Opening the dossier…
Opening the dossier…
Contractor dossier
450 projects on file, including joint ventures this contractor is part of.
Total projects
450
Total budget
₱28.3B
Average progress
97.0%
Completion rate
81.1%
Average risk score
51.0
Medium risk on average, out of 100
Flagged as unusual
24
5.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 205 | ₱12.5B | 45.2 | 6 | 98.0% |
| Region XI | 163 | ₱11.7B | 55.6 | 14 | 95.7% |
| Region IV-A | 31 | ₱2.1B | 58.0 | 0 | 99.0% |
| National Capital Region | 27 | ₱805.5M | 48.9 | 0 | 100.0% |
| Region I | 11 | ₱569.5M | 67.2 | 3 | 82.9% |
| Region V | 9 | ₱258.8M | 51.5 | 0 | 100.0% |
| Central Office | 2 | ₱259.2M | 71.5 | 0 | 100.0% |
| Region X | 1 | ₱47.5M | 95.4 | 1 | 90.0% |
| Region II | 1 | ₱102.8M | 59.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 255 | ₱17.4B | 52.1 | 5 | 98.0% |
| Flood Control and Drainage | 79 | ₱4.7B | 47.9 | 1 | 97.9% |
| Buildings and Facilities | 50 | ₱1.2B | 39.5 | 1 | 99.2% |
| Bridges | 34 | ₱2B | 44.3 | 1 | 94.0% |
| OTHER | 21 | ₱1.7B | 71.2 | 10 | 91.9% |
| GAA 2025 OO-2 | 4 | ₱527.7M | 92.5 | 2 | 70.6% |
| Bridges, Roads | 3 | ₱456.9M | 66.3 | 0 | 100.0% |
| GAA 2025 OO-1 | 2 | ₱191.1M | 94.3 | 2 | 57.4% |
| GAA 2025 SSP | 1 | ₱47.5M | 95.4 | 1 | 90.0% |
| Water Provision and Storage | 1 | ₱49M | 51.6 | 1 | 76.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25KA0087INSTALLATION OF ROAD SAFETY DEVICES ALONG SAYRE HIGHWAY- K1522+000 - K1525+207BRGY. CABANGAHAN - BRGY. BANGCUD, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | On-Going | ₱47.5M | 90% | High risk95 | Flagged0.001 |
| 25LD0203PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)- K1572+000-K1573+032, K1575+322-K1575+565, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱95.5M | 84% | High risk95 | Flagged0.012 |
| 25LG0081CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- PRES. DIOSDADO P. MACAPAGAL NATL HI-WAY- K1731 + 000 - K1739 +000 | Region XI | Davao Oriental 2nd DEO | On-Going | ₱95.5M | 31% | High risk94 | Flagged0.035 |
| 25LF0102CONSTRUCTION OF FLOOD CONTROL ALONG CATEEL RIVER (TINA SECTION, SAN RAFAEL) CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱143.2M | 40% | High risk93 | Flagged0.023 |
| 25LI0001CONSTRUCTION OF REVETMENT ALONG AGUSAN RIVER, LOWER MAPAWA BRIDGE UPSTREAM, BARANGAY MAPAWA, MARAGUSAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱143.3M | 73% | High risk93 | Flagged0.012 |
| 25CF0002FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PEÑARANDA RIVER (PHASE 1), BARANGAY PAMBUAN, GAPAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | On-Going | ₱96.5M | 75% | High risk92 | —-0.011 |
| 25CE0108CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, BARANGAY POBLACION NORTE, MUNICIPALITY OF RIZAL, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱144.7M | 95% | High risk91 | —-0.006 |
| 24AA0491IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION/CONCRETING OF PASUQUIN-TADAO-BANGUI-DADAOR LOCAL ACCESS ROAD IN PASUQUIN, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱152.8M | 38% | High risk87 | Flagged0.089 |
