Contractor dossier
450 projects on file, including joint ventures this contractor is part of.
Total projects
450
Total budget
₱28.3B
Average progress
97.0%
Completion rate
81.1%
Average risk score
51.0
Medium risk on average, out of 100
Flagged as unusual
24
5.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 205 | ₱12.5B | 45.2 | 6 | 98.0% |
| Region XI | 163 | ₱11.7B | 55.6 | 14 | 95.7% |
| Region IV-A | 31 | ₱2.1B | 58.0 | 0 | 99.0% |
| National Capital Region | 27 | ₱805.5M | 48.9 | 0 | 100.0% |
| Region I | 11 | ₱569.5M | 67.2 | 3 | 82.9% |
| Region V | 9 | ₱258.8M | 51.5 | 0 | 100.0% |
| Central Office | 2 | ₱259.2M | 71.5 | 0 | 100.0% |
| Region X | 1 | ₱47.5M | 95.4 | 1 | 90.0% |
| Region II | 1 | ₱102.8M | 59.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 255 | ₱17.4B | 52.1 | 5 | 98.0% |
| Flood Control and Drainage | 79 | ₱4.7B | 47.9 | 1 | 97.9% |
| Buildings and Facilities | 50 | ₱1.2B | 39.5 | 1 | 99.2% |
| Bridges | 34 | ₱2B | 44.3 | 1 | 94.0% |
| OTHER | 21 | ₱1.7B | 71.2 | 10 | 91.9% |
| GAA 2025 OO-2 | 4 | ₱527.7M | 92.5 | 2 | 70.6% |
| Bridges, Roads | 3 | ₱456.9M | 66.3 | 0 | 100.0% |
| GAA 2025 OO-1 | 2 | ₱191.1M | 94.3 | 2 | 57.4% |
| GAA 2025 SSP | 1 | ₱47.5M | 95.4 | 1 | 90.0% |
| Water Provision and Storage | 1 | ₱49M | 51.6 | 1 | 76.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25KA0087INSTALLATION OF ROAD SAFETY DEVICES ALONG SAYRE HIGHWAY- K1522+000 - K1525+207BRGY. CABANGAHAN - BRGY. BANGCUD, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | On-Going | ₱47.5M | 90% | High risk95 | Flagged0.001 |
| 25LD0203PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)- K1572+000-K1573+032, K1575+322-K1575+565, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱95.5M | 84% | High risk95 | Flagged0.012 |
| 25LG0081CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- PRES. DIOSDADO P. MACAPAGAL NATL HI-WAY- K1731 + 000 - K1739 +000 | Region XI | Davao Oriental 2nd DEO | On-Going | ₱95.5M | 31% | High risk94 | Flagged0.035 |
| 25LF0102CONSTRUCTION OF FLOOD CONTROL ALONG CATEEL RIVER (TINA SECTION, SAN RAFAEL) CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱143.2M | 40% | High risk93 | Flagged0.023 |
| 25LI0001CONSTRUCTION OF REVETMENT ALONG AGUSAN RIVER, LOWER MAPAWA BRIDGE UPSTREAM, BARANGAY MAPAWA, MARAGUSAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱143.3M | 73% | High risk93 | Flagged0.012 |
| 25CF0002FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PEÑARANDA RIVER (PHASE 1), BARANGAY PAMBUAN, GAPAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | On-Going | ₱96.5M | 75% | High risk92 | —-0.011 |
| 25CE0108CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, BARANGAY POBLACION NORTE, MUNICIPALITY OF RIZAL, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱144.7M | 95% | High risk91 | —-0.006 |
| 24AA0491IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION/CONCRETING OF PASUQUIN-TADAO-BANGUI-DADAOR LOCAL ACCESS ROAD IN PASUQUIN, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱152.8M | 38% | High risk87 | Flagged0.089 |
| 25CL0048CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG GABOR RIVER (SOUTH SIDE), PHASE 1, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱142.7M | 100% | High risk81 | —-0.013 |
| 24CL0002FLOOD CONTROL WORKS ALONG BANCAL - SAN ISIDRO - MAMBOG RIVER (PHASE I), TOTUN LANUM, BARANGAY MAMBOG, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.4M | 100% | High risk81 | —-0.045 |
| 25CL0001CONSTRUCTION OF FLOOD CONTROL AND DRAINAGE STRUCTURE (FCDS) ALONG BANCAL-SAN ISIDRO-MAMBOG RIVER, SECTION 1, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.2M | 89% | High risk81 | —-0.017 |
| 24CL0003FLOOD CONTROL WORKS ALONG BANCAL - SAN ISIDRO - MAMBOG RIVER (PHASE I), TOTUN LANUM, BARANGAY SAN ISIDRO. BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱96M | 100% | High risk81 | —-0.045 |
