Contractor dossier
5 projects on file, including joint ventures this contractor is part of.
Total projects
5
Total budget
₱97.7M
Average progress
78.2%
Completion rate
60.0%
Below 70%
Average risk score
62.3
High risk on average, out of 100
Flagged as unusual
1
20.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 5 | ₱97.7M | 62.3 | 1 | 78.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| GAA 2025 OO-1 | 1 | ₱27.8M | 92.1 | 1 | 20.3% |
| GAA 2025 SSP | 1 | ₱4.8M | 89.7 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱43.4M | 45.2 | 0 | 70.6% |
| Buildings and Facilities | 1 | ₱12.9M | 42.6 | 0 | 100.0% |
| Roads | 1 | ₱8.7M | 42.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AE0037CONSTRUCTION OF NEW BRIDGES - LUZONG SUR BR. ALONG MANILA NORTH ROAD (RE-ADVERTISEMENT) | Region I | La Union 1st DEO | On-Going | ₱27.8M | 20% | High risk92 | Flagged0.021 |
| 25AE0036BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY POBLACION, LUNA, LA UNION | Region I | La Union 1st DEO | Completed | ₱4.8M | 100% | High risk90 | —-0.020 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25AE0037CONSTRUCTION OF NEW BRIDGES - LUZONG SUR BR. ALONG MANILA NORTH ROAD (RE-ADVERTISEMENT) | Region I | La Union 1st DEO | On-Going | ₱27.8M | 20% | High risk92 | Flagged0.021 |
| 2 | 25AE0036BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY POBLACION, LUNA, LA UNION | Region I | La Union 1st DEO | Completed | ₱4.8M | 100% | High risk90 | —-0.020 |
| 3 | 25AE0049BASIC INFRASTRUCTURE PROGRAM (BIP) - REHABILITATION OF FLOOD CONTROL ALONG AMBURAYAN RIVER, BARANGAY MINDORO, BANGAR, LA UNION | Region I | La Union 1st DEO | On-Going | ₱43.4M | 71% | Medium risk45 | —-0.027 |
| 4 | 24AE0098CONSTRUCTION OF 2-STOREY 4-CLASSROOM BUILDING AT REGIONAL SCIENCE HIGH SCHOOL FOR REGION I, BANGAR, LA UNION | Region I | La Union 1st DEO | Completed | ₱12.9M | 100% | Medium risk43 | —-0.046 |
| 5 | 23AE0047REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - BACNOTAN-LUNA-BALAOAN ROAD - K0302+1146 - K0303+320 | Region I | La Union 1st DEO | Completed | ₱8.7M | 100% | Medium risk42 | —-0.088 |