Contractor dossier
15 projects on file, including joint ventures this contractor is part of.
Total projects
15
Total budget
₱128.9M
Average progress
86.7%
Completion rate
86.7%
Average risk score
33.9
Medium risk on average, out of 100
Flagged as unusual
2
13.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 15 | ₱128.9M | 33.9 | 2 | 86.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 7 | ₱69.9M | 36.9 | 1 | 85.7% |
| Buildings and Facilities | 4 | ₱9.4M | 13.2 | 0 | 100.0% |
| Flood Control and Drainage | 3 | ₱20.6M | 40.6 | 1 | 66.7% |
| OTHER | 1 | ₱29M | 75.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22EF0009CONSTRUCTION OF MALINAO RIVER FLOOD CONTROL STRUCTURE, STA.0+000-STA.0+234 RIGHT BANK, STA.0+040-STA. 0+240 LEFT BANK, NARRA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱29M | 100% | High risk75 | —-0.009 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22EF0039CONSTRUCTION OF RANSANG RIVER FLOOD CONTROL STRUCTURE, LEFT BANK STA. 0+000-0+083 DOWNSTEAM, STA. 0+102.5- 0+253 UPSTREAM, RIZAL, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱9.9M | 0% | Medium risk42 | Flagged0.032 |
| 22EF0046CONST./IMPROVEMENT OF PANGOBILIAN ROAD LEADING TO MAINIT SEVEN FALLS, BRGY. MAINIT, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱14.7M | 0% | Medium risk39 | Flagged0.016 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 22EF0009CONSTRUCTION OF MALINAO RIVER FLOOD CONTROL STRUCTURE, STA.0+000-STA.0+234 RIGHT BANK, STA.0+040-STA. 0+240 LEFT BANK, NARRA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱29M | 100% | High risk75 | —-0.009 |
| 2 | 22EF0039CONSTRUCTION OF RANSANG RIVER FLOOD CONTROL STRUCTURE, LEFT BANK STA. 0+000-0+083 DOWNSTEAM, STA. 0+102.5- 0+253 UPSTREAM, RIZAL, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱9.9M | 0% | Medium risk42 | Flagged0.032 |
| 3 | 22EF0024CONST. OF MALATGAO RIVER FLOOD CONTROL STRUCTURE, STA. 0+000-STA. 0+094 LEFT RIVERBANK, STA. 0+020-STA. 0+094 RIGHT RIVERBANK, QUEZON, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱5.5M | 100% | Medium risk40 | —-0.037 |
| 4 | 22EF0047CONST. OF TUMARBONG RIVER FLOOD CONTROL STRUCTURE, STA. 0+000-STA. 0+150, QUEZON, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱5.2M | 100% | Medium risk40 | —-0.026 |
| 5 | 22EF0023CONST./IMPROVEMENT OF ACCESS ROAD LEADING TO OGI'S TAU'T BATO CULTURAL COMMUNITY, BRGY. RANSANG, RIZAL, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱11M | 100% | Medium risk40 | —-0.043 |
| 6 | 19EF0060CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO OGIS TAU'T BATO CULTURAL COMMUNITY, BRGY RANSANG, RIZAL, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱11.7M | 100% | Medium risk40 | —-0.064 |
| 7 | 22EF0046CONST./IMPROVEMENT OF PANGOBILIAN ROAD LEADING TO MAINIT SEVEN FALLS, BRGY. MAINIT, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱14.7M | 0% | Medium risk39 | Flagged0.016 |
| 8 | 22EF0006CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD, TABUD ROAD LEADING TO TABUD WATERFALLS, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱9.2M | 100% | Medium risk39 | —-0.060 |
| 9 | 21EF0061CONCRETING OF ABO-ABO-ISUGOD ROAD. QUEZON, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱13M | 100% | Medium risk39 | —-0.066 |
| 10 | 22EF0050CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO LABOG HOTSPRING, BRGY. LABOG, SOFRONIO ESPAÑOLA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱8.3M | 100% | Medium risk38 | —-0.056 |
| 11 | 21EF0062CONCRETING OF ROAD FROM NAT'L. HIGHWAY TO GOV. ABUEG NHS, HEALTH CENTER, SLAUGHTER HOUSE & PUBLIC MARKET, BRGY. BARONG-BARONG, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱2.1M | 100% | Low risk23 | —-0.059 |
| 12 | 22EF0011CONST. OF MULTI-PURPOSE BUILDING BARANGAY IWAHIG, BATARAZA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱3.8M | 100% | Low risk18 | —-0.043 |
| 13 | 21EF0121PARTIAL COMPLETION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), BRGY. IPILAN, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱2M | 100% | Low risk16 | —-0.056 |
| 14 | 22EF0051CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY POB. 1, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱1.8M | 100% | Low risk10 | —-0.046 |
| 15 | 22EF0014CONST. (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. BARONG-BARONG, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱1.8M | 100% | Low risk10 | —-0.060 |