Contractor dossier
55 projects on file, including joint ventures this contractor is part of.
Total projects
55
Total budget
₱1.1B
Average progress
96.1%
Completion rate
83.6%
Average risk score
42.9
Medium risk on average, out of 100
Flagged as unusual
2
3.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 54 | ₱1.1B | 42.8 | 2 | 96.0% |
| Region VII | 1 | ₱34.8M | 47.2 | 0 | 96.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 24 | ₱393.3M | 39.2 | 0 | 98.1% |
| Roads | 15 | ₱433.6M | 44.4 | 0 | 94.6% |
| Flood Control and Drainage | 5 | ₱102.6M | 47.2 | 0 | 95.6% |
| Water Provision and Storage | 5 | ₱9.7M | 22.0 | 0 | 100.0% |
| Bridges | 3 | ₱40.3M | 47.4 | 0 | 100.0% |
| OTHER | 2 | ₱64.4M | 84.4 | 1 | 89.5% |
| GAA 2025 OO-1 | 1 | ₱53.9M | 95.2 | 1 | 52.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IC0056NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING -TERTIARY ROADS - BAGAHUPI-BABATNGON-STA CRUZ-BARUGO-CARIGARA ROAD - K0918 + 559 - K0918 + 992, K0922 + 000 - K0922 + 380, K0922 + 401 - K0923 + 000, BABATNGON, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱53.9M | 52% | High risk95 | Flagged0.007 |
| 24IC0225CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SAN VICENTE, TOLOSA, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱48.2M | 79% | High risk91 | Flagged0.052 |
| 19IM0043ROAD WIDENING-LEYTE SAMAR ROAD (VIA GUINTIGUI-AN) K0904+167-K0904+676, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱16.2M | 100% | High risk78 | —-0.036 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IC0225CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SAN VICENTE, TOLOSA, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱48.2M | 79% | High risk91 | Flagged0.052 |
| 25IC0056NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING -TERTIARY ROADS - BAGAHUPI-BABATNGON-STA CRUZ-BARUGO-CARIGARA ROAD - K0918 + 559 - K0918 + 992, K0922 + 000 - K0922 + 380, K0922 + 401 - K0923 + 000, BABATNGON, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱53.9M | 52% | High risk95 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 18ID0088OFF-CARRIAGEWAY IMPROVEMENT TERTIARY ROAD,TANAUAN-DAGAMI ROAD,K0934+378-K0935+773 | Region VIII | Leyte 2nd DEO | Completed | ₱16.3M | 100% | Medium risk48 | —-0.095 |
| 27 | 19IC0079CONST. OF ONE STOREY, THREE-CLASSROOM SCHOOL BUILDING (9.5MX27.0M) WITH PARAPET, SAN FRANCISCO WEST ELEM. SCHOOL, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱6.3M | 100% | Medium risk48 | —-0.055 |
| 28 | 19ID0045CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-POBLACION LA PAZ TO CALABATO HOT SPRING,LA PAZ,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱19.3M | 100% | Medium risk48 | —-0.095 |
| 29 | 18ID0117CONSTRUCTION OF 1 UNIT,2 STOREY,4 CLASSROOM SCHOOL BUILDING AT HIBUNAUAN NHS,BURAUEN,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱9.5M | 100% | Medium risk48 | —-0.054 |
| 30 | 24HH0080CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY BUOT, CEBU CITY | Region VII | Cebu City DEO | On-Going | ₱34.8M | 96% | Medium risk47 | —-0.054 |
| 31 | 20ID0016CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF LUAN SEAWALL,BRGY. LUAN,DULAG,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱28.7M | 100% | Medium risk47 | —-0.078 |
| 32 | 20ID0017CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG DOMIRI RIVER,BRGY. CULASIAN, CAPOOCAN,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱10.6M | 100% | Medium risk47 | —-0.081 |
