Contractor dossier
125 projects on file, including joint ventures this contractor is part of.
Total projects
125
Total budget
₱817.2M
Average progress
93.6%
Completion rate
85.6%
Average risk score
36.1
Medium risk on average, out of 100
Flagged as unusual
2
1.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 121 | ₱635.1M | 35.9 | 2 | 93.3% |
| Region IV-B | 4 | ₱182.1M | 41.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 62 | ₱232.8M | 31.9 | 0 | 92.2% |
| Roads | 45 | ₱437.9M | 37.9 | 0 | 98.6% |
| Flood Control and Drainage | 11 | ₱85.8M | 36.1 | 0 | 90.9% |
| Water Provision and Storage | 3 | ₱11.5M | 38.1 | 0 | 82.1% |
| GAA 2025 SSP | 2 | ₱7.7M | 90.6 | 1 | 85.5% |
| GAA 2025 OO-1 | 1 | ₱36.2M | 92.6 | 1 | 22.4% |
| OTHER | 1 | ₱5.3M | 45.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DB0150CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CANAL AT BARANGAY WAWA, NASUGBU, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 100% | High risk94 | —-0.006 |
| 25DE0139ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN DIVERSION ROAD, PACKAGE P, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱36.2M | 22% | High risk93 | Flagged0.003 |
| 25DB0174CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY PANTALAN, NASUGBU, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱2.9M | 71% | High risk87 | Flagged0.006 |
| 25DB0080CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY PUTING BATO EAST, CITY OF CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 1% | High risk75 | —-0.006 |
| 25DB0033ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJ FLOODS - FLOOD MANAGEMENT PROG - CONSTRUCTION/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL / SLOPE PROTECTION, BARANGAY ZONE 4, TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱9.5M | 0% | High risk68 | —-0.001 |
| 16DE0150MFO1 - NATIONAL ROAD NETWORK SERVICES, ASSETS PRESERVATION OF NATIONAL ROADSREHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADSINCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAYDEVELOPMENT AND MANAGEMENT-4 (HDM-4), SE | Region IV-A | Batangas 2nd DEO | Completed | ₱31.7M | 100% | High risk65 | —-0.072 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DB0174CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY PANTALAN, NASUGBU, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱2.9M | 71% | High risk87 | Flagged0.006 |
| 25DE0139ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN DIVERSION ROAD, PACKAGE P, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱36.2M | 22% | High risk93 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 18DB0119CONSTRUCTION OF MULTIPURPOSE BUILDING (COVERED COURT) BRGY. CAHILAN I, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱3.9M | 100% | Low risk26 | —-0.102 |
| 77 | 21DB0100CONSTRUCTION OF MULTIPURPOSE FACILITY (COVERED COURT) IN BARANGAY PUTINGKAHOY, LIAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱3.8M | 100% | Low risk26 | —-0.103 |
| 78 | 22DB0068CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN LIAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱3M | 100% | Low risk26 | —-0.099 |
| 79 | 24DB0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY , LIAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱3M | 100% | Low risk25 | —-0.100 |
| 80 | 25DB0118CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL) IN BARANGAY PAYAPA IBABA, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱1.9M | 5% | Low risk25 | —-0.033 |
| 81 | 20DB0045CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. GUINHAWA, TUY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.104 |
| 82 | 18DB0155CONSTRUCTION OF MULTIPURPOSE BUILDING (HEALTH CENTER) BRGY. NONONG CASTO, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱1.9M | 100% | Low risk25 | —-0.101 |
| 83 | 22DB0057CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN BARANGAY ANAK DAGAT, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2M | 100% | Low risk25 | —-0.104 |
| 84 | 19DB0046CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION 11, BALAYAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱1.9M | 100% | Low risk25 | —-0.103 |
| 85 | 21DB0148CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, IN BARANGAY PALINCARO, TUY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.101 |
| 86 | 19DB0076CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. ARUMAHAN, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱1.9M | 100% | Low risk25 | —-0.099 |
| 87 | 18DB0154CONSTRUCTION OF MULTIPURPOSE BUILDING (COVERED COURT) BRGY. ARUMAHAN, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱1.9M | 100% | Low risk25 | —-0.101 |
| 88 | 20DB0075CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY. HALANG, TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2M | 100% | Low risk25 | —-0.101 |
| 89 | 25DB0058CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROG (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY MUNTING INDANG, NASUGBU, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2M | 100% | Low risk25 | —-0.100 |
| 90 | 23DB0122CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. HUKAY, CALATAGAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2M | 100% | Low risk25 | —-0.098 |
| 91 | 18DB0079CONTINUATION OF CONSTRUCTION OF MULTIPURPOSE BUILDING (COVERED COURT), BRGY. CUBAMBA, TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱1.9M | 100% | Low risk25 | —-0.102 |
| 92 | 19DB0061CONCRETING OF ROAD, CALATAGAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱3.4M | 100% | Low risk25 | —-0.099 |
| 93 | 21DB01351. CONC OF RD IN BRGY. CAHIL, 2. CONC. OF RD IN BRGY. CORAL NI LOPEZ, 3. CONC. OF RD IN BGRY. DILA, 4. CONC. OF RD IN BRGY. LOMA, CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱4M | 100% | Low risk24 | —-0.104 |
| 94 | 21DB0055CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY BALISONG, TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱1.9M | 100% | Low risk24 | —-0.101 |
| 95 | 18DB0084OFF CARRIAGEWAY IMPROVEMENT: SECONDARY ROADS ALONG PALICO-BALAYAN-BATANGAS RD K0105+830 | Region IV-A | Batangas 1st DEO | Completed | ₱3.8M | 100% | Low risk24 | —-0.102 |
| 96 | 23DB0036CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2M | 100% | Low risk24 | —-0.101 |
| 97 | 19DB0058CONCRETING OF ROAD, BRBY. CALOOCAN, BALAYAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2.9M | 100% | Low risk24 | —-0.101 |
| 98 | 19DB0127CONCRETING OF ROAD, BRGY. CAHIL, CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱2.9M | 100% | Low risk24 | —-0.106 |
| 99 | 25DB0090CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN BARANGAY GAHOL, TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱1.9M | 100% | Low risk24 | —-0.104 |
| 100 | 19DB0159CONCRETING OF FARM TO MARKET ROAD IN BRGY. MAGAHIS, TUY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱4.7M | 100% | Low risk23 | —-0.053 |