Opening the dossier…
Opening the dossier…
Contractor dossier
170 projects on file, including joint ventures this contractor is part of.
Total projects
170
Total budget
₱6.1B
Average progress
97.3%
Completion rate
90.0%
Average risk score
53.0
Medium risk on average, out of 100
Flagged as unusual
3
1.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 155 | ₱5.2B | 53.1 | 2 | 97.6% |
| Region IV-B | 15 | ₱837.2M | 51.3 | 1 | 94.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 84 | ₱3.3B | 53.4 | 0 | 99.5% |
| Buildings and Facilities | 37 | ₱780.4M | 42.3 | 0 | 100.0% |
| Flood Control and Drainage | 25 | ₱999.9M | 49.3 | 0 | 100.0% |
| Bridges | 6 | ₱168.7M | 50.8 | 0 | 68.4% |
| OTHER | 5 | ₱298.4M | 76.2 | 1 | 81.7% |
| GAA 2025 OO-1 | 4 | ₱214.6M | 93.5 | 0 | 91.1% |
| GAA 2025 SSP | 3 | ₱106.6M | 94.7 | 2 | 72.7% |
| GAA 2025 OO-2 | 2 | ₱19.2M | 88.0 | 0 | 94.3% |
| Bridges, Roads | 2 | ₱123.8M | 53.8 | 0 | 100.0% |
| Water Provision and Storage | 2 | ₱12.3M | 45.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DM0011NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CATANAUAN DIVERSION ROAD, QUEZON (PACKAGE 6), QUEZON, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | On-Going | ₱94.6M | 95% | High risk96 | —-0.005 |
| 25DM0138CONSTRUCTION OF FLOOD MITIGATION, STRUCTURE ALONG BINGABING CREEK, BRGY. MADULAO, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | On-Going | ₱48.5M | 58% | High risk95 | Flagged0.008 |
| 25DM0147CONSTRUCTION OF DRAINAGE SYSTEM, BRGY. MADULAO, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | On-Going | ₱48.5M | 60% | High risk95 | Flagged0.008 |
| 25DL0001ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, GUMACA BY-PASS ROAD, PACKAGE A, QUEZON | Region IV-A | Quezon 4th DEO | On-Going | ₱48M | 94% | High risk94 | —-0.013 |
| 25DM0077CONSTRUCTION OF ROAD, SITIO PIER, BARANGAY SAN ANTONIO PALA, MUNICIPALITY OF CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | On-Going | ₱9.6M | 100% | High risk94 | —-0.008 |
| 25DM0005ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - GUMACA-PITOGO-MULANAY-SN NARCISO RD - K0279 + 000 - K0280 + 000, MULANAY, QUEZON | Region IV-A | Quezon 3rd DEO | On-Going | ₱33.6M | 100% | High risk92 | —-0.014 |
| 25DM0007ASSET PRESERVATION PROGRAM -REHABILITATION /RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - GUMACA - PITOGO - MULANAY - SN NARCISO RD - K0281+ 056 - K0281 + 117, K0281 + 188 - K0281 + 251, K0285+700 - K0286+100, MULA | Region IV-A | Quezon 3rd DEO | On-Going | ₱38.4M | 76% | High risk92 | —-0.006 |
| 25DL0151ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SEAWALL, ATIMONAN, QUEZON | Region IV-A | Quezon 4th DEO | On-Going | ₱9.6M | 94% | High risk88 | —-0.031 |
| 25DL0146ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BREAKWATER, ATIMONAN, QUEZON | Region IV-A | Quezon 4th DEO | On-Going | ₱9.6M | 95% | High risk88 | —-0.031 |
| 24DL0170CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES 59. CONSTRUCTION OF MULTI-PURPOSE BUILDING, GUMACA, QUEZON | Region IV-A | Quezon 4th DEO | On-Going | ₱94.1M | 97% | High risk79 | —-0.003 |
| 23EA0068CONSTRUCTION OF MULTI-PURPOSE BUILDING (AMPHITHEATER) PULANG LUPA, BRGY. BOLO, TORRIJOS, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱49.5M | 21% | High risk79 | Flagged0.032 |
| 17DL0088A. MFO 1: NATIONAL ROAD NETWORK SERVICES 1. ASSET PRESERVATION OF NATIONAL ROADS D. CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS 1. SECONDARY ROADS A. GUMACA-PITOGO-MULANAY-SN NARCISO RD - K0198+-1528-K0198+-1261 (B/S), K0198+ | Region IV-A | Quezon 4th DEO | Completed | ₱56.4M | 100% | High risk76 | —-0.038 |
