Contractor dossier
31 projects on file, including joint ventures this contractor is part of.
Total projects
31
Total budget
₱1.8B
Average progress
92.6%
Completion rate
87.1%
Average risk score
46.8
Medium risk on average, out of 100
Flagged as unusual
3
9.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 28 | ₱1B | 44.9 | 2 | 95.3% |
| Region IV-A | 3 | ₱754.6M | 64.7 | 1 | 67.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges | 30 | ₱1.7B | 45.2 | 2 | 95.1% |
| GAA 2025 OO-1 | 1 | ₱65.1M | 93.6 | 1 | 17.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CF0143BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES-SAGANA BR. (B01346LZ) ALONG JCT. TABLANG - GABALDON RD | Region III | Nueva Ecija 2nd DEO | On-Going | ₱65.1M | 18% | High risk94 | Flagged0.014 |
| 23D00160CONSTRUCTION OF TAGAYTAY FLYOVER, BRGY. MENDEZ - CROSSING EAST JUNCTION, TAGAYTAY CITY K0061+416 - K0062+016 | Region IV-A | Region IV-A | On-Going | ₱564.3M | 68% | High risk66 | Flagged0.022 |
| 24D00051CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), MARAGONDON SECTION, CAVITE | Region IV-A | Region IV-A | On-Going | ₱93.9M | 34% | High risk64 | —-0.002 |
| 17CE0033REPLACEMENT OF PERMANENT WEAK BRIDGES DIBABUYAN BR. (B00114LZ), DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 1st DEO | Completed | ₱55.9M | 100% | High risk64 | —-0.033 |
| 22D00004GENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), GENERAL AGUINALDO, CAVITE | Region IV-A | Region IV-A | Completed | ₱96.5M | 100% | High risk63 | —-0.048 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23D00160CONSTRUCTION OF TAGAYTAY FLYOVER, BRGY. MENDEZ - CROSSING EAST JUNCTION, TAGAYTAY CITY K0061+416 - K0062+016 | Region IV-A | Region IV-A | On-Going | ₱564.3M | 68% | High risk66 | Flagged0.022 |
| 19C00005BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES, SICSICAN BRIDGE (BO1936LZ) ALONG DAANG MAHARLIKA (LZ)-PHASE II, NUEVA ECIJA 1ST LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA | Region III | Region III | On-Going | ₱111.6M | 49% | Medium risk52 | Flagged0.016 |
| 25CF0143BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES-SAGANA BR. (B01346LZ) ALONG JCT. TABLANG - GABALDON RD | Region III | Nueva Ecija 2nd DEO | On-Going | ₱65.1M | 18% | High risk94 | Flagged0.014 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CF0143BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES-SAGANA BR. (B01346LZ) ALONG JCT. TABLANG - GABALDON RD | Region III | Nueva Ecija 2nd DEO | On-Going | ₱65.1M | 18% | High risk94 | Flagged0.014 |
| 2 | 23D00160CONSTRUCTION OF TAGAYTAY FLYOVER, BRGY. MENDEZ - CROSSING EAST JUNCTION, TAGAYTAY CITY K0061+416 - K0062+016 | Region IV-A | Region IV-A | On-Going | ₱564.3M | 68% | High risk66 | Flagged0.022 |
| 3 | 24D00051CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), MARAGONDON SECTION, CAVITE | Region IV-A | Region IV-A | On-Going | ₱93.9M | 34% | High risk64 | —-0.002 |
| 4 | 17CE0033REPLACEMENT OF PERMANENT WEAK BRIDGES DIBABUYAN BR. (B00114LZ), DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 1st DEO | Completed | ₱55.9M | 100% | High risk64 | —-0.033 |
| 5 | 22D00004GENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), GENERAL AGUINALDO, CAVITE | Region IV-A | Region IV-A | Completed | ₱96.5M | 100% | High risk63 | —-0.048 |
| 6 | 17CF0144CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS WIDENING OF PERMANENT BRIDGES TO MORE THAN 2 LANES TABUATING BRIDGE (B01313LZ) ALONG DAANG MAHARLIKA (LZ), SAN LEONARDO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱40.3M | 100% | Medium risk57 | —-0.038 |
| 7 | 17CF0196CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS REPLACEMENT OF PERMANENT WEAK BRIDGES SAN JUAN BR. 3 (B00151LZ) ALONG JCT. TABLANG GABALDON ROAD. | Region III | Nueva Ecija 2nd DEO | Completed | ₱23.8M | 100% | Medium risk54 | —-0.036 |
| 8 | 17CF0166CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES TO MORE THAN 2-LANES-PRIMARY ABOT BRIDGE (B001300LZ) ALONG STA. ROSA-TARLAC ROAD. | Region III | Nueva Ecija 2nd DEO | Completed | ₱20.5M | 100% | Medium risk54 | —-0.039 |
