Contractor dossier
43 projects on file, including joint ventures this contractor is part of.
Total projects
43
Total budget
₱2.3B
Average progress
91.3%
Completion rate
74.4%
Average risk score
53.6
Medium risk on average, out of 100
Flagged as unusual
5
11.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 41 | ₱2.2B | 54.4 | 5 | 90.9% |
| Region IV-B | 2 | ₱78.4M | 37.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 13 | ₱841.5M | 54.3 | 0 | 99.5% |
| Bridges | 11 | ₱412.8M | 50.5 | 2 | 83.9% |
| Water Provision and Storage | 10 | ₱388.2M | 48.5 | 0 | 100.0% |
| Buildings and Facilities | 5 | ₱177.1M | 53.1 | 1 | 80.0% |
| Flood Control and Drainage | 2 | ₱180.9M | 57.8 | 0 | 92.6% |
| GAA 2025 OO-1 | 1 | ₱63M | 95.4 | 1 | 25.7% |
| OTHER | 1 | ₱236.4M | 83.7 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00068ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) K0722+200 - K0722+280, K0722+283 - K0722+503, K0723+000 - K0723+470, K0723+700 - K0723+930, K0725+0 | Region VIII | Region VIII | On-Going | ₱63M | 26% | High risk95 | Flagged0.015 |
| 19I00120ASSET PRESERVATION / REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CATBALOGAN DIVERSION RD. - KO801+(-850) - KO801+510, SAMAR | Region VIII | Region VIII | Completed | ₱236.4M | 100% | High risk84 | Flagged0.009 |
| 22IK0063CONSTRUCTION OF COASTAL DIKE AT PIER I TO BUNU-ANAN (PHASE 2), CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱144.1M | 85% | High risk68 | —-0.000 |
| 24I00137ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - RPIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0810+500 - K0813+120, K0813+600 - K0814+500, K0816+000 - K0817+000, K0826+200 - K0827+000, SAMAR 2ND | Region VIII | Region VIII | On-Going | ₱197.9M | 94% | High risk65 | —-0.022 |
| 23IK0045REHAB./RECONST./UPGRADING OF DAMGED PAVED ROADS - PRIMARY ROADS ALONG DAANG MAHARLIKA (SM) (SN ISIDRO-SN JUANICO BR), CATBALOGAN, PARANAS, HINABANGAN & CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱107.3M | 100% | High risk61 | —-0.036 |
| 21I00034CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-ACCESS ROAD FROM BRGY. POLANGI-BRGY. PANAYURAN-BRGY. LITERON LEADING TO LULUGAYAN FALLS, CALBIGA RIVER AND ...... CALBIGA SAMAR | Region VIII | Region VIII | Completed | ₱102.7M | 100% | High risk61 | —-0.072 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00152BRIDGE - WIDENING OF PERMANENT BRIDGES - PUPUA PARALLEL BR. ALONG MAHALIKA HIGHWAY (SN ISIDRO - SN JUANICO BR.) | Region VIII | Region VIII | On-Going | ₱33.7M | 0% | Medium risk47 | Flagged0.019 |
| 25I00068ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) K0722+200 - K0722+280, K0722+283 - K0722+503, K0723+000 - K0723+470, K0723+700 - K0723+930, K0725+0 | Region VIII | Region VIII | On-Going | ₱63M | 26% | High risk95 | Flagged0.015 |
| 18IK0115CONSTRUCTION OF UPDATED STANDARD 1-UNIT, 4-STOREY, TWENTY (20) CLASSROOM SCHOOL BUILDING, SAMAR NATIONAL SCHOOL, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱41.1M | 100% | Medium risk54 | Flagged0.015 |
| 19I00120ASSET PRESERVATION / REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CATBALOGAN DIVERSION RD. - KO801+(-850) - KO801+510, SAMAR | Region VIII | Region VIII | Completed | ₱236.4M | 100% | High risk84 | Flagged0.009 |
| 23IJ0106OO1: WIDENING OF PERMANENT BRIDGES, NIJAGA BR. (B00594SM) ALONG CALBAYOG DIVERSION RD, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱67.7M | 40% | Medium risk56 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25I00068ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) K0722+200 - K0722+280, K0722+283 - K0722+503, K0723+000 - K0723+470, K0723+700 - K0723+930, K0725+0 | Region VIII | Region VIII | On-Going | ₱63M | 26% | High risk95 | Flagged0.015 |
| 2 | 19I00120ASSET PRESERVATION / REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CATBALOGAN DIVERSION RD. - KO801+(-850) - KO801+510, SAMAR | Region VIII | Region VIII | Completed | ₱236.4M | 100% | High risk84 | Flagged0.009 |
| 3 | 22IK0063CONSTRUCTION OF COASTAL DIKE AT PIER I TO BUNU-ANAN (PHASE 2), CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱144.1M | 85% | High risk68 | —-0.000 |
| 4 | 24I00137ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - RPIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0810+500 - K0813+120, K0813+600 - K0814+500, K0816+000 - K0817+000, K0826+200 - K0827+000, SAMAR 2ND | Region VIII | Region VIII | On-Going | ₱197.9M | 94% | High risk65 | —-0.022 |
