Contractor dossier
33 projects on file, including joint ventures this contractor is part of.
Total projects
33
Total budget
₱480.5M
Average progress
99.3%
Completion rate
93.9%
Average risk score
48.5
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 32 | ₱460.7M | 47.8 | 0 | 99.2% |
| Region III | 1 | ₱19.8M | 69.6 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 22 | ₱265.1M | 48.4 | 0 | 100.0% |
| Roads | 8 | ₱151.3M | 49.9 | 0 | 96.9% |
| Flood Control and Drainage | 3 | ₱64.2M | 45.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CC0201CONSTRUCTION OF LOCAL ROAD INCLUDING BRIDGE, BRGY. BONGA MENOR, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱19.8M | 100% | High risk70 | —-0.070 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24OG0101REHABILITATION / CONSTRUCTION OF BOX CULVERT (DRAINAGE OUTFALL), NATIONAL KIDNEY AND TRANSPLANT INSTITUTE (NKTI) COMPOUND, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱29.7M | 100% | Medium risk46 | —-0.088 |
| 27 | 22OF0173REHABILITATION OF MULTI-PURPOSE FACILITY (COVERED COURT) AT BARANGAY BAHAY TORO, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱24.7M | 100% | Medium risk46 | —-0.089 |
| 28 | 24OF0084CONSTRUCTION OF DRAINAGE SYSTEMS AT ST. JUDE AND VARIOUS CONNECTING DRAINAGES AT BRGY. BAESA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱9.7M | 100% | Medium risk46 | —-0.050 |
| 29 | 24OG0019REHABILITATION OF ROAD, BARANGAY ROXAS, PHASE II, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱9.5M | 75% | Medium risk46 | —-0.053 |
| 30 | 24OG0014REHABILITATION OF ROAD, BARANGAY SANTOL, PHASE II, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱9.7M | 100% | Medium risk46 | —-0.100 |
| 31 | 23OF0013REHABILITATION OF ROAD WITH DRAINAGE IMPROVEMENT, BARANGAY RAMON MAGSAYSAY, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱9.7M | 100% | Medium risk46 | —-0.101 |
| 32 | 23OF0079REHABILITATION OF VARIOUS ROADS WITH DRAINAGE IMPROVEMENT AT BRGY. MARIBLO, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱7.6M | 100% | Medium risk46 | —-0.101 |
| 33 | 23OF0071REHABILITATION OF VARIOUS ROADS WITH DRAINAGE IMPROVEMENT AT BRGY. SIENNA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱6.7M | 100% | Medium risk46 | —-0.101 |