525 projects on file, including joint ventures this contractor is part of.
Total projects
525
Total budget
₱35.4B
Average progress
93.7%
Completion rate
79.0%
Average risk score
52.2
Medium risk on average, out of 100
Flagged as unusual
45
8.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 482 | ₱32.3B | 52.1 | 39 | 94.0% |
| Region XII | 8 | ₱602.9M | 54.4 | 2 | 85.0% |
| Region IV-B | 7 | ₱658.8M | 55.9 | 3 | 65.6% |
| Region XIII | 6 | ₱265.3M | 48.9 | 1 | 98.1% |
| Region X | 6 | ₱270.1M | 47.7 | 0 | 100.0% |
| Region IV-A | 5 | ₱458.6M | 59.5 | 0 | 100.0% |
| Region I | 5 | ₱482.5M | 54.4 | 0 | 97.5% |
| Region II | 4 | ₱384.1M | 58.6 | 0 | 100.0% |
| Cordillera Administrative Region | 1 | ₱44.3M | 49.5 | 0 | 100.0% |
| Region III | 1 | ₱14.1M | 31.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 287 | ₱20.6B | 52.9 | 17 | 92.3% |
| Flood Control and Drainage | 123 | ₱7.2B | 49.1 | 4 | 98.2% |
| Buildings and Facilities | 55 | ₱2.8B | 38.6 | 3 | 95.5% |
| OTHER | 25 | ₱2B | 71.9 | 10 | 92.7% |
| Bridges | 17 | ₱872.6M | 51.3 | 1 | 98.6% |
| Bridges, Roads | 7 | ₱1.1B | 67.1 | 3 | 77.7% |
| GAA 2025 SSP | 5 | ₱357.6M | 95.0 | 5 | 70.7% |
| GAA 2025 OO-2 | 3 | ₱359.8M | 92.5 | 1 | 72.7% |
| Water Provision and Storage | 2 | ₱54.3M | 44.2 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱59.3M | 93.9 | 1 | 67.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25LK0071CONSTRUCTION OF ROAD, SITIO AYAGON, BARANGAY LUMIAD TO SITIO SALUKADANG, BARANGAY MAPULA, PAQUIBATO DISTRICT, DAVAO CITY | Region XI | Davao City 3rd DEO | On-Going | ₱47.8M | 96% | High risk95 | Flagged0.006 |
| 25MC0045CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 3, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱112.3M | 39% | High risk95 | Flagged0.041 |
| 25NH0049CONST. OF SEAWALL, BRGY. ARAS-ASAN, CAGWAIT, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱66.9M | 89% | High risk95 | Flagged0.022 |
| 25LK0070CONSTRUCTION OF ROAD, SITIO BANBAN TO SITIO AYAGON, BARANGAY LUMIAD, PAQUIBATO DISTRICT, DAVAO CITY | Region XI | Davao City 3rd DEO | On-Going | ₱81.2M | 80% | High risk95 | Flagged0.017 |
| 25ME0115CONSTRUCTION OF MULTI-PURPOSE BUILDING, (MALAPATAN COLLEGE OF SCIENCE AND TECHNOLOGY), MALAPATAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱49.5M | 49% | High risk95 | Flagged0.037 |
| 25L00025CONSTRUCTION OF CONCRETE BRIDGE - BUHANGIN - TIGATTO - MANDUG - CALLAWA - FATIMA ROAD, PACKAGE 12, DAVAO CITY | Region XI | Region XI | On-Going | ₱59.3M | 67% | High risk94 | Flagged0.011 |
| 25LD0034CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALUTAKAY RIVER, BALUTAKAY BRIDGE TO PUROK 2 UPSTREAM SECTION, BARANGAY BALUTAKAY, HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱95.6M | 81% | High risk94 | —-0.003 |
| 25LF0130CONSTRUCTION OF COASTAL PROTECTION, PROTECTING SURIGAO DEL SUR BDRY.- DAVAO ORIENTAL COASTAL RD. (PINAKPAKAN SECTION), MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱142.6M | 46% | High risk93 | Flagged0.021 |
