Contractor dossier
156 projects on file, including joint ventures this contractor is part of.
Total projects
156
Total budget
₱3.6B
Average progress
96.0%
Completion rate
89.1%
Average risk score
33.7
Medium risk on average, out of 100
Flagged as unusual
5
3.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 155 | ₱3.6B | 33.6 | 5 | 96.0% |
| National Capital Region | 1 | ₱49M | 48.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 59 | ₱1.2B | 34.4 | 3 | 94.0% |
| Buildings and Facilities | 50 | ₱585.8M | 28.9 | 0 | 96.1% |
| Flood Control and Drainage | 41 | ₱1.6B | 36.6 | 0 | 99.7% |
| Water Provision and Storage | 3 | ₱111.1M | 42.8 | 1 | 96.4% |
| Bridges | 2 | ₱42.9M | 30.8 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱32.6M | 89.1 | 1 | 52.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CL0140REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS OLONGAPO-BUGALLON RD - K0179 + 156 - K0179 + 390, K0215 + 000 - K0215 + 500, K0223 + 725 - K0224 + 000, K0241 + 920 - K0242 + 524, CABANGAN, PALAUIG, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱32.6M | 52% | High risk89 | Flagged0.006 |
| 24CL0130CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG GABOR RIVER, BALINCAGUING SECTION (PHASE I), SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.2M | 100% | High risk81 | —-0.043 |
| 24CM0067BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF CASTILLEJOS WATER SYSTEM, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱99M | 89% | High risk80 | Flagged0.004 |
| 24CL0143CONSTRUCTION OF SLOPE PROTECTION PACKAGE 18 AT BOTOLAN- CAPAZ RD., BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱96.5M | 100% | High risk80 | —-0.045 |
| 24CM0009ASSET PRESERVATION PROGRAM-CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS, OLONGAPO-BUGALLON RD., K0133+040, K0133+223.30, K0133+305.15, K0133+353.70, K0133+404.45, K0133+550, K0135+300, K0135+332, K0135+372.70, SUB | Region III | Zambales 2nd DEO | On-Going | ₱69.5M | 85% | High risk74 | —-0.024 |
| 25CM0042CSSP, BIP, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF SUBIC-CAWAG-BALAYBAY ROAD (HANJIN ROAD INTERMITTENT SECTION), SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱77.6M | 87% | High risk74 | —-0.029 |
| 25CM0071CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF SAN MARCELINO MULTI-PURPOSE BUILDING INCLUDING FACILITIES PHASE 2, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱29.3M | 41% | High risk74 | —-0.017 |
| 24CL0092CONSTRUCTION OF MULTI-PURPOSE BUILDING, ZNHS, ZONE 6, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱42.9M | 68% | High risk74 | —-0.017 |
| 24CL0193CONSTRUCTION OF MULTI-PURPOSE FACILITY, CALIGUIT, BARANGAY DIRITA, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱39.1M | 100% | High risk74 | —-0.034 |
| 25CM0069CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF SAN MARCELINO MUNICIPAL HALL AT SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱24.4M | 0% | High risk74 | —-0.004 |
| 24CL0111CONSTRUCTION OF ACADEMIC BLDG. FOR COLLEGE OF MARINE ENGINEERING PMMA, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱29M | 100% | High risk74 | —-0.062 |
| 24CL0127CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANCAL-SAN ISIDRO-MAMBOG RIVER (TOTUN LANUM) PHASE 3, SITIO TAMBAK, (NORTH SIDE), BARANGAY PALANGINAN, IBA, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱47.6M | 100% | High risk73 | —-0.057 |
| 24CM0056MULTI-PURPOSE/FACILITIES, REHABILITATION OF DPWH ZAMBALES 2ND DISTRICT ENGINEERING OFFICE BUILDING, SAN NICOLAS, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱16M | 100% | High risk73 | —-0.065 |
