Opening the dossier…
Opening the dossier…
Contractor dossier
202 projects on file, including joint ventures this contractor is part of.
Total projects
202
Total budget
₱9.4B
Average progress
90.8%
Completion rate
85.1%
Average risk score
40.0
Medium risk on average, out of 100
Flagged as unusual
10
5.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 166 | ₱6.7B | 36.0 | 7 | 94.8% |
| National Capital Region | 20 | ₱1.5B | 55.4 | 0 | 70.0% |
| Region IV-B | 6 | ₱405.3M | 70.9 | 3 | 78.8% |
| Region I | 5 | ₱238.1M | 52.4 | 0 | 51.6% |
| Region IV-A | 4 | ₱342.1M | 58.7 | 0 | 95.3% |
| Region V | 1 | ₱227.4M | 69.5 | 0 | 94.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 66 | ₱2.5B | 35.6 | 2 | 86.2% |
| Roads | 60 | ₱2.7B | 38.7 | 0 | 94.0% |
| Flood Control and Drainage | 51 | ₱3.1B | 40.0 | 1 | 96.8% |
| Bridges | 12 | ₱414.5M | 40.2 | 2 | 82.3% |
| OTHER | 5 | ₱183.5M | 64.7 | 0 | 100.0% |
| GAA 2025 SSP | 4 | ₱283.7M | 94.3 | 4 | 51.8% |
| Water Provision and Storage | 3 | ₱159.4M | 43.3 | 1 | 92.1% |
| Bridges, Roads | 1 | ₱95.2M | 51.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CN0064CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NORTH POBLACION, DIPACULAO, AURORA | Region III | Aurora DEO | On-Going | ₱97.1M | 34% | High risk96 | Flagged0.024 |
| 25ED0165CONSTRUCTION OF SAN AGUSTIN BRIDGE (PUBLIC MARKET), BARANGAY IBABA EAST,CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱57M | 48% | High risk94 | Flagged0.023 |
| 25ED0166CONSTRUCTION OF BRIDGE, BARANGAY PERSONAS, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱42.8M | 82% | High risk94 | Flagged0.011 |
| 25ED0110CONSTRUCTION OF ROAD, BARANGAY BULUSAN TO BARANGAY BONDOC, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱86.8M | 43% | High risk93 | Flagged0.030 |
| 22C00098CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF WATER SUPPLY SYSTEM IN PALAYAN CITY, NUEVA ECIJA, PROVINCE OF NUEVA ECIJA | Region III | Region III | On-Going | ₱145.5M | 76% | High risk79 | Flagged0.023 |
| 24C00180FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF ABITONAN RIVER FLOOD CONTROL STRUCTURE, DIPACULAO, AURORA, PROVINCE OF AURORA | Region III | Region III | Completed | ₱169.8M | 100% | High risk77 | —-0.030 |
| 25C00505CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RDS. LEAD. TO MAJ./STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF DONA REMEDIOS TRINIDAD NORZAGARAY SAN JOSE RD. (DRT SECT.), NORZAGARAY, BUL | Region III | Region III | On-Going | ₱95.1M | 0% | High risk75 | Flagged0.019 |
| 24C00644CONVERGENCE & SPL. SUPPORT PROG.-BASIC INFRA PROG.-ACCESS RD. & OR BRS. FR. THE NAT'L. RDS. LEAD. TO MAJ. STRAT. PUBLIC BLDGS./FACILITIES: 1. CONST. OF BRGY. BAYABAS-IPIL RD. 2. CONST. OF BRGY. MUCDOL-SALAY RD. 3. CONST. OF RD. GUPA-DITALE, ALL AT DIPACUL | Region III | Region III | On-Going | ₱146.3M | 20% | High risk74 | —-0.001 |
| 24CC0231CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY STO. NINO, PANDI, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.7M | 100% | High risk74 | —-0.074 |
| 18CF0141ASSET PRESERVATION PROGRAM -REHABILITATION/RECONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - NUEVA ECIJA - AURORA RD- K0156+100 - K0156+260, K0160+600 -K0161+050 | Region III | Nueva Ecija 2nd DEO | Completed | ₱96.5M | 100% | High risk73 | —-0.056 |