| 5 | 23IK0045REHAB./RECONST./UPGRADING OF DAMGED PAVED ROADS - PRIMARY ROADS ALONG DAANG MAHARLIKA (SM) (SN ISIDRO-SN JUANICO BR), CATBALOGAN, PARANAS, HINABANGAN & CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱107.3M | 100% | High risk61 | —-0.036 |
| 6 | 21I00034CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-ACCESS ROAD FROM BRGY. POLANGI-BRGY. PANAYURAN-BRGY. LITERON LEADING TO LULUGAYAN FALLS, CALBIGA RIVER AND ...... CALBIGA SAMAR | Region VIII | Region VIII | Completed | ₱102.7M | 100% | High risk61 | —-0.072 |
| 7 | 19IK0068CONSTRUCTION OF MODIFIED DESIGN WITH PARAPET, 4-STOREY, 20-CL SCHOOL BUILDING, TINGIB E/S, BASEY, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱50.8M | 100% | Medium risk57 | —-0.043 |
| 8 | 22IK0036CONST. OF ROAD, BONGA - PAMAMAS-AN - LINOOBAN - MARARANGSI - CALUYAHAN, MOTIONG, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱86.8M | 100% | Medium risk57 | —-0.077 |
| 9 | 23IJ0072OO1: REPLACEMENT OF PERMANENT WEAK BRIDGES - GANDARA BR. (B00359SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.), SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱87M | 87% | Medium risk57 | —-0.004 |
| 10 | 23IJ0106OO1: WIDENING OF PERMANENT BRIDGES, NIJAGA BR. (B00594SM) ALONG CALBAYOG DIVERSION RD, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱67.7M | 40% | Medium risk56 | Flagged0.001 |
| 11 | 20IJ0050(RE-ADVERTISED) LOCAL PROGRAM: CONSTRUCTION OF WATER SYSTEM (LEVEL 3), CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱68.7M | 100% | Medium risk55 | —-0.055 |
| 12 | 18IK0115CONSTRUCTION OF UPDATED STANDARD 1-UNIT, 4-STOREY, TWENTY (20) CLASSROOM SCHOOL BUILDING, SAMAR NATIONAL SCHOOL, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱41.1M | 100% | Medium risk54 | Flagged0.015 |
| 13 | 20IK0005ASSET PRESERVATION - REHAB./RECOSNTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS, SAN JUANICO - BASEY - SOHOTON ROAD, K0904+331 - K0905+400, K0906+000 - K0906+060 | Region VIII | Samar 2nd DEO | Completed | ₱48.1M | 100% | Medium risk54 | —-0.095 |
| 14 | 21IK0033CONST. OF CONCRETE ROAD - CONCRETING/REHAB. OF MAGDAWAT-LAYO-CANLOBO ROAD (PHASE 2), PINABACDAO, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱48.4M | 100% | Medium risk54 | —-0.087 |
| 15 | 20IJ0058LOCAL PROGRAM: CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, STA. MARGARITA, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱54.8M | 100% | Medium risk54 | —-0.042 |
| 16 | 21IK0040CONST./IMPROVEMENT OF ACCESS ROAD LEADING TO BURI BEACH, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱47.8M | 100% | Medium risk54 | —-0.096 |
| 17 | 22IJ0014CONSTRUCTION OF LEVEL III WATER SYSTEM, BRGY. CABUNGAAN AND BRGY. ILIJAN, STO. NIÑO, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱48.9M | 100% | Medium risk53 | —-0.063 |
| 18 | 24IJ0076CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, GANDARA, SAMAR (PHASE 1) | Region VIII | Samar 1st DEO | On-Going | ₱19.7M | 0% | Medium risk53 | —-0.018 |
| 19 | 20IK0061ASPHALT OVERLAY OF CATBALOGAN CITY | Region VIII | Samar 2nd DEO | Completed | ₱47.2M | 100% | Medium risk53 | —-0.095 |
| 20 | 18IK0118CONSTRUCTION OF UPDATED STANDARD 1-UNIT, 4-STOREY, SIXTEEN (16) CLASSROOM SCHOOL BUILDING, SAMAR NATIONAL SCHOOL, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱36.6M | 100% | Medium risk51 | —-0.046 |
| 21 | 18IK0107CONST. OF MODIFIED DESIGN WITH PARAPET, 1-UNIT, 2-STOREY, TEN (10) CL. SCHOOL BLDG., WRIGHT NHS, WRIGHT, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱28.9M | 100% | Medium risk50 | —-0.049 |
| 22 | 21IJ0067CONSTRUCTION OF LEVEL III WATER SUPPLY PROJECT, TARANGNAN, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱42.1M | 100% | Medium risk50 | —-0.061 |
| 23 | 19IK0040WIDENING OF PERMANENT BRIDGES, HINABANGAN BRIDGE (B00416SM) ALONG HINABANGAN DIVERSION ROAD, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱37.2M | 100% | Medium risk50 | —-0.059 |
| 24 | 20IK0067WIDENING OF PERMANENT BRIDGE, POLANGI BRIDGE (B00386SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.), K0848+1066 | Region VIII | Samar 2nd DEO | Completed | ₱29.3M | 100% | Medium risk50 | —-0.052 |
| 25 | 20IK0002PREVENTIVE MAINTENANCE OF ROAD ASPHALT OVERLAY DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR), K0809+350 - K0810+131.5 | Region VIII | Samar 2nd DEO | Completed | ₱28.9M | 100% | Medium risk50 | —-0.095 |