Opening the dossier…
Opening the dossier…
Contractor dossier
93 projects on file, including joint ventures this contractor is part of.
Total projects
93
Total budget
₱1.7B
Average progress
92.3%
Completion rate
82.8%
Average risk score
41.7
Medium risk on average, out of 100
Flagged as unusual
2
2.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 89 | ₱1.4B | 41.0 | 2 | 92.5% |
| Region V | 3 | ₱172.2M | 62.2 | 0 | 83.3% |
| National Capital Region | 1 | ₱55.6M | 42.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 35 | ₱634.5M | 39.0 | 0 | 91.8% |
| Buildings and Facilities | 32 | ₱644.7M | 41.0 | 1 | 87.6% |
| Bridges | 20 | ₱309.2M | 50.0 | 0 | 100.0% |
| Flood Control and Drainage | 4 | ₱20.9M | 27.2 | 0 | 100.0% |
| OTHER | 1 | ₱38.1M | 67.6 | 1 | 65.7% |
| Water Provision and Storage | 1 | ₱3.2M | 25.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25D00076CONSTRUCTION OF DEPARTMENT OF LABOR AND EMPLOYMENT (DOLE) REGIONAL OFFICE IV-A BUILDING, CABUYAO CITY, LAGUNA, PHASE II | Region IV-A | Region IV-A | On-Going | ₱41M | 0% | High risk72 | —-0.009 |
| 25DP0078CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KANLURAN KABUBUHAYAN, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱6.8M | 62% | High risk72 | —-0.029 |
| 24D00199OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADSCALAMBA-STA.CRUZ-FAMY JCT ROAD - K0051 + 460 - K0051 + 763, K0052 + 010 - K0052 + 430, K0052 + 443 - K0052 + 510, K0056 + 325 - K0056 + 553, K0056 + 650 - K0056 + 723, K0057 + 289 - K0057 + 651 | Region IV-A | Region IV-A | On-Going | ₱47.3M | 13% | High risk69 | —-0.019 |
| 23DI0058OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - STA ROSA-ULAT-TAGAYTAY RD - K0044 + 750 - K0045 + 650 | Region IV-A | Laguna 2nd DEO | On-Going | ₱38.1M | 66% | High risk68 | Flagged0.010 |
| 25FD0026CONSTRUCTION (COMPLETION) OF DPWH CAMARINES SUR 1ST DISTRICT ENGINEERING OFFICE, BARANGAY UPPER BINAHAN, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱75.6M | 67% | High risk64 | —-0.046 |
| 24FD0075CONSTRUCTION OF DPWH CAMARINES SUR 1ST DISTRICT ENGINEERING OFFICE, BARANGAY UPPER BINAHAN, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱48M | 91% | High risk62 | —-0.053 |
| 24FD0074CONSTRUCTION OF MULTI-PURPOSE BUILDING (DISTRICT OFFICE), RAGAY CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱48.6M | 91% | High risk61 | —-0.053 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24D00286DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) OTHER FACILITIES - SARIAYA DIALYSIS CENTER, QUEZON | Region IV-A | Region IV-A | On-Going | ₱5.9M | 0% | Medium risk43 | Flagged0.011 |
| 23DI0058OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - STA ROSA-ULAT-TAGAYTAY RD - K0044 + 750 - K0045 + 650 | Region IV-A | Laguna 2nd DEO | On-Going | ₱38.1M | 66% | High risk68 | Flagged0.010 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24DP0116CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES STRUCTURAL AND RESILIENCE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY ALIBUNGBUNGAN, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱5.7M | 100% | Medium risk49 | —-0.107 |
| 27 | 24DI0018CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CAMP MACARIO SAKAY, LOS BANOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.106 |
| 28 | 24DP0091CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES STRUCTURAL AND RESILIENCE PROGRAM - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY KANLURAN LAZAAN, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4.8M | 100% | Medium risk48 | —-0.106 |
| 29 | 23DI0101REPLACEMENT OF PERMANENT WEAK BRIDGES - MAITIM BR. (B02510LZ) ALONG CALAMBA-STA CRUZ-FAMY JCT RD | Region IV-A | Laguna 2nd DEO | Completed | ₱29.4M | 100% | Medium risk48 | —-0.069 |
| 30 | 21DH0072CONSTRUCTION OF PERMANENT BRIDGE, BRGY. MENDIOLA TO BRGY. HALAYHAYIN, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱33.5M | 100% | Medium risk48 | —-0.060 |
| 31 | 20DP0074CONSTRUCTION OF FOUR (4) STOREY TWELVE (12) CLASSROOM AT SAN FRANCISCO ELEMENTARY SCHOOL, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱38.8M | 100% | Medium risk48 | —-0.050 |
