Total projects
5
Total budget
₱67.3M
Average progress
100.0%
Completion rate
100.0%
Average risk score
38.3
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 5 | ₱67.3M | 38.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 3 | ₱7.6M | 25.3 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱43M | 65.3 | 0 | 100.0% |
| Bridges | 1 | ₱16.7M | 50.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 17BD0014MFO2: CONSTRUCTION OF FLOOD CONTROL SYSTEM, BUNTUN BRIDGE, TUGUEGARAO SIDE (DOWNSTREAM), REVETMENT: STA. 0+178-STA. 0+374, BUNTUN, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱43M | 100% | High risk65 | —-0.037 |
| 2 | 18BD0103ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, IGUIG BRIDGE 1 (B01918LZ) ALONG CAGAYAN VALLEY ROAD, IGUIG, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱16.7M | 100% | Medium risk50 | —-0.036 |
| 3 | 20BB0042CONVERGENCE & SPECIAL SUPPORT PROGRAM-CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - CONST. OF CONCRETE ROAD- JGCCSMBP TO SITIO BATANGAN LEADING BANANA PLANTATION PIÑA ESTE, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.081 |
| 4 | 18BD0026ROAD CONCRETING (COMPLETION) AT MIT ST., BRGY. UGAC NORTE, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱956K | 100% | Low risk18 | —-0.082 |
| 5 | 17BD0101CONCRETING OF CALAMAGUI FMR, CALAMAGUI, AMULUNG, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱1.8M | 100% | Low risk15 | —-0.004 |