| 21CF0172NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0094 + 272.10 - K0094 + 842.60, K0094 + 866.60 - K0095 + 400.00 | Region III | Nueva Ecija 2nd DEO | Completed | ₱95.7M | 100% | High risk72 | —-0.029 |
| 22C00045CONVERGENCE & SPECIAL SUPPORT PROGRAM-CONST./IMPR'VT. OF VARIOUS INFRA IN SUPPORT OF NAT'L/ SECURITY-(TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS), CONST. OF ARMY LEADERSHIP DEV'T. EDCU. CENTER (ALDEC) MPB, TRADOC, PA, CAMP O DON | Region III | Region III | Completed | ₱9.6M | 100% | High risk71 | —-0.068 |
| 25C00480CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROAD S THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONST. OF BYPASS ROAD (PHASE 10) AT DONA REMEDIOS TRINIDAD TO SAN JOSE DEL MONTE | Region III | Region III | On-Going | ₱71.3M | 1% | High risk70 | Flagged0.014 |
| 24CK0176REHABILITATION OF DIKE ALONG LUCUNG RIVER BARANGAY SANTO NINO SECTION, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱96.5M | 86% | High risk70 | Flagged0.023 |
| 21F00089LOCAL PROGRAM: BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-CONSTRUCTION OF THE MULTI-PURPOSE BUILDING (NEW PILI PUBLIC MARKET),OLD SAN ROQUE, PILI | Region V | Region V | On-Going | ₱227.4M | 94% | High risk70 | —-0.011 |
| 25CN0160CONTRUCTION OF BAYANIHAN - QUIRINO ROAD, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱48M | 1% | High risk69 | —-0.016 |
| 24C00376ASSET PRESERVATION PROGRAM-CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-PRIMARY ROADS, DAANG MAHARLIKA (LZ), PROVINCE OF NUEVA ECIJA | Region III | Region III | On-Going | ₱40.5M | 57% | High risk69 | —-0.024 |
| 17CF0044ASSET PRESERVATION OF NATIONAL ROADS (ARTERIAL), REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT- 4 (HDM-4) PRIMARY ROADS, JOSE ABAD SANTOS | Region III | Nueva Ecija 2nd DEO | Completed | ₱7.4M | 100% | High risk68 | —-0.070 |
| 25OC0120CONSTRUCTION OF DRAINAGE MAIN ALONG DR. A. SANTOS AVENUE, DISTRICT 1,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱141.9M | 0% | High risk67 | —-0.011 |
| 24OF0160CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 4) MEDICAL CENTER, AT BRGY. TANDANG SORA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱147.2M | 24% | High risk66 | —-0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24C00638DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU-BRGY. CRISTO REY, CAPAS MEGA RURAL HEALTH UNIT, PROVINCE OF TARLAC | Region III | Region III | On-Going | ₱29.6M | 0% | Medium risk54 | Flagged0.036 |
| 25ED0110CONSTRUCTION OF ROAD, BARANGAY BULUSAN TO BARANGAY BONDOC, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱86.8M | 43% | High risk93 | Flagged0.030 |
| 25CN0064CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NORTH POBLACION, DIPACULAO, AURORA | Region III | Aurora DEO | On-Going | ₱97.1M | 34% | High risk96 | Flagged0.024 |
| 24CK0176REHABILITATION OF DIKE ALONG LUCUNG RIVER BARANGAY SANTO NINO SECTION, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱96.5M | 86% | High risk70 | Flagged0.023 |
| 25ED0165CONSTRUCTION OF SAN AGUSTIN BRIDGE (PUBLIC MARKET), BARANGAY IBABA EAST,CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱57M | 48% | High risk94 | Flagged0.023 |
| 22C00098CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF WATER SUPPLY SYSTEM IN PALAYAN CITY, NUEVA ECIJA, PROVINCE OF NUEVA ECIJA | Region III | Region III | On-Going | ₱145.5M | 76% | High risk79 | Flagged0.023 |
