Contractor dossier
22 projects on file, including joint ventures this contractor is part of.
Total projects
22
Total budget
₱938.6M
Average progress
83.3%
Completion rate
50.0%
Below 70%
Average risk score
50.5
Medium risk on average, out of 100
Flagged as unusual
3
13.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 22 | ₱938.6M | 50.5 | 3 | 83.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 16 | ₱570.3M | 46.8 | 2 | 89.4% |
| Bridges | 2 | ₱109.2M | 53.6 | 0 | 47.8% |
| Buildings and Facilities | 2 | ₱13.7M | 50.0 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱235.5M | 95.4 | 1 | 5.9% |
| OTHER | 1 | ₱9.9M | 58.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00176NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BASEY-MAYDOLONG, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱235.5M | 6% | High risk95 | Flagged0.050 |
| 24I00162ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0791+649 - K0792+200, K0796+558 - K0797+000, K0806+120 - K0807+000, K0822+000 - K0824+500, K0 | Region VIII | Region VIII | On-Going | ₱163.9M | 91% | High risk65 | —-0.030 |
| 23IK0109NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS, BASEY-MARABUT-PINAMITINAN RD (S00124SM)- K0914+000-K0915+000, K0936+000-K0937+000, K0939+000-K0940+000, K0940+000-K0941+000, K0946+000-K0947+000, K0947+000-K0948+000, K0948+000-K0948+875 | Region VIII | Samar 2nd DEO | On-Going | ₱238.8M | 68% | High risk65 | —-0.010 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00176NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BASEY-MAYDOLONG, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱235.5M | 6% | High risk95 | Flagged0.050 |
| 23IC0132CONCRETING OF BRGY. SAN DIEGO TO SITIO MAHANLOD FMR, BRGY. SAN DIEGO, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱12.4M | 0% | Medium risk45 | Flagged0.032 |
| 24IM0088CONCRETING OF BRGY. 106 SANTO NIÑO FMR, BRGY. 106 SANTO NIÑO, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | On-Going | ₱14.9M | 80% | Medium risk52 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25I00176NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BASEY-MAYDOLONG, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱235.5M | 6% | High risk95 | Flagged0.050 |
| 2 | 24I00162ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0791+649 - K0792+200, K0796+558 - K0797+000, K0806+120 - K0807+000, K0822+000 - K0824+500, K0 | Region VIII | Region VIII | On-Going | ₱163.9M | 91% | High risk65 | —-0.030 |
| 3 | 23IK0109NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS, BASEY-MARABUT-PINAMITINAN RD (S00124SM)- K0914+000-K0915+000, K0936+000-K0937+000, K0939+000-K0940+000, K0940+000-K0941+000, K0946+000-K0947+000, K0947+000-K0948+000, K0948+000-K0948+875 | Region VIII | Samar 2nd DEO | On-Going | ₱238.8M | 68% | High risk65 | —-0.010 |
| 4 | 24IM0082CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAY 97 CABALAWAN, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | On-Going | ₱9.9M | 100% | Medium risk59 | —-0.025 |
| 5 | 24I00313BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES - TANGAO BR. (B00335SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.) | Region VIII | Region VIII | On-Going | ₱89.6M | 27% | Medium risk58 | —-0.000 |
| 6 | 24IM0088CONCRETING OF BRGY. 106 SANTO NIÑO FMR, BRGY. 106 SANTO NIÑO, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | On-Going | ₱14.9M | 80% | Medium risk52 | Flagged0.001 |
| 7 | 24IJ0043CLUSTER: CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING 1. BARANGAY PINANANGAN, STO. NIÑO, SAMAR 2. BARANGAY COROCAWAYAN, STO. NIÑO, SAMAR 3. BARANGAY LOBE-LOBE, STO. NIÑO, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱8.9M | 100% | Medium risk51 | —-0.097 |
| 8 | 23IJ0085CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BUENAVISTA, STO. NIÑO, WESTERN SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.099 |
| 9 | 24IJ0072CSSP: CONSTRUCTION OF CIRCUMFERENTIAL ROAD, STO. NIÑO, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱19.8M | 100% | Medium risk49 | —-0.096 |
| 10 | 24IJ0031OO1: WIDENING OF PERMANENT BRIDGES, CAPACUHAN BR. (B00364SM) ALONG CALBAYOG - CATARMAN RD | Region VIII | Samar 1st DEO | On-Going | ₱19.6M | 68% | Medium risk49 | —-0.012 |
| 11 | 25IE0017CONSTRUCTION OF JNR CASILION-NEW BALANAC ROAD (PHASE 2), VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱19.6M | 92% | Medium risk48 | —-0.059 |
| 12 | 24IJ0080OO1: PREVENTIVE MAINTENANCE - TERTIARY ROADS - CALBAYOG DIVERSION RD. - K0727+000 - K0727+348.15, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱24.4M | 100% | Medium risk48 | —-0.095 |
| 13 | 24IJ0023OO1: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS, CALBAYOG - CATARMAN RD. K0795+455 - K0795+512 | Region VIII | Samar 1st DEO | Completed | ₱18.2M | 100% | Medium risk48 | —-0.094 |
| 14 | 23IJ0060CONSTRUCTION OF ROAD, BARANGAY MACATINGOG, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱9.8M | 100% | Medium risk48 | —-0.094 |
| 15 | 23IJ0080REPAIR/RECONSTRUCTION OF NATIONAL ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG DAANG MAHARLIKA (S00062SM), K0691+(-065) - K0691+(-100) CALBAYOG CITY, SAMAR 1ST | Region VIII | Samar 1st DEO | Completed | ₱5.3M | 100% | Medium risk47 | —-0.096 |
| 16 | 23IJ0040CSSP: CONSTRUCTION OF ROAD FROM BRGY. LOOC TO BRGY. SAPUTAN, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱9.9M | 100% | Medium risk47 | —-0.094 |
| 17 | 24IJ0029CSSP: ACCESS ROAD LEADING TO SULPAN CAVE, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱4.9M | 100% | Medium risk47 | —-0.054 |
| 18 | 23IJ0074CONCRETING OF QUEZON TO SAN ISIDRO FMR, BRGY. QUEZON AND BRGY. SAN ISIDRO, SAN JORGE, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.044 |
| 19 | 23IC0132CONCRETING OF BRGY. SAN DIEGO TO SITIO MAHANLOD FMR, BRGY. SAN DIEGO, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱12.4M | 0% | Medium risk45 | Flagged0.032 |
| 20 | 23IC0123CONCRETING OF BRGY. CAMBAHANON FMR, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱12.4M | 100% | Medium risk44 | —-0.043 |
| 21 | 25IJ0012OO1: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS, SECONDARY ROADS - CALBAYOG - CATARMAN RD. - K0785+(-261) - K0785+(-199), K0788+311 - K0788+368, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱2.7M | 100% | Low risk25 | —-0.062 |
| 22 | 23IJ0081CLUSTER: 1. REPAIR/RECONSTRUCTION OF NATIONAL ROADS ALONG CALBAYOG DIVERSION ROAD (S00085SM) ROADSLIP AND SLOPE PROTECTION, K0730+400 -K0730+440 BRGY. PAGBALIKAN, CALBAYOG CITY, SAMAR2. REPAIR/RECONSTRUCTION OF NATIONAL ROADS W/ SLIPS, SLOPE COLLAPSE A | Region VIII | Samar 1st DEO | Completed | ₱3.4M | 100% | Low risk24 | —-0.093 |