Contractor dossier
90 projects on file, including joint ventures this contractor is part of.
Total projects
90
Total budget
₱3.2B
Average progress
86.2%
Completion rate
72.2%
Average risk score
49.0
Medium risk on average, out of 100
Flagged as unusual
7
7.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 89 | ₱3B | 48.8 | 6 | 87.0% |
| Region IV-B | 1 | ₱186M | 67.1 | 1 | 17.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 73 | ₱1.8B | 47.4 | 1 | 89.6% |
| Bridges | 8 | ₱179.9M | 40.2 | 1 | 93.7% |
| Buildings and Facilities | 5 | ₱737.1M | 62.3 | 1 | 59.5% |
| GAA 2025 OO-1 | 2 | ₱48.2M | 92.1 | 2 | 43.4% |
| Bridges, Roads | 1 | ₱186M | 67.1 | 1 | 17.8% |
| Flood Control and Drainage | 1 | ₱274.3M | 66.6 | 1 | 64.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00079ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR.) - K0790+200 - K0791+322 | Region VIII | Region VIII | On-Going | ₱28.9M | 35% | High risk92 | Flagged0.009 |
| 25I00144ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0794+800 - K0794+873, K0797+140 - K0797+210, K0802+210 - K0802+300, K0803+010 - K0803+300, K0803+750 - | Region VIII | Region VIII | On-Going | ₱19.2M | 51% | High risk92 | Flagged0.007 |
| 22I00108CONSTRUCTION OF OFFICE OF CIVIL DEFENSE (OCD) REGIONAL OFFICE 8 BUILDING, GOVERNMENT CENTER, BRGY. CANDAHUG, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱216.2M | 16% | High risk69 | Flagged0.015 |
| 21I00082CONSTRUCTION OF NEW BILIRAN PROVINCIAL HOSPITAL, BARANGAY LARRAZABAL, NAVAL, BILIRAN | Region VIII | Region VIII | On-Going | ₱386M | 100% | High risk69 | —-0.001 |
| 25E00253SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF TAGDAO-ISUGOD DIVERSION ROAD, QUEZON, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱186M | 18% | High risk67 | Flagged0.017 |
| 24I00058REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITY | Region VIII | Region VIII | On-Going | ₱274.3M | 65% | High risk67 | Flagged0.005 |
| 23IM0093CONSTRUCTION OF MULTI-PURPOSE FACILITIES (VIEWING DECK AND BOARDWALK) NEAR SAN JUANICO BRIDGE (PHASE 2), TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱96.4M | 7% | High risk66 | —-0.002 |
| 24I00095ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR), K0718+581 - K0718+815, K0747+179 - K0751+090, SAMAR 1ST | Region VIII | Region VIII | On-Going | ₱254.1M | 91% | High risk65 | —-0.015 |
| 23IK0048PREVENTIVE MAINT. - SECONDARY ROADS (BASEY-MARABUT-PINIMITINAN RD), K0910+100-K0910+750, K0912+530-K0913+000, K0923+335-K0924+000, K0924+000-K0924+701, K0926+K0093-K0927+000, K0928+524-K0929+000, K0930+000-K0930+150, K0931+K0847-K0932+000 | Region VIII | Samar 2nd DEO | Completed | ₱120.6M | 100% | High risk61 | —-0.080 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25E00253SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF TAGDAO-ISUGOD DIVERSION ROAD, QUEZON, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱186M | 18% | High risk67 | Flagged0.017 |
| 22I00108CONSTRUCTION OF OFFICE OF CIVIL DEFENSE (OCD) REGIONAL OFFICE 8 BUILDING, GOVERNMENT CENTER, BRGY. CANDAHUG, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱216.2M | 16% | High risk69 | Flagged0.015 |