| 25CL0183CONCRETING OF BANTAY CARMEN TO SAGPAT FMR, BRGY. MALOMA, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱49.1M | 0% | High risk72 | Flagged0.044 |
| 25CK0061CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY PARULUNG, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱7.9M | 98% | High risk71 | —-0.044 |
| 23CL0175CONSTRUCTION OF BY-PASS AND DIVERSION ROADS IBA-BOTOLAN, ZAMBALES (PHASE 3) | Region III | Zambales 1st DEO | On-Going | ₱38.1M | 0% | High risk70 | Flagged0.051 |
| 25CL0186CONCRETING OF STA. RITA FMR, BRGY. BANGANTALINGA, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱19.7M | 0% | High risk69 | Flagged0.043 |
| 24CL0192CONSTRUCTION OF ROAD, BARANGAY BURGOS, SAN ANTONIO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱14.5M | 100% | High risk69 | —-0.062 |
| 25CK0015REHABILITATION OF EXISTING DIKE ALONG SAPANG KWARTEL (BRGY. MINANE), PHASE I, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱14.7M | 100% | High risk68 | —-0.064 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23CL0175CONSTRUCTION OF BY-PASS AND DIVERSION ROADS IBA-BOTOLAN, ZAMBALES (PHASE 3) | Region III | Zambales 1st DEO | On-Going | ₱38.1M | 0% | High risk70 | Flagged0.051 |
| 25CL0183CONCRETING OF BANTAY CARMEN TO SAGPAT FMR, BRGY. MALOMA, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱49.1M | 0% | High risk72 | Flagged0.044 |
| 25CL0186CONCRETING OF STA. RITA FMR, BRGY. BANGANTALINGA, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱19.7M | 0% | High risk69 | Flagged0.043 |
| 25CL0140REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS OLONGAPO-BUGALLON RD - K0179 + 156 - K0179 + 390, K0215 + 000 - K0215 + 500, K0223 + 725 - K0224 + 000, K0241 + 920 - K0242 + 524, CABANGAN, PALAUIG, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱32.6M | 52% | High risk89 | Flagged0.006 |
| 24CM0067BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF CASTILLEJOS WATER SYSTEM, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱99M | 89% | High risk80 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 24CK0028REHABILITATION OF EXISTING DIKE ALONG PARUA RIVER (BALUTU SECTION, RIGHT BANK), STA. 14+253 TO STA. 14+443, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱46.7M | 100% | Low risk29 | —-0.090 |
| 102 | 24CK0027REHABILITATION OF EXISTING DIKE ALONG LUCUNG RIVER (MALUPA SECTION, LEFT BANK), STA. 1+637 TO STA. 1+674 AND STA. 2+196 TO STA. 2+376, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱46.7M | 100% | Low risk29 | —-0.092 |
| 103 | 24CK0128CONSTRUCTION OF ROAD, BRGY. STA. MONICA, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱4.8M | 100% | Low risk29 | —-0.102 |
| 104 | 19CK0077REHABILITATION OF EXISTING DIKE ALONG SAPANG BALEN CREEK, TALIMUNDOC SECTION, RIGHT BANK, STA. 0+881.00 TO STA. 1+331.00, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱18.6M | 100% | Low risk29 | —-0.094 |
| 105 | 22CK0110REHABILITATION OF EXISTING DIKE ALONG BULALO RIVER, BANTOG SECTION, DOWNSIDE (D/S) OF CHECK GATE, STA. 0+358.00 TO STA. 0+501.00 - R/S, STA. 0+358.00 TO STA. 0+501.00 - L/S, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱19.2M | 100% | Low risk29 | —-0.090 |
| 106 | 25CK0016REHABILITATION OF EXISTING DIKE ALONG SAPANG KWARTEL (BRGY. MINANE), PHASE II, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱14.7M | 100% | Low risk29 | —-0.091 |
| 107 | 20CK0029REHABILITATION/IMPROVEMENT OF EXISTING EARTH DIKE ALONG LUCUNG RIVER (MALUPA SECTION, LEFT BANK), CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱16M | 100% | Low risk29 | —-0.092 |
