Opening the dossier…
Opening the dossier…
Contractor dossier
4 projects on file, including joint ventures this contractor is part of.
Total projects
4
Total budget
₱66.9M
Average progress
100.0%
Completion rate
100.0%
Average risk score
44.8
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 4 | ₱66.9M | 44.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 2 | ₱57.1M | 46.2 | 0 | 100.0% |
| Roads | 2 | ₱9.8M | 43.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24AJ0008CONSTRUCTION OF SLOPE PROTECTION ALONG INGALERA RIVER, BARANGAY BARANG, MALASIQUI, PANGASINAN (PHASE V) | Region I | Pangasinan 4th DEO | Completed | ₱47.7M | 100% | Medium risk49 | —-0.069 |
| 2 | 24AJ0037CONSTRUCTION OF ROAD, BARANGAY MANZON, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | Medium risk44 | —-0.089 |
| 3 | 23AJ0145CONSTRUCTION OF SLOPE PROTECTION, BRGY. CABATLING, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱9.4M | 100% | Medium risk43 | —-0.022 |
| 4 | 24AJ0013CONSTRUCTION OF ROAD, BARANGAY GOLIMAN, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.092 |