| 25MH0023CONSTRUCTION OF RIVER BANK PROTECTION AT BAGUMBAYAN RIVER, BARANGAY POBLACION, BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱121.7M | 92% | High risk91 | —-0.001 |
| 17L00098RECONST./CONC./WIDENING OF SLAUGHTER HOUSE RD UNTIL F. TORRES BR. INCL. RROW, DAVAO CITY 1ST LD (PAC | Region XI | Region XI | Completed | ₱135M | 100% | High risk80 | Flagged0.003 |
| 22LB0265CONSTRUCTION OF RETARDING BASIN PROTECTING NATIONAL ROAD, LA VERNASECTION, STA. 0+000 - STA. 0+500, DAVAOCITY | Region XI | Davao City DEO | On-Going | ₱279.9M | 99% | High risk80 | Flagged0.052 |
| 17L00024REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL.SLOPE PROTECTION (BRGY. BINCUNGAN SECT.) DAVAO | Region XI | Region XI | Completed | ₱114.5M | 100% | High risk79 | Flagged0.008 |
| 22LH0144REHABILITATION OF ROAD ALONG BAGUIO PROPER TO BRGY. TAWAN TAWAN, DAVAO CITY, DAVAO DEL SUR, STA. 0+000.000-STA. 7+000.000 | Region XI | Davao City 2nd DEO | Completed | ₱94M | 100% | High risk79 | —-0.015 |
| 17L00144WIDENING/IMPVT. OF BYPASS RD AT JCT. DAANG MAHARLIKA-LICANAN-BUNAWAN-MAHAYAG-INDANGAN-CABANTIAN-JCT. | Region XI | Region XI | Completed | ₱182.2M | 100% | High risk78 | Flagged0.027 |
| 24L00019CONSTRUCTION OF GRAVEL ROAD - BUHANGIN - TIGATTO - MANDUG - CALLAWA - FATIMA ROAD, PACKAGE 11, DAVAO CITY | Region XI | Region XI | On-Going | ₱86.8M | 91% | High risk77 | Flagged0.015 |
| 18LC0022CONSTRUCTION OF CONCRETE REVETMENT ON STEEL SHEET PILES AND CONSTRUCTION OF EARTH DIKE ALONG SAUG RIVER, INCLUDING ROW, CANATAN SECTION, ASUNCION, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱58.9M | 100% | High risk77 | —-0.023 |
| 17LB0289CONST. OF MPB, DAVAO CITY, PACKAGE 55 A) CONST. OF MPB, BRGY. 18-B, DAVAO CITY B)CONST. OF 7 STOREY | Region XI | Davao City DEO | Completed | ₱86.4M | 100% | High risk76 | —-0.011 |
| 18LB0003CONSTRUCTION OF DRAINAGE STRUCTURE ALONG DAVAO CITY DIVERSION ROAD K1508+280-K1510+905, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱57.8M | 100% | High risk76 | —-0.026 |
| 19LH0020PAVING OF SHOULDER ALONG CALINAN-BAGUIO-CADALIAN ROAD, K1695+140 TO K1697+375.76 (BOTHSIDE); K1694+392 TO K1694+400 (RIGHTSIDE); K1694+400 TO K1694+860 (BOTHSIDE); K1684+870.887 TO K1684+900 (LEFTSIDE); K1684+900 TO K1686+432.63 (BOTHSIDE); K1686+432.63 | Region XI | Davao City 2nd DEO | Completed | ₱51.3M | 100% | High risk76 | —-0.027 |
| 24LB0111CONSTRUCTION OF RETARDING BASIN - PHASE 2, LA VERNA, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱52.5M | 16% | High risk76 | Flagged0.037 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22LB0265CONSTRUCTION OF RETARDING BASIN PROTECTING NATIONAL ROAD, LA VERNASECTION, STA. 0+000 - STA. 0+500, DAVAOCITY | Region XI | Davao City DEO | On-Going | ₱279.9M | 99% | High risk80 | Flagged0.052 |
| 25MC0045CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 3, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱112.3M | 39% | High risk95 | Flagged0.041 |