| 24C00605STATE UNIVERSITIES AND COLLEGES (SUCS)-ESTABLISHMENTOF COLLEGE BUSINESS CENTER WITH FACILITIES AND EQUIPMENT-SAN LUIS CAMPUS-AURORA STATE COLLEGE OF TECHNOLOGY, SAN LUIS, AURORA, PROVINCE OF AURORA | Region III | Region III | On-Going | ₱39.4M | 56% | Medium risk47 | Flagged0.020 |
| 25C00505CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RDS. LEAD. TO MAJ./STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF DONA REMEDIOS TRINIDAD NORZAGARAY SAN JOSE RD. (DRT SECT.), NORZAGARAY, BUL | Region III | Region III | On-Going | ₱95.1M | 0% | High risk75 | Flagged0.019 |
| 25C00480CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROAD S THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONST. OF BYPASS ROAD (PHASE 10) AT DONA REMEDIOS TRINIDAD TO SAN JOSE DEL MONTE | Region III | Region III | On-Going | ₱71.3M | 1% | High risk70 | Flagged0.014 |
| 25ED0166CONSTRUCTION OF BRIDGE, BARANGAY PERSONAS, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱42.8M | 82% | High risk94 | Flagged0.011 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 22CF0116REHABILITATION OF MULTI-PURPOSE BUILDING AT BARANGAY BAGONG SIKAT, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱7.9M | 100% | Medium risk34 | —-0.105 |
| 102 | 18CE0042REHABILITATION/IMPROVEMENT OF PAMPANGA RIVER CONTROL, BRGY. POBLACION NORTE, RIZAL, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱43.8M | 100% | Medium risk34 | —-0.102 |
| 103 | 20CF0079CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN VICENTE, GAPAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱5.9M | 100% | Medium risk34 | —-0.107 |
| 104 | 19CF0069REHABILITATION/ MAJOR REPAIR OF FLOOD CONTROL STRUCTURE- REHABILITATION/IMPROVEMENT OF PAMPANGA RIVER FLOOD CONTROL, BRGY. BAGONG SIKAT, CABIAO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱54.7M | 100% | Medium risk33 | —-0.092 |
| 105 | 22CF0060NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING- PRIMARY ROADS-JOSE ABAD SANTOS AVE. (JASA) - K0102+014.40-K0103+506.70, K0105+1008.50-K0106+548.50, K0105+997.50-K0105+1008.50, K0106+548.50-K0107+000, K107+591.15-K0107+805, K0110+679-K0110+836.90 | Region III | Nueva Ecija 2nd DEO | Completed | ₱43.4M | 100% | Medium risk33 | —-0.103 |
| 106 | 22CF0113CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY VALLE CRUZ, CABANATUAN CITY | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.107 |
| 107 | 18CF0069NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - NUEVA ECIJA-AURORA ROAD, K0125+430 - K0125+933, K0126+006 - K0126+069, K0126+365 -K0126+467, K0127+054 - K0127+306, K0127+326 - K0127+335, K0127+398 - K0127+500, K0127+879 - K0128+229 | Region III | Nueva Ecija 2nd DEO | Completed | ₱28.8M | 100% | Medium risk33 | —-0.103 |
| 108 | 18CF0063NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROAD, DAANG MAHARLIKA (LZ) -K0092+026.00 -K0092+962.00, K0101+992.20 - K0102+102.90, K103+169.30 - K0103+856.60 | Region III | Nueva Ecija 2nd DEO | Completed | ₱39M | 100% | Medium risk33 | —-0.104 |
| 109 | 19CF0098CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, BRGY. SAN ROQUE, JAEN, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱48.7M | 100% | Medium risk33 | —-0.093 |