| 24LI0126ASSET PRESERVATION - REHABILATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BENIGNO S. AQUINO JR. NATIONAL HIGHWAY K 1414+267 - K1414+309, K1414+837 - K1414+847, K1417+000 - K1422+204 | Region XI | Davao de Oro 2nd DEO | On-Going | ₱143.3M | 74% | High risk80 | Flagged0.035 |
| 24CL0017CONSTRUCTION OF FLOOD MITIGATION FACILITY OF BALILI-TAMBAK RIVER (PHASE II), PALANGINAN, IBA, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱96.5M | 100% | High risk80 | —-0.044 |
| 24CF0128SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER (PHASE III), S | Region III | Nueva Ecija 2nd DEO | On-Going | ₱190.1M | 98% | High risk80 | Flagged0.010 |
| 24L00140PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DAVAO - COTABATO RD (DAVAO CITY - JCT. DIGOS SECT) - K1526 + 385 - K1527 + 418, DAVAO CITY | Region XI | Region XI | On-Going | ₱95.5M | 99% | High risk80 | Flagged0.013 |
| 24L00141PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DAVAO - COTABATO RD (DAVAO CITY - JCT. DIGOS SECT) - (S00160MN) K1527 + 418 - K1527 + 813, K1528 + 053 - K1528 + 719, (S00098MN) CHAINAGE 0 - CHAINAGE 95, DAVAO CITY | Region XI | Region XI | On-Going | ₱95.5M | 99% | High risk80 | Flagged0.013 |
| 24L00208PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DIGOS - MAKAR RD - K1581 + 011 - K1584 + 066, DAVAO DEL SUR | Region XI | Region XI | On-Going | ₱95.8M | 98% | High risk80 | Flagged0.014 |
| 24LI0125ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BENIGNO S. AQUINO JR. NATIONAL HIGHWAY- K1422+204-K1425+000 | Region XI | Davao de Oro 2nd DEO | On-Going | ₱107.4M | 67% | High risk79 | Flagged0.030 |
| 24LI0121PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MONTEVISTA - COMPOSTELA - MATI BDRY. RD K1428+000 - K1432+070, K1432+215 - K1434+000, K1478+794 - K1479+555, K1479+588 - K1481+062 (SECTION 1) | Region XI | Davao de Oro 2nd DEO | Completed | ₱144.7M | 100% | High risk79 | Flagged0.002 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AA0491IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION/CONCRETING OF PASUQUIN-TADAO-BANGUI-DADAOR LOCAL ACCESS ROAD IN PASUQUIN, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱152.8M | 38% | High risk87 | Flagged0.089 |
| 24AA0493IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF BRIDGE, BRGY. ESTANCIA, PIDDIG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱39M | 11% | High risk74 | Flagged0.055 |
| 23CL0163CONSTRUCTION OF ACCESS ROAD/DIVERSION ROAD DAANG KALIKASAN TO UACON P1, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱94.6M | 100% | High risk77 | Flagged0.040 |
| 23CL0164CONSTRUCTION OF ACCESS ROAD/DIVERSION ROAD DAANG KALIKASAN TO UACON P2, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱94.6M | 100% | High risk76 | Flagged0.037 |
| 25LG0081CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- PRES. DIOSDADO P. MACAPAGAL NATL HI-WAY- K1731 + 000 - K1739 +000 | Region XI | Davao Oriental 2nd DEO | On-Going | ₱95.5M | 31% | High risk94 | Flagged0.035 |
| 24LI0126ASSET PRESERVATION - REHABILATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BENIGNO S. AQUINO JR. NATIONAL HIGHWAY K 1414+267 - K1414+309, K1414+837 - K1414+847, K1417+000 - K1422+204 | Region XI | Davao de Oro 2nd DEO | On-Going | ₱143.3M | 74% | High risk80 | Flagged0.035 |
| 24LI0125ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BENIGNO S. AQUINO JR. NATIONAL HIGHWAY- K1422+204-K1425+000 | Region XI | Davao de Oro 2nd DEO | On-Going | ₱107.4M | 67% | High risk79 | Flagged0.030 |
| 23LA0119ASSET PRESERVATION - PREVENTIVE MAINTENANCE- PRIMARY ROADS, DAANG MAHARLIKA (S00126MN), K1431+818.000 - K1433+679.000 | Region XI | Davao de Oro 1st DEO | On-Going | ₱94.7M | 97% | High risk64 | Flagged0.030 |
| 23AA0497CONSTRUCTION OF SEAWALL ALONG PASALENG BAY, BRGY. PASALENG, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱45.7M | 100% | High risk71 | Flagged0.025 |