| 24DM0155CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVENTION CENTER), BARANGAY POCTOL, MUNICIPALITY OF PITOGO, QUEZON, PITOGO, QUEZON | Region IV-A | Quezon 3rd DEO | On-Going | ₱49.5M | 90% | High risk76 | —-0.008 |
| 16DJ0068CONSTRUCTION OF BY-PASSES/DIVERSION ROADS, INCLUDING ROW, CANDELARIA BY-PASS ROAD, QUEZON 2ND LD CANDELARIA, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱48.9M | 100% | High risk72 | —-0.042 |
| 17D00026ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG MSR JCT-LOPEZ-CATANAUAN ROAD, K0248+912-K0250+790 & K0250+816-K0254+275, CATANAUAN, QUEZON | Region IV-A | Region IV-A | Completed | ₱144.3M | 100% | High risk71 | —-0.048 |
| 17D00023ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG CATANAUAN-BUENAVISTA ROAD K0266+025 - K0266+838, K0269+862-K0270+088 & | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk71 | —-0.044 |
| 17D00024ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG CATANAUAN-BUENAVISTA ROAD, K0262+323-K0266+025, BUENAVISTA, QUEZON | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk71 | —-0.045 |
| 17D00025ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL STRATEGIES TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG CATANAUAN-BUENAVISTA ROAD, K0272+067-K0275+840, BUENAVISTA, QUEZON | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk71 | —-0.048 |
| 17DM0051ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG CATANAUAN-BUENAVISTA RD - K0275 + 840 - K0277 + 487, BUENAVISTA, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱63.5M | 100% | High risk69 | —-0.069 |
| 17DL0091A. MFO -1: NATIONAL ROAD NETWORK SERVICES 1. ASSET PRESERVATION OF NATIONAL ROADS D. CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS 1. SECONDARY ROADS C. MSR JCT-LOPEZ-BUENAVISTA RD- K0219+848 - K0220+313, K0228+083 - K0228+683 | Region IV-A | Quezon 4th DEO | Completed | ₱51.9M | 100% | High risk68 | —-0.070 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23EA0068CONSTRUCTION OF MULTI-PURPOSE BUILDING (AMPHITHEATER) PULANG LUPA, BRGY. BOLO, TORRIJOS, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱49.5M | 21% | High risk79 | Flagged0.032 |
| 25DM0138CONSTRUCTION OF FLOOD MITIGATION, STRUCTURE ALONG BINGABING CREEK, BRGY. MADULAO, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | On-Going | ₱48.5M | 58% | High risk95 | Flagged0.008 |
| 25DM0147CONSTRUCTION OF DRAINAGE SYSTEM, BRGY. MADULAO, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | On-Going | ₱48.5M | 60% | High risk95 | Flagged0.008 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 18DL0105CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, MAGALLANES NHS, 1 UNIT - UNIQUE WORKSHOPS, 5 UNITS - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱30.7M | 100% | Medium risk40 | —-0.027 |
| 152 | 18DL0128CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, GUINAYANGAN NHS, 3 UNITS - REGULAR WORKSHOPS, 2 UNITS -SCIENCE LABS, 2 UNITS - ICT LABS, GUINAYANGAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱22.2M | 100% | Medium risk40 | —-0.029 |
| 153 | 18DL0103CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, LOPEZ NATIONAL COMPREHENSIVE HIGH SCHOOL, 1 UNIT - UNIQUE WORKSHOPS, 5 UNITS - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱30.7M | 100% | Medium risk40 | —-0.026 |
| 154 | 18DL0109CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, SAN FRANCISCO B NHS, 2 UNITS - UNIQUE WORKSHOPS, 2 UNITS - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱25.6M | 100% | Medium risk39 | —-0.028 |
| 155 | 18DL0092CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, BANTAD NATIONAL HIGH SCHOOL, 1 UNIT - UNIQUE WORKSHOPS, 1 UNIT - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, GUMACA, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱19.8M | 100% | Medium risk39 | —-0.030 |