| 25CL0048CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG GABOR RIVER (SOUTH SIDE), PHASE 1, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱142.7M | 100% | High risk81 | —-0.013 |
| 24CL0002FLOOD CONTROL WORKS ALONG BANCAL - SAN ISIDRO - MAMBOG RIVER (PHASE I), TOTUN LANUM, BARANGAY MAMBOG, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.4M | 100% | High risk81 | —-0.045 |
| 25CL0001CONSTRUCTION OF FLOOD CONTROL AND DRAINAGE STRUCTURE (FCDS) ALONG BANCAL-SAN ISIDRO-MAMBOG RIVER, SECTION 1, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.2M | 89% | High risk81 | —-0.017 |
| 24CL0003FLOOD CONTROL WORKS ALONG BANCAL - SAN ISIDRO - MAMBOG RIVER (PHASE I), TOTUN LANUM, BARANGAY SAN ISIDRO. BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱96M | 100% | High risk81 | —-0.045 |
| 24LI0126ASSET PRESERVATION - REHABILATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BENIGNO S. AQUINO JR. NATIONAL HIGHWAY K 1414+267 - K1414+309, K1414+837 - K1414+847, K1417+000 - K1422+204 | Region XI | Davao de Oro 2nd DEO | On-Going | ₱143.3M | 74% | High risk80 | Flagged0.035 |
| 24CL0017CONSTRUCTION OF FLOOD MITIGATION FACILITY OF BALILI-TAMBAK RIVER (PHASE II), PALANGINAN, IBA, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱96.5M | 100% | High risk80 | —-0.044 |
| 24CF0128SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER (PHASE III), S | Region III | Nueva Ecija 2nd DEO | On-Going | ₱190.1M | 98% | High risk80 | Flagged0.010 |
| 24L00140PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DAVAO - COTABATO RD (DAVAO CITY - JCT. DIGOS SECT) - K1526 + 385 - K1527 + 418, DAVAO CITY | Region XI | Region XI | On-Going | ₱95.5M | 99% | High risk80 | Flagged0.013 |
| 24L00141PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DAVAO - COTABATO RD (DAVAO CITY - JCT. DIGOS SECT) - (S00160MN) K1527 + 418 - K1527 + 813, K1528 + 053 - K1528 + 719, (S00098MN) CHAINAGE 0 - CHAINAGE 95, DAVAO CITY | Region XI | Region XI | On-Going | ₱95.5M | 99% | High risk80 | Flagged0.013 |
| 24L00208PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DIGOS - MAKAR RD - K1581 + 011 - K1584 + 066, DAVAO DEL SUR | Region XI | Region XI | On-Going | ₱95.8M | 98% | High risk80 | Flagged0.014 |
| 24LI0125ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BENIGNO S. AQUINO JR. NATIONAL HIGHWAY- K1422+204-K1425+000 | Region XI | Davao de Oro 2nd DEO | On-Going | ₱107.4M | 67% | High risk79 | Flagged0.030 |
| 24LI0121PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MONTEVISTA - COMPOSTELA - MATI BDRY. RD K1428+000 - K1432+070, K1432+215 - K1434+000, K1478+794 - K1479+555, K1479+588 - K1481+062 (SECTION 1) | Region XI | Davao de Oro 2nd DEO | Completed | ₱144.7M | 100% | High risk79 | Flagged0.002 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AA0491IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION/CONCRETING OF PASUQUIN-TADAO-BANGUI-DADAOR LOCAL ACCESS ROAD IN PASUQUIN, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱152.8M | 38% | High risk87 | Flagged0.089 |
| 24AA0493IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF BRIDGE, BRGY. ESTANCIA, PIDDIG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱39M | 11% | High risk74 | Flagged0.055 |