| 24C00615STATE UNIVERSITIES AND COLLEGES (SUCS)-CONSTRUCTION OF MULTI-PURPOSE BUILDING, PRESIDENT RAMON MAGSAYSAY STATE UNIVERSITY, IBA, ZAMBALES, PROVINCE OF ZAMBALES | Region III | Region III | On-Going | ₱49.3M | 60% | High risk62 | Flagged0.023 |
| 25LF0102CONSTRUCTION OF FLOOD CONTROL ALONG CATEEL RIVER (TINA SECTION, SAN RAFAEL) CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱143.2M | 40% | High risk93 | Flagged0.023 |
| 24L00231INSTALLATION OF SOLAR LIGHTS ALONG TAGUM-PANABO CIRCUM RD. K1510+000 - K1514+000 | Region XI | Region XI | On-Going | ₱47.8M | 69% | High risk76 | Flagged0.018 |
| 24LC0066TAGUM CITY DIVERSION ROAD K1455+(-573) - K1456+135, K1461+090 - K1461+115, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | On-Going | ₱88.5M | 87% | High risk77 | Flagged0.018 |
| 24L00208PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DIGOS - MAKAR RD - K1581 + 011 - K1584 + 066, DAVAO DEL SUR | Region XI | Region XI | On-Going | ₱95.8M | 98% | High risk80 | Flagged0.014 |
| 24L00140PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DAVAO - COTABATO RD (DAVAO CITY - JCT. DIGOS SECT) - K1526 + 385 - K1527 + 418, DAVAO CITY | Region XI | Region XI | On-Going | ₱95.5M | 99% | High risk80 | Flagged0.013 |
| 24L00141PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - DAVAO - COTABATO RD (DAVAO CITY - JCT. DIGOS SECT) - (S00160MN) K1527 + 418 - K1527 + 813, K1528 + 053 - K1528 + 719, (S00098MN) CHAINAGE 0 - CHAINAGE 95, DAVAO CITY | Region XI | Region XI | On-Going | ₱95.5M | 99% | High risk80 | Flagged0.013 |
| 25LI0001CONSTRUCTION OF REVETMENT ALONG AGUSAN RIVER, LOWER MAPAWA BRIDGE UPSTREAM, BARANGAY MAPAWA, MARAGUSAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱143.3M | 73% | High risk93 | Flagged0.012 |
| 25LD0203PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)- K1572+000-K1573+032, K1575+322-K1575+565, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱95.5M | 84% | High risk95 | Flagged0.012 |
| 24CF0128SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER (PHASE III), S | Region III | Nueva Ecija 2nd DEO | On-Going | ₱190.1M | 98% | High risk80 | Flagged0.010 |
| 24CD0306ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE PRIMARY ROADS ASHPHALT OVERLAY ALONG GEN. ALEJO SANTOS HIGHWAY K0069+484 K0071+471 NORZAGARAY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱93.6M | 100% | High risk70 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 401 | 22CF0121SPECIAL ROAD FUND-MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239-REPAIR/REHAB./IMPRVT ALONG DAANG MAHARLIKA (LZ)-K0104+171.00, K0104+252.60, K0104+313.70-K0104+322.80, K0104+446.90-K0104+491.90, K0104+653.00-K0104+671.50, K010 | Region III | Nueva Ecija 2nd DEO | Completed | ₱21.7M | 100% | Medium risk32 | —-0.103 |
| 402 | 22CF0027ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - BANGAD - FORT MAGSAYSAY RD - K0125+000-K0125+715, K0126+102-K0126+432.55 | Region III | Nueva Ecija 2nd DEO | Completed | ₱15.6M | 100% | Medium risk32 | —-0.101 |
| 403 | 20CF0071CONSTRUCTION OF CORONEL RIVER FLOOD CONTROL, BRGY. BAGONG SIKAT, GABALDON, NUEVA ECIJA, STA. 30+162.18 - STA. 30+836.18 | Region III | Nueva Ecija 2nd DEO | Completed | ₱38.1M | 100% | Medium risk32 | —-0.090 |
| 404 | 19CF0056CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS, CORONEL RIVER FLOOD CONTROL, BRGY. BAGONG SIKAT, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱38.1M | 100% | Medium risk32 | —-0.092 |
| 405 | 23CF0021ASSET PRESERVATION PROGRAM - REHABILITATION / ECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - GAPAN-FORT MAGSAYSAY RD., K0095+000-K0096+000, K0096+604-K0096+740.37 | Region III | Nueva Ecija 2nd DEO | Completed | ₱17M | 100% | Medium risk32 | —-0.106 |
| 406 | 23CE0098CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BARANGAY II, QUEZON, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱9.9M | 100% | Medium risk32 | —-0.104 |
| 407 | 19CF0001REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES, BATO FERRY BR. (B01337LZ) ALONG JCT. TABLANG - GABALDON RD. | Region III | Nueva Ecija 2nd DEO | Completed | ₱9.7M | 100% | Medium risk31 | —-0.064 |