| 156 | 18DL0112CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, VILLA PEREZ NHS, 2 UNITS - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, GUMACA, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱19.5M | 100% | Medium risk39 | —-0.030 |
| 157 | 18DL0120CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, DR. ARSENIO C. NICOLAS NHS - DOMINLOG EXT., 2 UNITS - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, CALAUAG, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱19.5M | 100% | Medium risk39 | —-0.030 |
| 158 | 18DL0097CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, GUITES NHS, 1 UNIT - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱16.8M | 100% | Medium risk39 | —-0.031 |
| 159 | 18DL0118CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, BANTULINAO INTEGRATED SCHOOL, 2 UNITS - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS -ICT LABS, CALAUAG, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱19.5M | 100% | Medium risk39 | —-0.030 |
| 160 | 18DL0119CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, DR. ARSENIO C. NICOLAS NHS, 2 UNITS - UNIQUE WORKSHOPS, 1 UNIT - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, CALAUAG, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱22.9M | 100% | Medium risk39 | —-0.028 |
| 161 | 18DL0096CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, DAO NATIONAL HIGH SCHOOL (FORMERLY SAN FRANCISCO B NHS - SAN MIG), 1 UNIT - UNIQUE WORKSHOPS, 1 UNIT - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, LOPEZ, | Region IV-A | Quezon 4th DEO | Completed | ₱19.8M | 100% | Medium risk39 | —-0.029 |
| 162 | 18DL0110CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, STO. NINO ILAYA NHS (FORMERLY SAN FRANCISCO B NHS), 1 UNIT - UNIQUE WORKSHOPS, 1 UNIT - REGULAR WORKSHOPS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱19.8M | 100% | Medium risk39 | —-0.030 |
| 163 | 18DL0106CY 2017 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF TVL AND OTHER WORKSHOPS, PAMAMPANGIN NHS, 2 UNITS - SCIENCE LABS, 2 UNITS - ICT LABS, LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱14.1M | 100% | Medium risk39 | —-0.032 |
| 164 | 18EA0061ROAD WIDENING OF MARINDUQUE CIRCUMFERENTIAL ROAD, K0060+000-K0061+000 | Region IV-B | Marinduque DEO | Completed | ₱46.4M | 100% | Medium risk38 | —-0.087 |
| 165 | 21EA0039REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD, K0082 + 370 - K0082 + 750 | Region IV-B | Marinduque DEO | Completed | ₱40.6M | 100% | Medium risk38 | —-0.087 |
| 166 | 17DL0052A. MFO-1: NATIONAL ROAD NETWORK SERVICES 1. ASSET PRESERVATION OF NATIONAL ROADS B. REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT - 4 (HDM- | Region IV-A | Quezon 4th DEO | Completed | ₱3.8M | 100% | Medium risk38 | —-0.067 |
| 167 | 20EA0024CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF NANGKA I FLOOD CONTROL MOGPOG, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱39.9M | 100% | Medium risk37 | —-0.075 |
| 168 | 21DK0203CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM IN REAL, PAGBILAO, LUCBAN, MAUBAN, INFANTA AND TAYABAS CITY, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱4.4M | 100% | Low risk25 | —-0.066 |
| 169 | 18DM0068CONSTRUCTION OF BARANGAY HEALTH STATIONS BARANGAY TAGBAKAN, SILANGAN, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱2.4M | 100% | Low risk23 | —-0.099 |
| 170 | 17DM0070CONSTRUCTION OF MULTI PURPOSE BUILDING (DAY CARE CENTER), BARANGAY TAGBACAN IBABA, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱1.4M | 100% | Low risk21 | —-0.068 |