| 23CL0163CONSTRUCTION OF ACCESS ROAD/DIVERSION ROAD DAANG KALIKASAN TO UACON P1, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱94.6M | 100% | High risk77 | Flagged0.040 |
| 23CL0164CONSTRUCTION OF ACCESS ROAD/DIVERSION ROAD DAANG KALIKASAN TO UACON P2, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱94.6M | 100% | High risk76 | Flagged0.037 |
| 25LG0081CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- PRES. DIOSDADO P. MACAPAGAL NATL HI-WAY- K1731 + 000 - K1739 +000 | Region XI | Davao Oriental 2nd DEO | On-Going | ₱95.5M | 31% | High risk94 | Flagged0.035 |
| 24LI0126ASSET PRESERVATION - REHABILATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BENIGNO S. AQUINO JR. NATIONAL HIGHWAY K 1414+267 - K1414+309, K1414+837 - K1414+847, K1417+000 - K1422+204 | Region XI | Davao de Oro 2nd DEO | On-Going | ₱143.3M | 74% | High risk80 | Flagged0.035 |
| 24LI0125ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BENIGNO S. AQUINO JR. NATIONAL HIGHWAY- K1422+204-K1425+000 | Region XI | Davao de Oro 2nd DEO | On-Going | ₱107.4M | 67% | High risk79 | Flagged0.030 |
| 23LA0119ASSET PRESERVATION - PREVENTIVE MAINTENANCE- PRIMARY ROADS, DAANG MAHARLIKA (S00126MN), K1431+818.000 - K1433+679.000 | Region XI | Davao de Oro 1st DEO | On-Going | ₱94.7M | 97% | High risk64 | Flagged0.030 |
| 23AA0497CONSTRUCTION OF SEAWALL ALONG PASALENG BAY, BRGY. PASALENG, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱45.7M | 100% | High risk71 | Flagged0.025 |
| 24C00615STATE UNIVERSITIES AND COLLEGES (SUCS)-CONSTRUCTION OF MULTI-PURPOSE BUILDING, PRESIDENT RAMON MAGSAYSAY STATE UNIVERSITY, IBA, ZAMBALES, PROVINCE OF ZAMBALES | Region III | Region III | On-Going | ₱49.3M | 60% | High risk62 | Flagged0.023 |
| 25LF0102CONSTRUCTION OF FLOOD CONTROL ALONG CATEEL RIVER (TINA SECTION, SAN RAFAEL) CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱143.2M | 40% | High risk93 | Flagged0.023 |
| 24L00231INSTALLATION OF SOLAR LIGHTS ALONG TAGUM-PANABO CIRCUM RD. K1510+000 - K1514+000 | Region XI | Region XI | On-Going | ₱47.8M | 69% | High risk76 | Flagged0.018 |
| 24LC0066TAGUM CITY DIVERSION ROAD K1455+(-573) - K1456+135, K1461+090 - K1461+115, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | On-Going | ₱88.5M | 87% | High risk77 | Flagged0.018 |
| 24L00208PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DIGOS - MAKAR RD - K1581 + 011 - K1584 + 066, DAVAO DEL SUR | Region XI | Region XI | On-Going | ₱95.8M | 98% | High risk80 | Flagged0.014 |
| 24L00140PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DAVAO - COTABATO RD (DAVAO CITY - JCT. DIGOS SECT) - K1526 + 385 - K1527 + 418, DAVAO CITY | Region XI | Region XI | On-Going | ₱95.5M | 99% | High risk80 | Flagged0.013 |
| 24L00141PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DAVAO - COTABATO RD (DAVAO CITY - JCT. DIGOS SECT) - (S00160MN) K1527 + 418 - K1527 + 813, K1528 + 053 - K1528 + 719, (S00098MN) CHAINAGE 0 - CHAINAGE 95, DAVAO CITY | Region XI | Region XI | On-Going | ₱95.5M | 99% | High risk80 | Flagged0.013 |
| 25LI0001CONSTRUCTION OF REVETMENT ALONG AGUSAN RIVER, LOWER MAPAWA BRIDGE UPSTREAM, BARANGAY MAPAWA, MARAGUSAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱143.3M | 73% | High risk93 | Flagged0.012 |
