Contractor dossier
17 projects on file, including joint ventures this contractor is part of.
Total projects
17
Total budget
₱98.8M
Average progress
95.1%
Completion rate
88.2%
Average risk score
38.7
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 11 | ₱72.3M | 34.4 | 0 | 100.0% |
| Region VIII | 6 | ₱26.5M | 46.4 | 0 | 86.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 8 | ₱36.1M | 36.9 | 0 | 89.5% |
| Water Provision and Storage | 5 | ₱21.5M | 41.2 | 0 | 100.0% |
| Roads | 2 | ₱16.9M | 39.8 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱24.4M | 38.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23EE0052CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL II)BARANGAY ILIAN, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | High risk63 | —-0.014 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 23EE0052CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL II)BARANGAY ILIAN, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | High risk63 | —-0.014 |
| 2 | 24IE0031CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN VICENTE, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱4.9M | 100% | Medium risk52 | —-0.099 |
| 3 | 24IE0049CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GIBACUNGAN, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 16% | Medium risk51 | —-0.025 |
| 4 | 23IE0060CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TABUNOK, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 100% | Medium risk50 | —-0.049 |
| 5 | 24IE0063CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY STA. ROSA, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.063 |
| 6 | 24IE0013CONSTRUCTION OF ROAD, BARANGAY CAHIGAN, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.091 |
| 7 | 24EE0101CONSTRUCTION OF ABONGAN CIS DRAINAGE CANAL, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱19.6M | 100% | Medium risk41 | —-0.057 |
| 8 | 24EE0050CONSTRUCTION OF WATER SUPPLY SYSTEM PROJECT (LEVEL II) MINAPLA, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.033 |
| 9 | 24EE0049CONSTRUCTION OF WATER SUPPLY SYSTEM PROJECT (LEVEL II) BANBANAN, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.032 |
| 10 | 21EE0131CONSTRUCTION OF SLOPE PROTECTION STA. TERESITA NATIONAL HIGH SCHOOLDUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.8M | 100% | Medium risk35 | —-0.010 |
| 11 | 24EE0008CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAMANTOLON, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk35 | —-0.070 |
| 12 | 23EE0085CONSTRUCTION OF MULTI-PURPOSE BUILDING (EL NIDO YOUTH CENTER) EL NIDO, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.069 |
| 13 | 22EE0021CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BUILDINGBARANGAY MAURINGEN, ARACELI, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱5M | 100% | Medium risk34 | —-0.069 |
| 14 | 23EE0092CONCRETING OF SO. TIMBURAN BRGY. PULARAQUEN FMR PHASE II BRGY. PULARAQUEN, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱11.9M | 100% | Medium risk31 | —-0.023 |
| 15 | 24IE0052CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY PAYAO, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2M | 100% | Low risk26 | —-0.098 |
| 16 | 18EF0128CLUSTER I-1. CONST. OF RAINWATER COLLECTION SYSTEM (RWCS OF PINAGLABANAN NHS, 2. PINAGLABANAN ES, 3. BERONG NHS, 4. MAASIN NHS, 5. TABON NHS, 6. DPWH-QUEZON FIELD OFFICE 7. PANITIAN NHS, 8. PANITIAN ES, 9. PANIBUGON ES, QUEZON, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱1.7M | 100% | Low risk16 | —-0.025 |
| 17 | 23EE0123CONSTRUCTION OF 1-STY 2 CL NEW GUINLO NATIONAL HIGH SCHOOL, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.6M | 100% | Low risk12 | —-0.029 |