| 9 | 17CF0204WIDENING OF PERMANENT BRIDGES INCLUDING ROW TO MORE THAN TWO LANES, BITAS BR. (B00128LZ) ALONG DAANG MAHARLIKA LZ | Region III | Nueva Ecija 2nd DEO | Completed | ₱16.6M | 100% | Medium risk54 | —-0.039 |
| 10 | 17CE0070CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES; MINULI BR. 2 (B01980LZ) ALONG DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 1st DEO | Completed | ₱14.7M | 100% | Medium risk54 | —-0.038 |
| 11 | 17CE0067CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES; TAYABO BR. (B01969LZ) ALONG DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 1st DEO | Completed | ₱14.5M | 100% | Medium risk54 | —-0.038 |
| 12 | 17CF0210WIDENING OF PERMANENT BRIDGES INCLUDING ROW TO MORE THAN 2 LANES MINATULA BRIDGE (B00125LZ) ALONG DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 2nd DEO | Completed | ₱24.2M | 100% | Medium risk53 | —-0.039 |
| 13 | 16CE0204CONST. & MAINT. OF BRIDGES ALONG NATIONAL ROADS, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-PRIMARY, BALBALUNGAO BR. I (B01286LZ) ALONG SN. JOSE-LUPAO RD. | Region III | Nueva Ecija 1st DEO | Completed | ₱18.3M | 100% | Medium risk53 | —-0.037 |
| 14 | 17CE0068CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES; TACTAC BR. (B01975LZ) ALONG DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 1st DEO | Completed | ₱11M | 100% | Medium risk53 | —-0.039 |
| 15 | 18C00030BRIDGE PROGRAM-CONSTRUCTION OF NEW PERMANENT BRIDGES-GENERAL LUNA BRIDGE (BO1324LZ) ALONG DAANG MAHARLIKA (LZ), NUEVA ECIJA 3RD LEGISLATIVE DISTRICT, CABANATUAN CITY | Region III | Region III | Completed | ₱139.9M | 100% | Medium risk53 | —-0.042 |
| 16 | 16CE0207CONST. & MAINT. OF BRIDGES ALONG NATIONAL ROADS, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-PRIMARY MANICLA BR. (B01968LZ) ALONG DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 1st DEO | Completed | ₱5.5M | 100% | Medium risk52 | —-0.036 |
| 17 | 16CE0212CONST. & MAINT. OF BRIDGES ALONG NATIONAL ROADS, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-SECONDARY,PORAIS BR. (B03401LZ) ALONG SAN JOSE CITY-RIZAL RD. VIA PINILI-PORAIS-VILLA JOSON-STA. MONICA-PORTAL RD. | Region III | Nueva Ecija 1st DEO | Completed | ₱5.4M | 100% | Medium risk52 | —-0.036 |
| 18 | 18C00028BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES, SICSICAN BRIDGE (BO1963LZ) ALONG DAANG MAHARLIKA (LZ), NUEVA ECIJA 1ST LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA | Region III | Region III | Completed | ₱122.2M | 100% | Medium risk52 | —-0.032 |
| 19 | 19C00005BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES, SICSICAN BRIDGE (BO1936LZ) ALONG DAANG MAHARLIKA (LZ)-PHASE II, NUEVA ECIJA 1ST LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA | Region III | Region III | On-Going | ₱111.6M | 49% | Medium risk52 | Flagged0.016 |
| 20 | 19C00008BRIDGE PROGRAM-CONSTRUCTION OF NEW PERMANENT BRIDGES-GENERAL LUNA BRIDGE (PARALLEL BRIDGE) ALONG DAANG MAHARLIKA (LZ)-PHASE II, NUEVA ECIJA 3RD LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA | Region III | Region III | Completed | ₱94.8M | 100% | Medium risk51 | —-0.048 |
| 21 | 18CF0154CONSTRUCTION OF BRIDGE, BRGY. NAZARETH LEADING TO MINALUNGAO NATIONAL PARK, BRGY. RIO CHICO, GENERAL TINIO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱94.6M | 100% | Medium risk51 | —-0.054 |
| 22 | 18CF0144NETWORK DEVELOPMENT PROGRAM (BRIDGE PROGRAM) WIDENING OF PERMANENT BRIDGE, MAMALACOL BRIDGE (B00143LZ), ALONG DAANG MAHARLIKHA (LZ) | Region III | Nueva Ecija 2nd DEO | Completed | ₱29.3M | 100% | Medium risk31 | —-0.066 |
| 23 | 18CF0145NETWORK DEVELOPMENT PROGRAM (BRIDGE PROGRAM) WIDENING OF PERMANENT BRIDGES, SAPANG BUHAY BR. 1(B00126LZ) ALONG DAANG MAHARLIKHA (LZ) | Region III | Nueva Ecija 2nd DEO | Completed | ₱15M | 100% | Medium risk31 | —-0.067 |
| 24 | 20C00014BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES-SICSICAN BRIDGE (BO1963LZ)-PHASE III, NUEVA ECIJA 1ST LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA | Region III | Region III | Completed | ₱30.6M | 100% | Medium risk31 | —-0.040 |
| 25 | 18CE0137REPLACEMENT OF PERMANENT WEAK BRIDGES, LOMBOY BR. 1 (B01964LZ) ALONG DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 1st DEO | Completed | ₱41.9M | 100% | Medium risk30 | —-0.062 |