| 25ME0115CONSTRUCTION OF MULTI-PURPOSE BUILDING, (MALAPATAN COLLEGE OF SCIENCE AND TECHNOLOGY), MALAPATAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱49.5M | 49% | High risk95 | Flagged0.037 |
| 24LB0111CONSTRUCTION OF RETARDING BASIN - PHASE 2, LA VERNA, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱52.5M | 16% | High risk76 | Flagged0.037 |
| 24LD0220CONSTRUCTION OF COASTAL ROAD INCLUDING BIKE LANES WITH SOLAR LIGHTS (APLAYA-DAWIS SECTION, PHASE 2, DIGOS CITY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱95.6M | 16% | High risk65 | Flagged0.037 |
| 21LB0117CONSTRUCTION OF RETARDING BASIN - LA VERNA OUTFALL SECTION, DAVAO CITY (STA. 0+000 - STA. 0+600) | Region XI | Davao City DEO | On-Going | ₱49M | 100% | High risk76 | Flagged0.029 |
| 17L00144WIDENING/IMPVT. OF BYPASS RD AT JCT. DAANG MAHARLIKA-LICANAN-BUNAWAN-MAHAYAG-INDANGAN-CABANTIAN-JCT. | Region XI | Region XI | Completed | ₱182.2M | 100% | High risk78 | Flagged0.027 |
| 24LD0214CONSTRUCTION OF FLOOD CONTROL STRUCTURE- CONCRETE REVETMENT ALONG BALUTAKAY RIVER (DOMINGO V. ABAWAG ES TO IGPIT SECTION), DIGOS CITY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱47.7M | 70% | Medium risk57 | Flagged0.027 |
| 25L00096CONSTRUCTION OF DRAINAGE STRUCTURES ALONG ROAD - MAHARLIKA HIGHWAY - K1484+(-600) - K1484+722, K1485+200 - K1485+839, DAVAO CITY | Region XI | Region XI | On-Going | ₱168.5M | 1% | Medium risk55 | Flagged0.026 |
| 24LH0110CONSTRUCTION OF 4STY24CL, BAGO OSHIRO NATIONAL HIGH SCHOOL, DAVAO CITY, DAVAO DEL SUR | Region XI | Davao City 2nd DEO | On-Going | ₱94.6M | 63% | Medium risk55 | Flagged0.024 |
| 20L00142CONSTRUCTION OF CONCRETE BRIDGE - TALOMO BRIDGE 4, DAVAO CITY | Region XI | Region XI | On-Going | ₱125.4M | 87% | High risk63 | Flagged0.022 |
| 25NH0049CONST. OF SEAWALL, BRGY. ARAS-ASAN, CAGWAIT, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱66.9M | 89% | High risk95 | Flagged0.022 |
| 25LF0130CONSTRUCTION OF COASTAL PROTECTION, PROTECTING SURIGAO DEL SUR BDRY.- DAVAO ORIENTAL COASTAL RD. (PINAKPAKAN SECTION), MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱142.6M | 46% | High risk93 | Flagged0.021 |
| 25L00009PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MAHARLIKA HIGHWAY - (S01364MN) K1476+555 - K1476+928, K1477+153 - K1478+615, K1479+145 - K1479+384, (S01362MN) CHAINAGE 0 - CHAINAGE 110, CHAINAGE 40+ - CHAINAGE 498, (S00065MN) K1477+(-831) - K1477+(-153) | Region XI | Region XI | On-Going | ₱138.4M | 0% | Medium risk55 | Flagged0.021 |
| 20L00164CONSTRUCTION OF ASPHALT ROAD - DAVAO CITY COASTAL BYPASS ROAD (BAGO APLAYA - TIMES BEACH - ROXAS AVENUE), PACKAGE 27, DAVAO CITY | Region XI | Region XI | On-Going | ₱380.1M | 97% | High risk66 | Flagged0.019 |
| 25L00008PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MAHARLIKA HIGHWAY - (S01364MN) K1470+336 - K1471+053, K1475+665 - K1476+555, (S00065MN) K1477+442-K1476+346, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱131.7M | 0% | Medium risk55 | Flagged0.018 |
| 25LK0070CONSTRUCTION OF ROAD, SITIO BANBAN TO SITIO AYAGON, BARANGAY LUMIAD, PAQUIBATO DISTRICT, DAVAO CITY | Region XI | Davao City 3rd DEO | On-Going | ₱81.2M | 80% | High risk95 | Flagged0.017 |