| 25LD0203PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)- K1572+000-K1573+032, K1575+322-K1575+565, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱95.5M | 84% | High risk95 | Flagged0.012 |
| 24CF0128SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER (PHASE III), S | Region III | Nueva Ecija 2nd DEO | On-Going | ₱190.1M | 98% | High risk80 | Flagged0.010 |
| 24CD0306ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE PRIMARY ROADS ASHPHALT OVERLAY ALONG GEN. ALEJO SANTOS HIGHWAY K0069+484 K0071+471 NORZAGARAY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱93.6M | 100% | High risk70 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 326 | 22LA0178CONCRETING OF STA. TERESA, BRGY. MAGNAGA TO TUGOP, BRGY. KINGKING FMR PHASE II, BRGY. KINGKING, PANTUKAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱11.9M | 100% | Medium risk41 | —-0.031 |
| 327 | 23CL0003ROAD WIDENING-SECONDARY ROADS, OLONGAPO-BUGALLON RD - K0158 + 640 - K0161 + 000 , SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱69.2M | 99% | Medium risk41 | —-0.050 |
| 328 | 23CL0121CONSTRUCTION OF 3-STOREY MULTI-PURPOSE BUILDING, POLYTECHNIC COLLEGE OF BOTOLAN, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱48.7M | 99% | Medium risk41 | —-0.048 |
| 329 | 23CF0072ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) - K0107+532-K0109+469 | Region III | Nueva Ecija 2nd DEO | Completed | ₱90.4M | 100% | Medium risk41 | —-0.091 |
| 330 | 17LA0031WIDENING OF BONGABONG BRIDGE (B00201MN) INCLUDING APPROACHES, PANTUKAN ALONG SURIGAO-DAVAO COASTAL ROAD, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱20.3M | 98% | Medium risk41 | —-0.026 |
| 331 | 23CL0153CONSTRUCTION OF MULTI-PURPOSE BUILDING, PRMSU CAMPUS, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱48.1M | 99% | Medium risk41 | —-0.052 |
| 332 | 21LA0238CONSTRUCTION (COMPLETION) OF ONE (1) UNIT, TWO (2) STOREY, SIX (6) CLASSROOM SCHOOL BUILDING AT CONCEPTION ES, MACO, COMPOSTELA VALLEY | Region XI | Davao de Oro 1st DEO | Completed | ₱25.8M | 100% | Medium risk41 | —-0.036 |
| 333 | 23CL0120PREVENTIVE MAINTENANCE - SECONDARY ROADS OLONGAPO-BUGALLON RD - K0236 + 000 - K0238 + 00, K0240 + 479 - K0241 + 352, K0241 + 352 - K0242 + 524, MASINLOC & CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱56.7M | 100% | Medium risk40 | —-0.088 |
| 334 | 23CL0056PREVENTIVE MAINTENANCE-TERTIARY ROADS AMUNGAN-PALAUIG-BANLOG RD - K0211 + (-831) - K0211 + (-473), K0211 + (-250) - K0212 + 478, K0219 + 890 - K0221 + 740, K0223 + 488 - K0223 + 951, IBA & PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱60.2M | 100% | Medium risk40 | —-0.091 |
| 335 | 21CF0150CONSTRUCTION OF NUEVA ECIJA 2ND DISTRICT ENGINEERING OFFICE BUILDING, CABANATUAN CITY | Region III | Nueva Ecija 2nd DEO | Completed | ₱51.7M | 100% | Medium risk39 | —-0.098 |
| 336 | 18CF0065ASSET PRESERVATION PROGRAM -REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - STA. ROSA - FORT MAGSAYSAY ROAD - K0108+(-520)-K0109+481.50, K0118+708.80 - K0120+646 | Region III | Nueva Ecija 2nd DEO | Completed | ₱65.2M | 100% | Medium risk39 | —-0.101 |