| 32 | 24DI0037WIDENING OF PERMANENT BRIDGES - BAY BR. 2 (B02511LZ) ALONG CALAMBA-STA CRUZ-FAMY JCT RD | Region IV-A | Laguna 2nd DEO | Completed | ₱23.9M | 100% | Medium risk47 | —-0.069 |
| 33 | 23DH0096CONSTRUCTION OF SAN ISIDRO-SUBA BRIDGE IN MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱19.8M | 100% | Medium risk47 | —-0.069 |
| 34 | 22DP0001BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - TERTIARY ROADS - ALUMBRADO BR. (B03137LZ) ALONG CALAUAN-NAGCARLAN BDRY RD | Region IV-A | Laguna 3rd DEO | Completed | ₱15.7M | 100% | Medium risk47 | —-0.067 |
| 35 | 21DP0047BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - TALAHIBING BR. (B03145LZ) ALONG SAN PABLO-RIZAL-NAGCARLAN-LILIW RD | Region IV-A | Laguna 3rd DEO | Completed | ₱21.6M | 100% | Medium risk47 | —-0.067 |
| 36 | 18DH0040CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES, MAYPUTAT BRIDGE (B02488LZ) ALONG RIZAL BDRY.-FAMY-QUEZON ROAD, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱21.7M | 100% | Medium risk47 | —-0.067 |
| 37 | 22DP0004BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - TERTIARY ROADS - MALIKBE BR. (B03136LZ) ALONG CALAUAN-NAGCARLAN BDRY RD | Region IV-A | Laguna 3rd DEO | Completed | ₱8.8M | 100% | Medium risk47 | —-0.066 |
| 38 | 21DP0019BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES MALAUNOD BR. (B02878LZ) ALONG DAANG MAHARLIKA (LZ) | Region IV-A | Laguna 3rd DEO | Completed | ₱27.4M | 100% | Medium risk47 | —-0.069 |
| 39 | 20DP0047ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0087 + 700 - K0088 + 980 | Region IV-A | Laguna 3rd DEO | Completed | ₱45.6M | 100% | Medium risk47 | —-0.104 |
| 40 | 22DP0010BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - TERTIARY ROADS - NAGCARLAN BR. (B03143LZ) ALONG SN PABLO-RIZAL-NAGCARLAN-LILIW RD | Region IV-A | Laguna 3rd DEO | Completed | ₱12M | 100% | Medium risk47 | —-0.067 |
| 41 | 18DP0009ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE OF TERTIARY ROADS, LIPA CITY ALAMINOS RD. K0076 + -835 - K0076 + 965 | Region IV-A | Laguna 3rd DEO | Completed | ₱29.4M | 100% | Medium risk47 | —-0.104 |
| 42 | 19DP0056CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - ASPHALT OVERLAY OF ROAD, BRGY. STA. MARIA, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱35.2M | 100% | Medium risk47 | —-0.109 |
| 43 | 18DH0029CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF BRIDGES INCLUDING ROW TO MORE THAN TWO (2) LANES, PILA BRIDGE (B02465LZ) ALONG CALAMBA-STA. CRUZ-FAMY JUNCTION, PILA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱5.6M | 100% | Medium risk47 | —-0.065 |
| 44 | 22DP0002BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - TERTIARY ROADS - KASAY-AN BR. (B02753LZ) ALONG SN PABLO-DOLORES RD | Region IV-A | Laguna 3rd DEO | Completed | ₱7.2M | 100% | Medium risk47 | —-0.067 |
| 45 | 22D00051CONSTRUCTION OF ACCESS ROAD LEADING TO KALIWA DAMSITE (MARCOS HIGHWAY TO QUEBOROSA), BRGY. MAGSAYSAY, INFANTA, QUEZON | Region IV-A | Region IV-A | Completed | ₱28.9M | 100% | Medium risk47 | —-0.106 |
| 46 | 24D00008SILANGAN ROAD (C.A. YULO AVENUE) CONNECTING SOUTH LUZON EXPRESSWAY LEADING TO THE INDUSTRIAL PARKS, CANLUBANG, CALAMBA CITY, LAGUNA | Region IV-A | Region IV-A | Completed | ₱4.8M | 100% | Medium risk47 | —-0.104 |
| 47 | 24D00096FY 2024 DPWH INFRASTRUCTURE PROGRAM - ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - RIZAL SHRINE RD -K0052+(-695) -K0052+(-625), K0052+512-K0052+633 | Region IV-A | Region IV-A | On-Going | ₱14.2M | 0% | Medium risk47 | —-0.046 |
| 48 | 25DH0019CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CALANGAY RIVER), STA. MARIA RIS, STA. MARIA, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱14.3M | 100% | Medium risk46 | —-0.057 |
| 49 | 20DP0042NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROAD - SAN PABLO- CALAUAN RD. - K0081 + 095 - K0081 + 586, K0081 + 593 - K0082 + 000 | Region IV-A | Laguna 3rd DEO | Completed | ₱26.1M | 100% | Medium risk46 | —-0.109 |
| 50 | 23DI0034REHABILITATION OF ROAD AT BARANGAY PALO-ALTO, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱9.7M | 100% | Medium risk46 | —-0.104 |