| 25I00079ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR.) - K0790+200 - K0791+322 | Region VIII | Region VIII | On-Going | ₱28.9M | 35% | High risk92 | Flagged0.009 |
| 25I00144ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0794+800 - K0794+873, K0797+140 - K0797+210, K0802+210 - K0802+300, K0803+010 - K0803+300, K0803+750 - | Region VIII | Region VIII | On-Going | ₱19.2M | 51% | High risk92 | Flagged0.007 |
| 24I00058REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITY | Region VIII | Region VIII | On-Going | ₱274.3M | 65% | High risk67 | Flagged0.005 |
| 24IM0084CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - APITONG-PATERNO RD - K0908+983 - K0909+061 | Region VIII | Tacloban City DEO | On-Going | ₱1.9M | 0% | Medium risk42 | Flagged0.004 |
| 22IF0052WIDENING OF PERMANENT BRIDGES PAGSANGA-AN BR. (B00222LT) ALONG PALOMPON - ISABEL - MERIDA - ORMOC ROAD | Region VIII | Leyte 4th DEO | On-Going | ₱60.8M | 69% | Medium risk55 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25I00079ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR.) - K0790+200 - K0791+322 | Region VIII | Region VIII | On-Going | ₱28.9M | 35% | High risk92 | Flagged0.009 |
| 2 | 25I00144ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0794+800 - K0794+873, K0797+140 - K0797+210, K0802+210 - K0802+300, K0803+010 - K0803+300, K0803+750 - | Region VIII | Region VIII | On-Going | ₱19.2M | 51% | High risk92 | Flagged0.007 |
| 3 | 22I00108CONSTRUCTION OF OFFICE OF CIVIL DEFENSE (OCD) REGIONAL OFFICE 8 BUILDING, GOVERNMENT CENTER, BRGY. CANDAHUG, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱216.2M | 16% | High risk69 | Flagged0.015 |
| 4 | 21I00082CONSTRUCTION OF NEW BILIRAN PROVINCIAL HOSPITAL, BARANGAY LARRAZABAL, NAVAL, BILIRAN | Region VIII | Region VIII | On-Going | ₱386M | 100% | High risk69 | —-0.001 |
| 5 | 25E00253SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF TAGDAO-ISUGOD DIVERSION ROAD, QUEZON, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱186M | 18% | High risk67 | Flagged0.017 |
| 6 | 24I00058REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITY | Region VIII | Region VIII | On-Going | ₱274.3M | 65% | High risk67 | Flagged0.005 |
| 7 | 23IM0093CONSTRUCTION OF MULTI-PURPOSE FACILITIES (VIEWING DECK AND BOARDWALK) NEAR SAN JUANICO BRIDGE (PHASE 2), TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱96.4M | 7% | High risk66 | —-0.002 |
| 8 | 24I00095ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR), K0718+581 - K0718+815, K0747+179 - K0751+090, SAMAR 1ST | Region VIII | Region VIII | On-Going | ₱254.1M | 91% | High risk65 | —-0.015 |
| 9 | 23IK0048PREVENTIVE MAINT. - SECONDARY ROADS (BASEY-MARABUT-PINIMITINAN RD), K0910+100-K0910+750, K0912+530-K0913+000, K0923+335-K0924+000, K0924+000-K0924+701, K0926+K0093-K0927+000, K0928+524-K0929+000, K0930+000-K0930+150, K0931+K0847-K0932+000 | Region VIII | Samar 2nd DEO | Completed | ₱120.6M | 100% | High risk61 | —-0.080 |
| 10 | 22IC0078ASSET PRESERVATION-PREVENTIVE MAINTENANCE-PRIMARY ROADS, DAANG MAHARLIKA (LT) (S00024LT) K0911+(-118) - K0912+833, BRGY. CAMPETIC, PALO, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱85.8M | 100% | Medium risk56 | —-0.085 |