| 24L00019CONSTRUCTION OF GRAVEL ROAD - BUHANGIN - TIGATTO - MANDUG - CALLAWA - FATIMA ROAD, PACKAGE 11, DAVAO CITY | Region XI | Region XI | On-Going | ₱86.8M | 91% | High risk77 | Flagged0.015 |
| 23E00162SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD, BRGY. STA. CRUZ PROVINCIAL ROAD, SITIO CENTRO, BACO, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱116.8M | 54% | High risk68 | Flagged0.012 |
| 20L00170RECONSTRUCTION TO CONCRETE PAVEMENT ALONG JCT. DAANG MAHARLIKA ROAD - GOV. GREGORIO V. CAÑEDA ROAD - JCT. FS DIZON ROAD, DAVAO CITY | Region XI | Region XI | On-Going | ₱77.7M | 20% | Medium risk56 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 451 | 20LA0063CONSTRUCTION OF REVETMENT ALONG MASARA RIVER LEADING TO HIJO RIVER, BRGY. ELIZALDE, MACO COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱29.4M | 100% | Medium risk44 | —-0.070 |
| 452 | 20LA0124CONSTRUCTION OF REVETMENT ALONG MANAT RIVER LEADING TO AGUSAN RIVER, TAPIA SECTION, MONTEVISTA COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱30.9M | 100% | Medium risk44 | —-0.070 |
| 453 | 20LB0240CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BAGO RIVER, STA. 3+370 - STA. 3+422, STA. 3+426 - STA. 3+480, STA. 3+545 - STA. 3+848, STA. 3+851 - STA. 3+876, STA. 3+880 - STA. 3+897,STA. 3+901 - STA. 3+915, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱28.9M | 100% | Medium risk44 | —-0.077 |
| 454 | 20LB0164CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MATINA RIVER, MATINA RIVER OUTFALL SECTION, BOTH BANK, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱28.4M | 100% | Medium risk44 | —-0.073 |
| 455 | 19M00028RECONSTRUCTION TO CONCRETE PAVEMENT-AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD, K1947+147-K1947+600, K1948+200-K1949+269 KALAMANSIG, SULTAN KUDARAT | Region XII | Region XII | Completed | ₱97.6M | 100% | Medium risk44 | —-0.076 |
| 456 | 19LF0059CONSTRUCTION OF REVETMENT ALONG CATEEL RIVER (ARAGON SECTION), CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱44.1M | 100% | Medium risk44 | —-0.064 |
| 457 | 20LB0161CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MATINA RIVER, MATINA APLAYA SECTION, RIGHT BANK, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱24.5M | 100% | Medium risk44 | —-0.075 |
| 458 | 23LB0040CONSTRUCTION OF RETARDING BASIN PROTECTING NATIONAL ROAD, LA VERNA SECTION, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱11.3M | 12% | Medium risk44 | Flagged0.007 |
| 459 | 18LF0022CONSTRUCTION OF REVETMENT ALONG CATEEL RIVER PROTECTING COMPOSTELA-CATEEL ROAD (DAVAO OR. SIDE) UDIONGAN SECTION | Region XI | Davao Oriental 1st DEO | Completed | ₱29.5M | 100% | Medium risk44 | —-0.064 |
| 460 | 18LF0028CONSTRUCTION OF REVETMENT, UDIONGAN RIVER, CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱29.8M | 100% | Medium risk44 | —-0.065 |