| 408 | 19CF0043CONCRETING OF ROAD WITH SLOPE PROTECTION, TABON-STO. CRISTO NORTE ROAD, PHASE II, GAPAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱14.9M | 100% | Medium risk31 | —-0.105 |
| 409 | 19CF0002RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, CABU BR. (B00117LZ) ALONG NUEVA ECIJA -AURORA RD. | Region III | Nueva Ecija 2nd DEO | Completed | ₱14.7M | 100% | Medium risk31 | —-0.064 |
| 410 | 23CF0023CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - SAN LEONARDO - JAEN - SAN ISIDRO BYPASS ROAD, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱14.3M | 100% | Medium risk31 | —-0.104 |
| 411 | 21CF0089CONSTRUCTION OF CORONEL RIVER FLOOD, STA.0+000.00 - STA.0+637.00, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱44.6M | 100% | Medium risk31 | —-0.089 |
| 412 | 19CF0060REHABILITATION / MAJOR REPAIR OF FLOOD CONTROL STRUCTURE -REHABILITATION OF DIGMALA RIVER (PHASE I) DIGMALA SECTION, BONGABON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱29.1M | 100% | Medium risk31 | —-0.087 |
| 413 | 23CL0006REPLACEMENT OF PERMANENT WEAK BRIDGES, BANGAR BR. (B01394LZ) ALONG OLONGAPO-BUGALLON RD, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱37.6M | 100% | Medium risk31 | —-0.059 |
| 414 | 19CF0092RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE, PEÑARANDA BR. (B01344LZ) ALONG GAPAN-FORT MAGSAYSAY RD. K0104+141 - K104+461.20 | Region III | Nueva Ecija 2nd DEO | Completed | ₱14.9M | 100% | Medium risk31 | —-0.066 |
| 415 | 23CF0060CONSTRUCTION OF ROADS, BARANGAY MACABAKLAY, GAPAN NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱11.7M | 100% | Medium risk31 | —-0.105 |
| 416 | 23CL0009WIDENING OF PERMANENT BRIDGES- DALAYAP BR.1 (B01406LZ) ALONG OLONGAPO-BUGALLON RD, CABANGAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱11.2M | 100% | Medium risk31 | —-0.024 |
| 417 | 23CL0009WIDENING OF PERMANENT BRIDGES- DALAYAP BR.1 (B01406LZ) ALONG OLONGAPO-BUGALLON RD, CABANGAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱11.2M | 100% | Medium risk31 | —-0.024 |
| 418 | 19CK0006BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES: BAMBAN OVERHEAD BR. (B02686LZ) ALONG MANILA NORTH ROAD, BAMBAN, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱34M | 100% | Medium risk30 | —-0.065 |
| 419 | 19CF0074CONSTRUCTION OF SLOPE PROTECTION STRUCTURE -CONSTRUCTION OF SLOPE PROTECTION/ FLOOD CONTROL PEÑARANDA RIVER, BRGY. SAN JOSEPH, PEÑARANDA, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱29.3M | 100% | Medium risk30 | —-0.090 |
| 420 | 22CF0120ASSET PRESERVATION PROGRAM-REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS-TERTIARY RD.-STA. ROSA-FORT MAGSAYSAY RD - K0110+147.40-K0110+320.30, K0110+370.50-K0110+393.00, K0110+456.00-K0110+460.50, K0110+518.50-K0110+613.50, K | Region III | Nueva Ecija 2nd DEO | Completed | ₱5.4M | 100% | Low risk30 | —-0.102 |
| 421 | 22CF0088NETWORK DEVELOPMENT PROGRAM - OFF - CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - DAANG MAHARLIKA (LZ) K0104+740 | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.8M | 100% | Low risk30 | —-0.106 |
| 422 | 18CF0075CONSTRUCTION OF PAMPANGA RIVER BANK, BRGY. SAN PABLO, JAEN, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱19M | 100% | Low risk30 | —-0.092 |
| 423 | 23CF0081CONSTRUCTION (IMPROVEMENT) OF DRAINAGE STRUCTURE, BARANGAY SAN LORENZO, GAPAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱19.6M | 100% | Low risk30 | —-0.093 |
| 424 | 20CK0024BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES: BAMBAN OVERHEAD BR. (B02686LZ) ALONG MANILA NORTH ROAD, BAMBAN, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱10.8M | 100% | Low risk30 | —-0.062 |
| 425 | 21CE0026CONCRETING OF ROAD, STO. CRISTO - DOÑA LUCIA, QUEZON, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱9.7M | 100% | Low risk30 | —-0.103 |