Opening the dossier…
Opening the dossier…
Contractor dossier
210 projects on file, including joint ventures this contractor is part of.
Total projects
210
Total budget
₱1.3B
Average progress
98.6%
Completion rate
92.4%
Average risk score
31.5
Medium risk on average, out of 100
Flagged as unusual
9
4.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 210 | ₱1.3B | 31.5 | 9 | 98.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 173 | ₱949.6M | 28.0 | 0 | 99.6% |
| Roads | 21 | ₱225.9M | 36.4 | 0 | 99.7% |
| GAA 2025 SSP | 5 | ₱39.3M | 94.4 | 5 | 81.5% |
| OTHER | 4 | ₱29.7M | 83.8 | 3 | 99.8% |
| Bridges | 4 | ₱27.2M | 29.4 | 0 | 92.4% |
| Water Provision and Storage | 2 | ₱12.7M | 28.5 | 1 | 55.4% |
| Flood Control and Drainage | 1 | ₱4.2M | 17.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NF0093CONSTRUCTION OF MULTI-PURPOSE BUILDING (HALF-WAY HOUSE), GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱9.9M | 64% | High risk95 | Flagged0.023 |
| 25NE0063CONSTRUCTION OF SENIOR CITIZENS BUILDING, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱9.8M | 83% | High risk95 | Flagged0.008 |
| 25NF0073CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY STA. FE, GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱4.9M | 95% | High risk94 | Flagged0.011 |
| 25NE0059CONSTRUCTION OF MULTI-PURPOSE BUILDING, LEGISLATIVE BUILDING, BARANGAY FERDINAND, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱9.8M | 76% | High risk94 | Flagged0.012 |
| 25NF0071CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY MABINI, SANTA MONICA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱4.9M | 89% | High risk94 | Flagged0.012 |
| 25NF0067CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING IN ABAD SANTOS ELEMENTARY SCHOOL, STA. MONICA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱9.9M | 100% | High risk87 | Flagged0.039 |
| 24NE0082CONSTRUCTION OF 1 STOREY 1-CLASSROOM SCHOOL BUILDING IN ROSITA ELEMENTARY SCHOOL, BARANGAY ROSITA, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 100% | High risk87 | Flagged0.033 |
| 25NF0066CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING IN PELAEZ ELEMENTARY SCHOOL, SAN ISIDRO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱9.9M | 99% | High risk86 | Flagged0.041 |
| 25NE0035CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS MAHAYAHAY(SAN JOSE)-GOMEZ(DINAGAT) ROAD LEADING TO TAGBUYAKHAW TOURISM AREA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 100% | High risk75 | —-0.008 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NF0066CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING IN PELAEZ ELEMENTARY SCHOOL, SAN ISIDRO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱9.9M | 99% | High risk86 | Flagged0.041 |
| 25NF0067CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING IN ABAD SANTOS ELEMENTARY SCHOOL, STA. MONICA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱9.9M | 100% | High risk87 | Flagged0.039 |
| 24NE0082CONSTRUCTION OF 1 STOREY 1-CLASSROOM SCHOOL BUILDING IN ROSITA ELEMENTARY SCHOOL, BARANGAY ROSITA, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 100% | High risk87 | Flagged0.033 |
| 25NF0093CONSTRUCTION OF MULTI-PURPOSE BUILDING (HALF-WAY HOUSE), GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱9.9M | 64% | High risk95 | Flagged0.023 |
| 25NE0059CONSTRUCTION OF MULTI-PURPOSE BUILDING, LEGISLATIVE BUILDING, BARANGAY FERDINAND, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱9.8M | 76% | High risk94 | Flagged0.012 |
| 25NF0071CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY MABINI, SANTA MONICA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱4.9M | 89% | High risk94 | Flagged0.012 |
| 25NF0073CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY STA. FE, GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | On-Going | ₱4.9M | 95% | High risk94 | Flagged0.011 |
| 25NE0063CONSTRUCTION OF SENIOR CITIZENS BUILDING, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱9.8M | 83% | High risk95 | Flagged0.008 |
| 25NE0064CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL 3), BARANGAY CUARINTA, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱9.8M | 11% | Medium risk39 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 23NF0074CONSTRUCTION OF 1STY 2CL DON ENRIQUE NAVARRO MEMORIAL SCHOOL | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4.7M | 100% | Medium risk30 | —-0.035 |