| 337 | 25CJ0144REHABILITATION OF TARLAC CITY SOUTHWEST DIVERSION ROAD (SEGMENT 1), TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱74.3M | 100% | Medium risk38 | —-0.095 |
| 338 | 22CF0062ASSET PRESERVATION PROGRAM - CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - CABANATUAN CITY CIRCUMFERENTIAL RD - K0113+(-166)-K0113+172, K0113+187-K0113+364, K0114+361-K0115+541 | Region III | Nueva Ecija 2nd DEO | Completed | ₱61.3M | 100% | Medium risk38 | —-0.100 |
| 339 | 24C00598ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS, DAANG MAHARLIKA (LZ), PROVINCE OF NUEVA ECIJA | Region III | Region III | Completed | ₱65.8M | 100% | Medium risk38 | —-0.100 |
| 340 | 23CL0125CONSTRUCTION (IMPROVEMENT) OF ROADS INCLUDING BIKES LANES AND ROAD SAFETY DEVICES ALONG SECONDARY ROAD, OLONGAPO - BUGALLON ROAD, K0 182+823 - K0 185+072, K0 172+025 - K0 175+484, SAN FELIPE & CABANGAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱49M | 100% | Medium risk38 | —-0.095 |
| 341 | 24CL0014CONSTRUCTION OF FLOOD CONTROL TAUGTOG - MAMBOG - BANCAL RIVER PHASE 1-A, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱86.8M | 100% | Medium risk38 | —-0.076 |
| 342 | 23CF0073ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0087+542-K0089+227 | Region III | Nueva Ecija 2nd DEO | Completed | ₱77.2M | 100% | Medium risk38 | —-0.095 |
| 343 | 23CF0049ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0090+915-K0092+617 | Region III | Nueva Ecija 2nd DEO | Completed | ₱58.4M | 100% | Medium risk38 | —-0.099 |
| 344 | 25CF0083ASSET PRESERVATION PROGRAM REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - STA ROSA - TARLAC RD - K0108+640-K0108+800, K0110+000-K0110+277, K0110+326-K0110+1009, K0110+1046-K0110+1274, K0111+000-K0111+100, K0114+000- | Region III | Nueva Ecija 2nd DEO | Completed | ₱73.6M | 100% | Medium risk38 | —-0.099 |
| 345 | 25CJ0210INSTALLATION OF ROAD SAFETY DEVICES AND SOLAR LED STREET LIGHTS ALONG CAMPOSANTO 1 - NORTE - TUBECTUBANG ROAD TO MANILA NORTH RD (ANNEX 2), MONCADO, TARLAC | Region III | Tarlac DEO | Completed | ₱47.3M | 100% | Medium risk38 | —-0.098 |
| 346 | 18CH0082CONSTRUCTION OF ROAD DIKE LEADING TO BANCAL PUGAD, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱49M | 100% | Medium risk38 | —-0.101 |
| 347 | 25CJ0022REHABILITATION OF SAN SEBASTIAN - BALETE DIVERSION ROAD (SEGMENT 1), TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱74.3M | 100% | Medium risk38 | —-0.096 |
| 348 | 19CF0023ASSET PRESERVATION -PREVENTIVE MAINTENANCE - PRIMARY ROADS, STA. ROSA- TARLAC RD, K0113+837.00 - K0117+723.00 | Region III | Nueva Ecija 2nd DEO | Completed | ₱61.9M | 100% | Medium risk38 | —-0.100 |
| 349 | 23CJ0174SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 IMPROVEMENT OF ROADS AND INSTALLATION OF ROAD SAFETY DEVICES ALONG ACCESS ROAD LEADING TO TARLAC ECOTOURISM PARK (PACKAGE C), SAN JOSE, TARLAC | Region III | Tarlac DEO | Completed | ₱50.7M | 100% | Medium risk37 | —-0.100 |
| 350 | 23CJ0171SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 IMPROVEMENT OF ROADS AND INSTALLATION OF ROAD SAFETY DEVICES ALONG ACCESS ROAD LEADING TO TARLAC ECOTOURISM PARK (PACKAGE A), SAN JOSE, TARLAC | Region III | Tarlac DEO | Completed | ₱49.6M | 100% | Medium risk37 | —-0.100 |