Opening the dossier…
Opening the dossier…
Contractor dossier
151 projects on file, including joint ventures this contractor is part of.
Total projects
151
Total budget
₱2B
Average progress
99.5%
Completion rate
95.4%
Average risk score
22.5
Low risk on average, out of 100
Flagged as unusual
3
2.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 151 | ₱2B | 22.5 | 3 | 99.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 91 | ₱1B | 21.1 | 0 | 99.6% |
| Buildings and Facilities | 39 | ₱270.7M | 16.6 | 0 | 99.9% |
| Bridges | 7 | ₱46.7M | 18.1 | 0 | 100.0% |
| Flood Control and Drainage | 6 | ₱167.3M | 25.7 | 0 | 100.0% |
| OTHER | 3 | ₱294.8M | 79.2 | 1 | 97.2% |
| Water Provision and Storage | 2 | ₱12M | 17.8 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱140.4M | 94.2 | 1 | 87.8% |
| GAA 2025 OO-2 | 1 | ₱94.7M | 92.7 | 0 | 87.2% |
| GAA 2025 SSP | 1 | ₱4.9M | 91.3 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MD0029MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱140.4M | 88% | High risk94 | Flagged0.019 |
| 25MD0031CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALOGO RIVER, UPSTREAM OF BALOGO BRIDGE, BARANGAY BALOGO, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱94.7M | 87% | High risk93 | —-0.004 |
| 25MD0054CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION 4, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱4.9M | 100% | High risk91 | Flagged0.007 |
| 24MD0049MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱106.1M | 92% | High risk81 | Flagged0.013 |
| 17MD0063IMPVT/WIDENING OF NATIONAL ROADS ALONG MIDSAYAP-MAKAR RD, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱93.1M | 100% | High risk80 | —-0.023 |
| 23MD0045SITIO LIMATONG-CAMPO 1 AND KAGUIRINGAN FALLS LEADING TO HIKING JUMP-OFF SITE TO MT. AGKIR-AGKIR, NORTH COTABATO, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱95.5M | 100% | High risk77 | —-0.023 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MD0029MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱140.4M | 88% | High risk94 | Flagged0.019 |
| 24MD0049MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱106.1M | 92% | High risk81 | Flagged0.013 |
| 25MD0054CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION 4, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱4.9M | 100% | High risk91 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 23MD0096CONCRETING OF BARANGAY LOWER GLAD - BARANGAY RANGABAN ROAD, BARANGAY LOWER GLAD, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱4.8M | 100% | Low risk19 | —-0.033 |
| 102 | 17MD0075REHAB/RECONST OF NATIONAL RDS W/ SLIPS, SLOPE COLLAPSE, & LANDSLIDE ALONG DUALINIG-BALIKI-SILIK RD,A | Region XII | Cotabato 1st DEO | Completed | ₱3.1M | 100% | Low risk19 | —-0.054 |
| 103 | 19MD0112CONCRETING/CONSTRUCTION OF SITIO LOWER LAMUYON, BRGY. BARANGIRAN - BRGY. POLAYAGAN FMR, BRGY. BARANGIRAN AND BRGY. POLAYAGAN, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱5M | 100% | Low risk19 | —-0.031 |
| 104 | 16MD0115REHAB/IMPVT & EXPANSION OF HOSPITAL BLDG, ALAMADA PROVINCIAL COMM. HOSP., ALAMADA, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱10.2M | 100% | Low risk17 | —-0.020 |
| 105 | 24MD0060CONSTRUCTION OF 1 UNIT, 1-STOREY 2-CLASSROOM SCHOOL BUILDING, ELPIDIO SINGCO ELEMENTARY SCHOOL, BARANGAY KIWANAN, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱5M | 100% | Low risk15 | —-0.018 |
| 106 | 17MD0199CLUSTER E - CONST. OF 1STY 3CL SB (TOILET ATTACHED) & 1STY 2CL SB (TOILET ATTACHED), MIGUEL INTES ES, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱6M | 100% | Low risk15 | —-0.020 |
| 107 | 17MD0040CONCRETING OF MAITING ROAD, BRGY. KITUBOD, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk15 | —-0.054 |
| 108 | 17MD0080CONST. OF MP BLDG. DR. C.H. DELES ES, BRGY UPPER GLAD I, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.5M | 100% | Low risk15 | —-0.060 |
| 109 | 17MD0006CONCRETING OF KATILACAN ROAD, BRGY. KATILACAN, PIKIT, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk14 | —-0.054 |
| 110 | 17MD0008CONC. OF LOWER MINGADING ROAD, BRGY. MINGADING, ALEOSAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk14 | —-0.054 |
| 111 | 20MD0068CONCRETING OF LOCAL ROAD, MARTIN TO TINAGO STATE, ULAMIAN, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk14 | —-0.051 |
| 112 | 17MD0042CONCRETING OF UPPLER GLAD 2-CENTRAL BULANAN RD (CENTRAL BULANAN SECT), MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk14 | —-0.053 |
| 113 | 20MD0084CONCRETING OF LOCAL ROAD, PUROK YELLOW BELL- DISTRICT 6, MAGSAYSAY STREET, SINAWINGAN, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk14 | —-0.051 |
| 114 | 17MD0004CONC. OF BURGOS ST., BRGY. BALOGO, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.052 |
| 115 | 20MD0070CONCRETING OF LOCAL ROAD, NIA VILLAGE, VILLARICA, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.084 |
| 116 | 18MD0047CONCRETING OF CROSSING ABAGA-NALIN ROAD, ABAGA-NALIN, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱3.7M | 100% | Low risk12 | —-0.084 |
| 117 | 18MD0014RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE KATIDTUAN BR. (B01866MN) ALONG DAVAO-COTABATO ROAD, (JCT. DIGOS-COTABATO SECTION), KATIDTUAN, KABACAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.058 |
| 118 | 18MD0031REHAB/MAJOR REPAIR OF PERMANENT BRIDGES GREBONA BR. (B01246MN), ALONG BAN-GUI-ALA-LIB ROAD, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.061 |
| 119 | 21MD0004CONCRETING OF LOCAL ROAD, MARTIN TO TINAGO STATE, BRGY. ULAMIAN, LIBUNGAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk11 | —-0.084 |
| 120 | 21MD0002CONCRETING OF PUROK 2, SLAUGHTER HOUSE ROAD, BRGY. POBLACION, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk11 | —-0.084 |
| 121 | 21MD0003CONCRETING OF LOCAL ROAD, PUROK 7, BRGY. GUMAGA, LIBUNGAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk11 | —-0.084 |
| 122 | 21MD0014CONCRETING OF BARANGAY AGRICULTURE-BARANGAY BUAL SUR ROAD, BARANGAY AGRICULTURE, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk11 | —-0.084 |
| 123 | 21MD0001CONCRETING OF ROADS, CRBI ROAD, DISTRICT 6, PUROK ORCHIDS, BRGY. SINAWINGAN, LIBUNGAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk10 | —-0.083 |
| 124 | 19MD0064CONCRETING OF SAN MATEO- HIGHWAY JCT.- HIGH SCHOOL ROAD, BRGY. SAN MATEO, ALEOSAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.088 |
| 125 | 21MD0016CONCRETING OF BARANGAY KIMAGANGO-ANONANG ROAD, BARANGAY KIMAGANGO, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk10 | —-0.085 |