| 11 | 20I00025ASSET PRESERVATION - PREVENTIVE MAINTENANCE - SECONDARY ROADS, BILIRAN CIRCUMFERENTIAL RD. - K1083+170 - K1084+392, K1084+914 - K1086+1000 (S00002BR), BILIRAN LD | Region VIII | Region VIII | Completed | ₱83.1M | 100% | Medium risk56 | —-0.088 |
| 12 | 20I00046ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD. - (S00073LT) K0957+(-212) - K0957+020, (S00080LT) K0939+(-345) - K0939+920, (S00076LT) K0940+(-088) - K0940+407, LEYTE 2ND LD | Region VIII | Region VIII | Completed | ₱87.4M | 100% | Medium risk55 | —-0.087 |
| 13 | 22IF0052WIDENING OF PERMANENT BRIDGES PAGSANGA-AN BR. (B00222LT) ALONG PALOMPON - ISABEL - MERIDA - ORMOC ROAD | Region VIII | Leyte 4th DEO | On-Going | ₱60.8M | 69% | Medium risk55 | Flagged0.003 |
| 14 | 23IA0041CONSTRUCTION (COMPLETION) OF TWO-STOREY OFFICE BUILDING, DPWH BILIRAN DEO, DPWH BUREAU OF EQUIPMENT, 8TH RES, BARANGAY LARRAZABAL, NAVAL, BILIRAN (11.582803, 124.410106) | Region VIII | Biliran DEO | On-Going | ₱19.6M | 92% | Medium risk54 | —-0.039 |
| 15 | 24I00241ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LT) - K0919+304 - K0920+127, LEYTE 1ST LD | Region VIII | Region VIII | On-Going | ₱53.6M | 100% | Medium risk54 | —-0.056 |
| 16 | 22IA0088CONSTRUCTION OF TWO-STOREY OFFICE BUILDING, DPWH BILIRAN DEO, DPWH BUREAU OF EQUIPMENT, 8TH RES, BARANGAY LARRAZABAL, NAVAL, BILIRAN (11.582803, 124.410106) | Region VIII | Biliran DEO | On-Going | ₱19M | 82% | Medium risk54 | —-0.032 |
| 17 | 22IA0001REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD | Region VIII | Biliran DEO | Completed | ₱48.7M | 100% | Medium risk54 | —-0.093 |
| 18 | 22IA0004NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS BILIRAN CIRCUMFERENTIAL ROAD-K1041+281 -K1042+1060(11.664323°, 124.355587° - 11.678173°, 124.356705°) | Region VIII | Biliran DEO | Completed | ₱49M | 100% | Medium risk53 | —-0.091 |
| 19 | 22IA0080REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES-BILIRAN BR.(B00057BR) ALONG LEYTE-BILIRAN RD. K1005+500 (124.48014, 11.45709 TO 124.47887, 11.45506) | Region VIII | Biliran DEO | Completed | ₱49M | 100% | Medium risk53 | —-0.062 |
| 20 | 23IM0005PREVENTIVE MAINTENANCE - TERTIARY ROADS - LEYTE-SAMAR RD (VIA GUINTIGUI-AN) K0899+555 -K0899+992 | Region VIII | Tacloban City DEO | Completed | ₱32.8M | 100% | Medium risk50 | —-0.095 |
| 21 | 25I00100NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0791+837 - K0793+000 | Region VIII | Region VIII | On-Going | ₱40M | 1% | Medium risk50 | —-0.031 |
| 22 | 25I00145NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO-SN JUANICO BR) - K0789+000 - K0790+000 | Region VIII | Region VIII | On-Going | ₱37.9M | 29% | Medium risk50 | —-0.040 |
| 23 | 24I00231ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LT) - K0898+658 - K0899+079, TACLOBAN CITY LD | Region VIII | Region VIII | On-Going | ₱24.1M | 96% | Medium risk49 | —-0.054 |
| 24 | 22IA0087WIDENING OF PERMANENT BRIDGES- ALIWAHAW BR. (B00059BR) ALONG NAVAL-CAIBIRAN CROSS COUNTRY RD. (124.459588°, 11.579430°) | Region VIII | Biliran DEO | On-Going | ₱28.4M | 81% | Medium risk49 | —-0.002 |
| 25 | 20IA0038ASSET PRESERVATION - PREVENTION MAINTENANCE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL ROAD, K1082+000 - K1083+170 | Region VIII | Biliran DEO | Completed | ₱31.4M | 100% | Medium risk49 | —-0.095 |