 |
| 227 | 24HO0060ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, SANTANDER-BARILI-TOLEDO RD - K0195 + 220 - K0195 + 327, K0196 + 1108 - K0197 + 786, K0200 + 162 - K0201 + 148 | Region VII | Cebu 7th DEO | On-Going | ₱95M | 90% | High risk61 | —-0.050 |
| 228 | 20HG0065OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM; NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS-DALAGUETE-MANTALONGON-BADIAN ROAD, BASAK, BADIAN, CEBU | Region VII | Cebu 2nd DEO | Completed | ₱93.5M | 100% | High risk61 | —-0.085 |
| 229 | 20HG0064OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM; NETWORK DEVELOPMENT- CONSTRUCTION OF MISSING LINKS/NEW ROADS-DALAGUETE-MANTALONGON-BADIAN ROAD, DOBDOB, BADIAN, CEBU | Region VII | Cebu 2nd DEO | Completed | ₱93.5M | 100% | High risk61 | —-0.085 |
| 230 | 22HF0026ASSET PRESERVATION PROGRAM - REHABILITATION OF TOLEDO-PINAMUNGAHAN-ALOGUINSAN-MANTALONGON RD - K0074 + 400 - K0074 + 800 WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE | Region VII | Cebu 3rd DEO | Completed | ₱96.3M | 100% | High risk61 | —-0.084 |
| 231 | 23HO0057ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, DALAGUETE-MANTALONGON BADIAN RD - K0112+335 - K0112+4 | Region VII | Cebu 7th DEO | Completed | ₱95.5M | 100% | High risk61 | —-0.084 |
| 232 | 23HO0058ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, DALAGUETE-MANTALONGON BADIAN RD - K0112+445 - K0112+5 | Region VII | Cebu 7th DEO | Completed | ₱95.5M | 100% | High risk61 | —-0.084 |
| 233 | 22HO0051ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, SANTANDER-BARILI-TOLEDO RD - K0202+923 - K0206+000 | Region VII | Cebu 7th DEO | Completed | ₱96M | 100% | High risk61 | —-0.085 |
| 234 | 23HO0134ORGANIZATIONAL OUTCOME 1: ENSURE SAFE RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - TERTIARY ROADS, SIBONGA-DUMANJUG ROAD - K0077 + 600 - K0080 + 430 | Region VII | Cebu 7th DEO | Completed | ₱95.6M | 100% | High risk61 | —-0.085 |
| 235 | 18HG0142CONCRETING OF BRGY. CABUTONGAN-SITIO TAKULING FMR, BRGY. CABUTONGAN, SANTANDER, CEBU | Region VII | Cebu 2nd DEO | Completed | ₱9.5M | 100% | High risk61 | —-0.012 |
| 236 | 22HO0038ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION, PREVENTIVE MAINTENANCE - SECONDARY ROADS - SANTANDER-BARILI-TOLEDO RD - K0161+000 - K0164+019 | Region VII | Cebu 7th DEO | Completed | ₱95.1M | 100% | High risk61 | —-0.084 |
| 237 | 23HO0017CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY KANTANGKAS, DUMANJUG, CEBU | Region VII | Cebu 7th DEO | Completed | ₱96.4M | 100% | High risk61 | —-0.084 |
| 238 | 16H00046NETWORK DEVELOPMENT, OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, PRIMARY ROADS, CEBU NORTH RD | Region VII | Region VII | Completed | ₱52.9M | 100% | High risk61 | —-0.062 |
| 239 | 25H00073ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, METRO CEBU EXPRESSWAY, PACKAGE 5, CEBU | Region VII | Region VII | On-Going | ₱94.6M | 1% | High risk61 | —-0.023 |
| 240 | 25HD0177CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF ROAD, BRGY MANIPIS - JCT LINAO | Region VII | Cebu 1st DEO | On-Going | ₱94.6M | 2% | High risk60 | —-0.024 |
| 241 | 25HD0186CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF BY-PASS AND DIVERSION RD CTWR | Region VII | Cebu 1st DEO | On-Going | ₱94.6M | 13% | High risk60 | —-0.025 |
| 242 | 25HD0187CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF MANGGILAMON - TAPUL ROAD TALISA | Region VII | Cebu 1st DEO | On-Going | ₱94.6M | 20% | High risk60 | —-0.029 |
| 243 | 23HO0161CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DUMANJUG BYPASS ROAD, BAR | Region VII | Cebu 7th DEO | On-Going | ₱96.4M | 100% | High risk60 | —-0.040 |
| 244 | 23HE0164CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRA. PROJETS ALLEVIATING GAPS (SIPAG) - ACCESS ROOADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST. OF CTWR LINAO-CANTABACO SECT. TALIS | Region VII | Cebu 1st DEO | On-Going | ₱96.3M | 56% | High risk60 | —-0.031 |
| 245 | 18HG0104ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES - TERTIARY ROADS: DALAGUETE-MANTALONGON-BADIAN ROAD, K0104+500-K0105+000, K0106+800-K0106+880, K0108+ | Region VII | Cebu 2nd DEO | Completed | ₱93.1M | 100% | High risk60 | —-0.085 |
| 246 | 23HO0054CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY BASAK - BARANGAY BASIAO, BADIAN, CE | Region VII | Cebu 7th DEO | Completed | ₱96.4M | 100% | High risk60 | —-0.084 |
| 247 | 23HO0118ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, DUMANJUG BY-PASS ROAD, BRGY. TANGIL, DUMANJUG, CEBU | Region VII | Cebu 7th DEO | Completed | ₱96.4M | 100% | High risk60 | —-0.084 |
| 248 | 23HO0006CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY COLABTINGON, DUMANJUG, CEBU | Region VII | Cebu 7th DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.084 |
| 249 | 23HO0101CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION, CONSTRUCTION OF ROAD, BARANGAY COLABTINGON (PACKAGE 2), DUMANJUG, CEBU | Region VII | Cebu 7th DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.084 |
| 250 | 23HF0116REPAIR/REHABILITATION OF ROADSIDE PROTECTION ALONG TOLEDO-TABUELAN-SAN REMIGIO ROAD, K0102+180 - K0102+450 | Region VII | Cebu 3rd DEO | Completed | ₱95.7M | 100% | High risk60 | —-0.083 |