| 108 | 20CK0081REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG LUCUNG RIVER (OLD LUCUNG LILIBANGAN & MAGAO SECTION), CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱29.4M | 100% | Low risk29 | —-0.093 |
| 109 | 18CK0157REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG O'DONNELL RIVER (MARUGLO SECTION, RIGHT BANK), CAPAS, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱46.1M | 100% | Low risk29 | —-0.091 |
| 110 | 20CK0075CONSTRUCTION OF CLASSROOMS: TWO (2) STOREY, TEN (10) CLASSROOM SCHOOL BUILDING AT ARANGUREN INTEGRATED SCHOOL, CAPAS, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱23.4M | 100% | Low risk28 | —-0.044 |
| 111 | 20CK0093CONSTRUCTION OF CLASSROOMS: TWO (2) STOREY, SIX (6) CLASSROOM SCHOOL BUILDING AT CAUT ELEMENTARY SCHOOL, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱14.7M | 100% | Low risk28 | —-0.051 |
| 112 | 20CK0076CONSTRUCTION OF CLASSROOMS: TWO (2) STOREY, TEN (10) CLASSROOM SCHOOL BUILDING AT CONCEPCION NORTH CENTRAL ELEMENTARY SCHOOL, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱23M | 100% | Low risk28 | —-0.045 |
| 113 | 19CK0139CONSTRUCTION OF CLASSROOMS: TWO (2) STOREY, TEN (10) CLASSROOM SCHOOL BUILDING AT SAN JOSE ELEMENTARY SCHOOL, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱25.6M | 100% | Low risk28 | —-0.045 |
| 114 | 20CK0089CONSTRUCTION OF NEW PUBLIC MARKET (LAND DEVELOPMENT, WET SECTION AND DRY SECTION B, 1 STOREY BUILDING), BAMBAN, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱17.9M | 100% | Low risk28 | —-0.047 |
| 115 | 20CM0090CONCRETING OF PUROK 3, BRGY. CONSUELO NORTE FMR, CONSUELO NORTE, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱9.6M | 100% | Low risk27 | —-0.038 |
| 116 | 18CM0116CONSTRUCTION OF 2-STOREY, 6-CLASSROOM SCHOOL BUILDING, DEL PILAR ELEMENTARY SCHOOL (BATCH 5), CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱11.4M | 100% | Low risk26 | —-0.048 |
| 117 | 21CM0065CONCRETING OF LLLNARES ST., SITIO SAN ISIDRO, BRGY. SAN PABLO FMR, BRGY. SAN PABLO, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱11.5M | 100% | Low risk26 | —-0.040 |
| 118 | 18CM0087CONCRETING OF SITIO ALIBANG EXTENSION, BRGY. NAUGSUL FMR, BRGY. NAUGSUL, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱9.3M | 100% | Low risk25 | —-0.039 |
| 119 | 18CM0082CONCRETING OF SITIO MALAYA, BRGY. ANINGWAY SACATIHAN FMR, BRGY. ANINGWAY SACATIHAN, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱6.5M | 100% | Low risk25 | —-0.039 |
| 120 | 20CK0095CONCRETING OF SITIO BULUSAN TROSO TO SITIO MAURICIA, BRGY. ANUPUL FMR, BRGY. ANUPUL, BAMBAN, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱11.4M | 100% | Low risk25 | —-0.041 |
| 121 | 18CK0126CONSTRUCTION OF CLASSROOMS: TWO (2) STOREY, SIX (6) CLASSROOM SCHOOL BUILDING AT CAPAS EAST CENTRAL SCHOOL, CAPAS, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱11.5M | 100% | Low risk24 | —-0.050 |
| 122 | 18CK0110CONCRETING OF SITIO RIVERSIDE, BARANGAY TINANG FMR, BARANGAY TINANG, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱7.6M | 100% | Low risk24 | —-0.040 |
| 123 | 23CK0059CONCRETING OF BRGY. CASTILLO ROAD FMR, BRGY. CASTILLO, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱11.9M | 100% | Low risk24 | —-0.044 |
| 124 | 21CK0102CONCRETING OF BRGY. BALANOY TO BRGY. DUMARAIS FMR, BRGY. BALANOY AND BRGY. DUMARAIS, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱11.8M | 100% | Low risk24 | —-0.041 |
| 125 | 18CK0152CONCRETING OF FARM TO MILL ROAD AT BARANGAY MAGAO TO CULATINGAN ROAD, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱8.7M | 100% | Low risk24 | —-0.041 |