| 33 | 18ID0147CONSTRUCTION OF 1 UNIT-2 STOREY FOUR(4)CLASSROOM SCHOOL BUILDING(MODIFIED)PATOC NATIONAL HIGH SCHOOL,DAGAMI, LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱13.8M | 100% | Medium risk46 | —-0.054 |
| 34 | 18ID0025CONSTRUCTION OF SEAWALL,BALUD SEAWALL,CAPOOCAN,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱6.3M | 100% | Medium risk46 | —-0.079 |
| 35 | 18ID0049CONSTRUCTION OF POBLACION ZONE 1,SEAWALL/BREAKWATER,CAPOOCAN,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱8M | 100% | Medium risk46 | —-0.080 |
| 36 | 17IM0056CONSTRUCTION OF SCHOOL BUILDING STANDARD DPWH THREE STOREY NINE CLASSROOMS, LEYTE NATIONAL HIGH SCHOOL, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱16.2M | 100% | Medium risk45 | —-0.027 |
| 37 | 17ID0050CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS WIDENING OF PERMANENT BRIDGES TO MORE THAN 2 LANES-PRIMARY TAGAK BRIDGE (B00529LT) ALONG PALO-CARIGARA-ORMOC ROAD | Region VIII | Leyte 2nd DEO | Completed | ₱11.4M | 100% | Medium risk44 | —-0.024 |
| 38 | 19ID0040CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT)BRGY. HIAGSAM,JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱2M | 100% | Low risk26 | —-0.097 |
| 39 | 18ID0108CONSTRUCTION OF MULTI-PURPOSE BUILDING/COVERED COURT ,BARANGAY DARO,JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱2M | 100% | Low risk26 | —-0.097 |
| 40 | 20ID0059CONSTRUCTION OF COVERED COURT,BARANGAY CALIPAYAN,MAYORGA,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.096 |
| 41 | 18IM0031REHABILITATION OF MULTI-PURPOSE BUILDING (CITY AGRICULTURE OFFICE BUILDING), BRGY. 25, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱2.8M | 100% | Low risk25 | —-0.095 |
| 42 | 19IM0039CONSTRUCTION OF ROAD WITH DRAINAGE, BRGY. 110 UTAP, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱4.7M | 100% | Low risk24 | —-0.095 |
| 43 | 18IG0090CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS, A. BUENAVISTA ELEMENTARY SCHOOL, BAYBAY CITY, LEYTE, B. IMELDA ELEMENTARY SCHOOL, BAYBAY CITY, LEYTE, C. PALHI ELEMENTARY SCHOOL, BAYBAY CITY, LEYTE, D. SABANG ELEMENT | Region VIII | Leyte 5th DEO | Completed | ₱3.2M | 100% | Low risk24 | —-0.061 |
| 44 | 18ID0091CONSTRUCTION OF MULTI-PURPOSE BUILDING(COVERED COURT) BRGY. BAGONG LIPUNAN,CARIGARA | Region VIII | Leyte 2nd DEO | Completed | ₱2.5M | 100% | Low risk24 | —-0.098 |
| 45 | 19IC0054CONST. OF MULTI-PURPOSE BUILDING (BRGY. HALL), BRGY. BLUEMENTRITT, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱2.4M | 100% | Low risk24 | —-0.097 |
| 46 | 19ID0004CONSTRUCTION OF MULTI-PURPOSE BUILDING(COVERED COURT)BRGY. STO. NIÑO,CAPOOCAN,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱3.8M | 100% | Low risk24 | —-0.098 |
| 47 | 18I00063CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), FY 2018: A. VILLABA, LEYTE...; B. BATO, LEYTE...; C. ORMOC CITY..., VILLABA, LEYTE; BATO, LEYTE & ORMOC CITY, LEYTE | Region VIII | Region VIII | Completed | ₱3.3M | 100% | Low risk23 | —-0.062 |
| 48 | 21IG0042CONSTRUCTION OF WATER SYSTEM, BARANGAY PINAMONOAN, MAHAPLAG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱495K | 100% | Low risk23 | —-0.058 |
| 49 | 19ID0078CONCRETING OF ROAD,POBLACION DISTRICT IV,TABON-TABON,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱2M | 100% | Low risk22 | —-0.089 |
| 50 | 19ID0074CONCRETING OF ROAD,SITIO PAGLAOM TO PROPER,BRGY. JABONG,TABONTABON,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱2M | 100% | Low risk22 | —-0.089 |