| 461 | 18LF0023CONSTRUCTION OF REVETMENT ON STEEL SHEET PILES FOUNDATION, SAN ALFONSO | Region XI | Davao Oriental 1st DEO | Completed | ₱25.9M | 100% | Medium risk44 | —-0.063 |
| 462 | 18LF0010CONSTRUCTION OF REVETMENT ALONG CABASAGAN RIVER, BOSTON, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱19.6M | 100% | Medium risk44 | —-0.064 |
| 463 | 18LF0032CONSTRUCTION OF REVETMENT, DAKUNG BANWA RIVER BANK PROTECTION ALONG BOSTON RIVER, BOSTON, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱28.2M | 100% | Medium risk44 | —-0.064 |
| 464 | 22LB0127REHABILITATION OF MAMAY CREEK, ANGLIONGTO SECTION, STA. 0+000 - 0+735, BRGY. BUHANGIN, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱43.7M | 100% | Medium risk44 | —-0.075 |
| 465 | 18LB0078INSTALLATION OF GABION AND MATTRESSES ALONG DAVAO RIVER NASIN TIGATTO FLOOD CONTROL, STA. 17+847-STA. 18+190, STA. 18+440-STA.18+626 LEFT BANK, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱44.1M | 100% | Medium risk44 | —-0.077 |
| 466 | 20LB0076CONSTRUCTION OF DRAINAGE ALONG JCT. PORRAS-N. TORREST ST. - DEL PILAR ST. - JCT. DACUDAO AVE., DAVAO CITY | Region XI | Davao City DEO | Completed | ₱34.6M | 100% | Medium risk44 | —-0.074 |
| 467 | 19LB0066CONSTRUCTION OF FLOOD MITIGATION STRUCTURES-BUNAWAN RIVER, STA. 2+000-STA. 2+370 WEST SIDE BRGY. BUNAWAN, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱39.2M | 100% | Medium risk44 | —-0.076 |
| 468 | 18LB0082INSTALLATION OF GABIONS AND MATTRESSES ALONG DAVAO RIVER BASIN WAAN FLOOD CONTROL STA.17+460-STA.17+789 RIGHT BANK, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱29.4M | 100% | Medium risk44 | —-0.078 |
| 469 | 18LB0084INSTALLATION OF GABIONS AND MATTRESSES ALONG DAVAO RIVER MANDUG SECTION,DDF SUBDIVISION, BRGY. MANDUG,DAVAO CITY | Region XI | Davao City DEO | Completed | ₱39.2M | 100% | Medium risk44 | —-0.079 |
| 470 | 21LB0309CONSTRUCTION OF FLOOD MITIGATION STRUCTURE PROTECTING DAANG MAHARLIKA (MN) AT BRGY. BUNAWAN, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱24.5M | 100% | Medium risk44 | —-0.071 |
| 471 | 21LB0310CONSTRUCTION OF FLOOD MITIGATION STRUCTURE PROTECTING DAANG MAHARLIKA (MN) AT BRGY. SASA, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱24.5M | 100% | Medium risk44 | —-0.072 |
| 472 | 18LB0077INSTALLATION OF GABIONS AND MATTRESSES ALONG DAVAO RIVER FLOOD CONTROL STRUCTURES ALONG MANDUG SECTION,DDF SUBDIVISION, PHASE 5, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱21.6M | 100% | Medium risk44 | —-0.077 |
| 473 | 20LC0053CONSTRUCTION OF MANGALCAL BANK PROTECTION ALONG CARMEN - DAPECOL COMPOUND ROAD, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱38.4M | 100% | Medium risk44 | —-0.075 |
| 474 | 20LF0101CONSTRUCTION OF REVETMENT ALONG CARAGA RIVER(DON LEON BALANTE SECTION) CARAGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱39.2M | 100% | Medium risk44 | —-0.065 |
| 475 | 21LF0027CONSTRUCTION OF CARAGA COASTAL PROTECTION (BRGY. CENTRAL, CARAGA, DAVAO ORIENTAL (STA.0+000 - STA.0+360), CARAGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱39.2M | 100% | Medium risk44 | —-0.066 |