| 110 | 23CF0088CONSTRUCTION (CONCRETING) OF PARTIDA ROAD, BOUNDARIES OF BARANGAY LAS PINAS AND SINASAJAN, PEÑARANDA, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱29M | 100% | Medium risk33 | —-0.105 |
| 111 | 20CF0067REHABILITATION/IMPROVEMENT OF PAMPANGA RIVER FLOOD CONTROL, BRGY. SAN ANTON, SAN LEONARDO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱48.5M | 100% | Medium risk33 | —-0.093 |
| 112 | 21CE0152CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), STO. DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱19.6M | 100% | Medium risk33 | —-0.102 |
| 113 | 19CF0020CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ACCESS ROAD LEADING TO MINALUNGAO NATIONAL PARK, SAN LEONARDO SECTION, SAN LEONARDO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱34.6M | 100% | Medium risk33 | —-0.105 |
| 114 | 20CF0091ASSET PRESERVATION CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - GAPAN-FORT MAGSAYSAY RD., K0102+010.50 - K0102+519.50, K0105+400.00 - K0106+085.00, K0106+085.00 - K0106+230.00, K0106+230.00 - K0106+300.00 | Region III | Nueva Ecija 2nd DEO | Completed | ₱21.7M | 100% | Medium risk32 | —-0.106 |
| 115 | 20CE0073REHABILITATION/RECONSTRUCTION OF ROAD, BALOC - SAGABA - MALASIN ROAD, STO. DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱39.2M | 100% | Medium risk32 | —-0.102 |
| 116 | 22CF0112CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY KAPT. PEPE, CABANATUAN CITY | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk32 | —-0.107 |
| 117 | 22C00020BRIDGE PROGRAM-REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-LABI BRIDGE (BO5024LZ) ALONG NUEVA ECIJA-AURORA ROAD, PROVINCE OF NUEVA ECIJA | Region III | Region III | Completed | ₱16.7M | 100% | Medium risk32 | —-0.065 |
| 118 | 21CF0170PREVENTIVE MAINTENANCE-PRIMARY ROADS, JOSE ABAD SANTOS AVE. (JASA) - K0 097+180.00-K0 097+540.20, K0 097+961.20-K0 097+1180.00, K0 098+066.70-K0 098+569.05 | Region III | Nueva Ecija 2nd DEO | Completed | ₱33.8M | 100% | Medium risk32 | —-0.104 |
| 119 | 20CF0108CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, BRGY. BAGONG SIKAT AND BRGY. SAN CARLOS, CABIAO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱48.5M | 100% | Medium risk32 | —-0.092 |
| 120 | 21CF0126CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING), JAEN, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱9.7M | 100% | Medium risk32 | —-0.106 |
| 121 | 23CE0032CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG RIO CHICO RIVER, BARANGAY MACAMIAS, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱48M | 100% | Medium risk32 | —-0.090 |
| 122 | 19CF0012ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS DAANG MAHARLIKA (LZ) K0104+979.30-K0105+386.00, K0120+560.00-K0121+355.00 | Region III | Nueva Ecija 2nd DEO | Completed | ₱22.6M | 100% | Medium risk32 | —-0.105 |
| 123 | 23CF0089CONSTRUCTION OF ROAD AND ROAD SHOULDER WITH DRAINAGE SYSTEM, IMELDA BLVD, BRGY. MAMBANGAN, SAN LEONARDO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱19.8M | 100% | Medium risk32 | —-0.105 |
| 124 | 24CF0085BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD ALONG POLICARPIO ST. AND CARMEN ST., BRGY. POBLACION, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱24.5M | 100% | Medium risk32 | —-0.105 |
| 125 | 21CF0051CONCRETING OF ROAD, BARANGAY MAGSALISI, JAEN, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱19.6M | 100% | Medium risk32 | —-0.105 |