| 152 | 24NF0074CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN NUEVA ESTRELLA ELEMENTARY SCHOOL, BARANGAY NUEVA ESTRELLA, MUNICIPALITY OF SOCORRO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱8M | 100% | Medium risk30 | —-0.038 |
| 153 | 23NF0076CONSTRUCTION OF 1STY 2CL PILAR CENTRAL ELEMENTARY SCHOOL | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4.7M | 100% | Low risk30 | —-0.035 |
| 154 | 22NE0075REHABILITATION/RECONSTRUCTION OF ROADSLIP ALONG DINAGAT-LORETO ROAD K0036+500-K0036+580, BRGY, DIEGAS, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱1.6M | 100% | Low risk18 | —-0.084 |
| 155 | 21NF0060REHABILITATION OF WATER SUPPLY SYSTEM IN BARANGAY POBLACION, PILAR, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱3M | 100% | Low risk18 | —-0.039 |
| 156 | 23NF0044CONSTRUCTION OF DRAINAGE CANAL, DAPA, SURIGAO DEL NORTE (PHASE II) | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4.2M | 100% | Low risk17 | —-0.062 |
| 157 | 22NE0057REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES CANAHAAN BR. (B00080DG) ALONG JCT MAGSAYSAY-CAGDIANAO ROAD, BRGY. R, ECLEO SR., CAGDIANAO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱975K | 100% | Low risk17 | —-0.047 |
| 158 | 20NE0037REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, ROSITA BRIDGE 1 (B00087DG) ALONG DINAGAT-LORETO ROAD, BRGY. ROSITA, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱1.9M | 100% | Low risk17 | —-0.049 |
| 159 | 20NF0016CONCRETING OF MALINAO-GEN. LUNA ROAD, BRGY. MALINAO, GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱1.9M | 100% | Low risk17 | —-0.075 |
| 160 | 23NF0094CONSTRUCTION OF 1STY 1CL STA FELOMINA ELEMENTARY SCHOOL, DAPA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱2M | 100% | Low risk13 | —-0.035 |
| 161 | 23NF0093CONSTRUCTION OF 1STY 1CL STA. CRUZ ELEMENTARY SCHOOL, GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱2M | 100% | Low risk13 | —-0.033 |
| 162 | 22NF0145CONSTRUCTION (COMPLETION) OF 2STY4CL, CARIDAD NATIONAL HIGH, PILAR, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱2.1M | 100% | Low risk13 | —-0.033 |
| 163 | 22NF0142CONSTRUCTION (COMPLETION) OF 2STY6CL, SAPAO NATIONAL HIGH SCHOOL SANTA MONICA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱2.1M | 100% | Low risk13 | —-0.034 |
| 164 | 22NF0149CONSTRUCTION (COMPLETION) OF 2STY4CL, SAN BENITO NATIONAL HIGH SCHOOL SAN BENITO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4M | 100% | Low risk13 | —-0.038 |
| 165 | 22NF0146CONSTRUCTION (COMPLETION) OF 2STY6CL, PILAR NATIONAL HIGH SCHOOL, PILAR, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱2.5M | 100% | Low risk13 | —-0.034 |
| 166 | 22NF0148CONSTRUCTION (COMPLETION) OF 2 UNITS 2STY4CL, PILAR NATIONAL HIGH SCHOOL, PILAR, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱3.5M | 100% | Low risk13 | —-0.034 |
| 167 | 22NF0138CONSTRUCTION (COMPLETION) OF 2STY6CL, SAN ISIDRO NATIONAL HIGH SCHOOL, SAN ISIDRO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱3.5M | 100% | Low risk12 | —-0.035 |
| 168 | 21NF0053CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MONTSERRAT, DAPA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱3.9M | 100% | Low risk12 | —-0.077 |
| 169 | 22NF0144CONSTRUCTION (COMPLETION) OF 2 UNITS 2STY4CL, STA. FE NATIONAL HIGH SCHOOL, GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4.1M | 100% | Low risk12 | —-0.034 |
| 170 | 22NF0147CONSTRUCTION (COMPLETION) OF 2STY4CL, BURGOS NATIONAL HIGH SCHOOL, BURGOS, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4M | 100% | Low risk12 | —-0.035 |
| 171 | 22NF0141CONSTRUCTION (COMPLETION) OF 2STY6CL, GEN. LUNA NATIONAL HIGH SCHOOL, GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4M | 100% | Low risk12 | —-0.035 |
| 172 | 20NF0037REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY BONGDO, SAN BENITO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱3.9M | 100% | Low risk12 | —-0.078 |
| 173 | 22NF0080CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BITAUG, BURGOS, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4M | 100% | Low risk12 | —-0.077 |
| 174 | 22NF0057CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY KATIPUNAN, DEL CARMEN, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱3M | 100% | Low risk12 | —-0.078 |
| 175 | 21NF0048CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY STA. FE, DAPA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱3.9M | 100% | Low risk12 | —-0.079 |