Contractor dossier
12 projects on file, including joint ventures this contractor is part of.
Total projects
12
Total budget
₱308.6M
Average progress
91.2%
Completion rate
75.0%
Average risk score
61.2
High risk on average, out of 100
Flagged as unusual
3
25.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 4 | ₱149.9M | 55.9 | 1 | 94.1% |
| Region III | 4 | ₱68.8M | 53.4 | 0 | 100.0% |
| Region VII | 3 | ₱78.5M | 83.6 | 2 | 72.5% |
| National Capital Region | 1 | ₱11.5M | 45.6 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 4 | ₱54.3M | 56.5 | 0 | 100.0% |
| Roads | 3 | ₱55.3M | 42.4 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱43.8M | 94.7 | 2 | 58.7% |
| OTHER | 2 | ₱131.1M | 72.8 | 1 | 88.3% |
| Flood Control and Drainage | 1 | ₱24.1M | 45.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HA0086CONSTRUCTION OF SCHOOL BUILDING AND CLASSROOMS FOR BACLAYON NATIONAL HIGH SCHOOL, LANDICAN, BACLAYON, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱34M | 43% | High risk95 | Flagged0.026 |
| 25HA0074CONSTRUCTION OF MULTI-PURPOSE BUILDING, DR. CECILIO PUTONG NATIONAL HIGH SCHOOL, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱9.9M | 74% | High risk95 | Flagged0.018 |
| 24I00216CLUSTER 10: 1. NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - ARTECHE, BRGY. CATUMSAN - JIPAPAD - LAS NAVAS - CATUBIG, RAWIS ROAD, EASTERN SAMAR; 2. CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING | Region VIII | Region VIII | On-Going | ₱96.4M | 77% | High risk84 | Flagged0.016 |
| 24CC0434CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY LUGAM, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱19.6M | 100% | High risk74 | —-0.072 |
| 24CC0508CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAMARAWAN, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.8M | 100% | High risk73 | —-0.074 |
| 24HC0098CONSTRUCTION OF FARMERS MULTI-PURPOSE BUILDING, BARANGAY POBLACION, DANAO, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱34.6M | 100% | High risk61 | —-0.025 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HA0086CONSTRUCTION OF SCHOOL BUILDING AND CLASSROOMS FOR BACLAYON NATIONAL HIGH SCHOOL, LANDICAN, BACLAYON, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱34M | 43% | High risk95 | Flagged0.026 |
| 25HA0074CONSTRUCTION OF MULTI-PURPOSE BUILDING, DR. CECILIO PUTONG NATIONAL HIGH SCHOOL, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱9.9M | 74% | High risk95 | Flagged0.018 |
| 24I00216CLUSTER 10: 1. NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - ARTECHE, BRGY. CATUMSAN - JIPAPAD - LAS NAVAS - CATUBIG, RAWIS ROAD, EASTERN SAMAR; 2. CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING | Region VIII | Region VIII | On-Going | ₱96.4M | 77% | High risk84 | Flagged0.016 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25HA0086CONSTRUCTION OF SCHOOL BUILDING AND CLASSROOMS FOR BACLAYON NATIONAL HIGH SCHOOL, LANDICAN, BACLAYON, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱34M | 43% | High risk95 | Flagged0.026 |
| 2 | 25HA0074CONSTRUCTION OF MULTI-PURPOSE BUILDING, DR. CECILIO PUTONG NATIONAL HIGH SCHOOL, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱9.9M | 74% | High risk95 | Flagged0.018 |
| 3 | 24I00216CLUSTER 10: 1. NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - ARTECHE, BRGY. CATUMSAN - JIPAPAD - LAS NAVAS - CATUBIG, RAWIS ROAD, EASTERN SAMAR; 2. CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING | Region VIII | Region VIII | On-Going | ₱96.4M | 77% | High risk84 | Flagged0.016 |
| 4 | 24CC0434CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY LUGAM, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱19.6M | 100% | High risk74 | —-0.072 |
| 5 | 24CC0508CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAMARAWAN, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.8M | 100% | High risk73 | —-0.074 |
| 6 | 24HC0098CONSTRUCTION OF FARMERS MULTI-PURPOSE BUILDING, BARANGAY POBLACION, DANAO, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱34.6M | 100% | High risk61 | —-0.025 |
| 7 | 23I00079SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY POLANGI TO GAYAM, TAFT, EASTERN SAMAR | Region VIII | Region VIII | Completed | ₱19.3M | 100% | Medium risk49 | —-0.095 |
| 8 | 23I00084SIPAG - FLOOD CONTROL MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY POBLACION, HERNANI, EASTERN SAMAR | Region VIII | Region VIII | Completed | ₱24.1M | 100% | Medium risk46 | —-0.077 |
| 9 | 23OD0016PREVENTIVE MAINTENANCE - TERTIARY ROADS 7TH AVE WEST - K0008 + (-295) - K0008 + 481, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱11.5M | 100% | Medium risk46 | —-0.100 |
| 10 | 23IL0071CONSTRUCTION OF 1STY3CL, GUADALUPE NATIONAL HIGH SCHOOL, MAASIN, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱10M | 100% | Medium risk45 | —-0.054 |
| 11 | 23CC0397CONSTRUCTION OF MULTI-PURPOSE FACILITY (COVERED COURT), BRGY. POBLACION, PANDI, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱9.9M | 100% | Medium risk34 | —-0.107 |
| 12 | 23CC0183SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LIGHTING ALONG PULILAN-BALIUAG BYPASS ROAD, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱24.5M | 100% | Medium risk32 | —-0.106 |