Contractor dossier
535 projects on file, including joint ventures this contractor is part of.
Total projects
535
Total budget
₱17.2B
Average progress
97.1%
Completion rate
82.8%
Average risk score
45.5
Medium risk on average, out of 100
Flagged as unusual
21
3.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 524 | ₱16.7B | 45.4 | 20 | 97.2% |
| Negros Island Region | 7 | ₱325.2M | 52.5 | 0 | 94.0% |
| Region VII | 4 | ₱150.5M | 46.5 | 1 | 97.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 196 | ₱7.8B | 48.3 | 3 | 96.6% |
| Buildings and Facilities | 119 | ₱1.5B | 34.9 | 1 | 98.6% |
| Flood Control and Drainage | 106 | ₱4.2B | 48.4 | 0 | 99.2% |
| Water Provision and Storage | 41 | ₱604.7M | 30.7 | 0 | 100.0% |
| Bridges | 40 | ₱944.6M | 40.3 | 2 | 98.7% |
| OTHER | 27 | ₱1.6B | 79.4 | 13 | 84.9% |
| GAA 2025 OO-2 | 4 | ₱457M | 93.6 | 0 | 92.0% |
| GAA 2025 SSP | 2 | ₱39.5M | 95.6 | 2 | 41.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IF0098CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, KANANGA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱29.7M | 46% | High risk96 | Flagged0.021 |
| 25IF0095CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF ORMOC, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱9.8M | 37% | High risk95 | Flagged0.023 |
| 25IF0010CONSTRUCTION OF LEONDONI FLOOD CONTROL STRUCTURE, BARANGAY LEONDONI, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱96M | 99% | High risk94 | —-0.013 |
| 25IF0009CONSTRUCTION OF SANTO NIÑO FLOOD CONTROL STRUCTURE, BARANGAY SANTO NIÑO, KANANGA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱96M | 99% | High risk94 | —-0.013 |
| 25IF0025CONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTURE, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱129M | 78% | High risk93 | —-0.002 |
| 25IG0031CONSTRUCTION OF MACAHILA FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, MACAHILA RIVER BASIN, BAYBAY CITY, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱136M | 92% | High risk93 | —-0.002 |
| 25IF0078CONCRETING OF BRGY. DOMONAR - BRGY. CAMBACBAC FMR, BRGY. DOMONAR, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱49.7M | 75% | High risk91 | Flagged0.050 |
| 25IF0077CONCRETING OF BRGY. LIBAS - BRGY. CALUNASAN FMR, BRGY. LIBAS AND BRGY. CALUNASAN, MERIDA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱49.7M | 54% | High risk91 | Flagged0.058 |
| 25IF0084CONCRETING OF BRGY. NASUNOGAN TO BRGY. AIRPORT AND LILO-AN FMR (PHASE I), BRGY. NASUNOGAN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱14.9M | 99% | High risk90 | Flagged0.037 |
| 24I00415CONSTRUCTION OF INNOVATION INCUBATION CENTER BUILDING - PALOMPON INSTITUTE OF TECHNOLOGY | Region VIII | Region VIII | On-Going | ₱34.6M | 11% | High risk90 | Flagged0.067 |
| 23ID0103CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP) -CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES,INDUSTRIES ECONOMIC ZONES(ROADS LEVERAGING FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT) MINUHANG (BALUARTE) -BALUD AND BALUD-DUKA ROAD CON | Region VIII | Leyte 2nd DEO | On-Going | ₱144.7M | 100% | High risk83 | Flagged0.021 |
| 18IE0082CONSTRUCTION OF CALUBIAN-JUBAY-DAJA ROAD INCLUDING BRIDGES, CALUBIAN AND SAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱160.2M | 100% | High risk83 | —-0.015 |
| 24I00370BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO TAB-OK, BARANGAY NALIBUNAN, ABUYOG, LEYTE | Region VIII | Region VIII | On-Going | ₱69.2M | 36% | High risk82 | Flagged0.015 |
| 18IE0070NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT TERTIARY ROADS, TABANGO-CATMON-LA FORTUNA-MANLAWAAN-GIMARCO RD., K1036+800 - K1038+000 TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱91.6M | 100% | High risk82 | —-0.025 |
| 18IE0069NETWORK DEVELOPMENT PROGRAM OFF-CARRIAGEWAY IMPROVEMENT SECONDARY ROADS, SAMBULAWAN JCT.-CALAGUISE-CALUBIAN RD., K0984+(-300)-K0984+766, K0984+838-K0985+505 LEYTE, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱92.6M | 100% | High risk82 | —-0.027 |
| 23IF0065CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ORMOC CITY DIVERSION ROAD (NAUNGAN - LINAO - ALEGRIA - POBLACION), OMOC CITY | Region VIII | Leyte 4th DEO | Completed | ₱105.5M | 100% | High risk82 | —-0.019 |
| 24I00168FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL (BARANGAY ZONE 5 SECTION SEGMENT 3), SOGOD, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱48.2M | 96% | High risk82 | Flagged0.000 |
| 24I00167FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL (BARANGAY ZONE 5 SECTION SEGMENT 2), SOGOD, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱48.2M | 97% | High risk82 | —-0.001 |
| 20IF0011WIDENING OF PERMANENT BRIDGES, BACAN BR. (B00582LT) ALONG ORMOC-BAYBAY SOUTHERN LEYTE BDRY. ROAD | Region VIII | Leyte 4th DEO | Completed | ₱69.6M | 100% | High risk81 | —-0.035 |
| 18IE0072NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT- SECONDARY ROADS, CALUBIAN JCT-SAN ISIDRO-TABANGO-VILLABA-PALOMPON ROAD, K1011+952 - K1013+700 SAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱91.7M | 100% | High risk81 | —-0.028 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24I00415CONSTRUCTION OF INNOVATION INCUBATION CENTER BUILDING - PALOMPON INSTITUTE OF TECHNOLOGY | Region VIII | Region VIII | On-Going | ₱34.6M | 11% | High risk90 | Flagged0.067 |
| 25IF0077CONCRETING OF BRGY. LIBAS - BRGY. CALUNASAN FMR, BRGY. LIBAS AND BRGY. CALUNASAN, MERIDA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱49.7M | 54% | High risk91 | Flagged0.058 |
| 25IF0078CONCRETING OF BRGY. DOMONAR - BRGY. CAMBACBAC FMR, BRGY. DOMONAR, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱49.7M | 75% | High risk91 | Flagged0.050 |
| 25IF0084CONCRETING OF BRGY. NASUNOGAN TO BRGY. AIRPORT AND LILO-AN FMR (PHASE I), BRGY. NASUNOGAN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱14.9M | 99% | High risk90 | Flagged0.037 |
| 25IF0095CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF ORMOC, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱9.8M | 37% | High risk95 | Flagged0.023 |
| 23ID0103CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP) -CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES,INDUSTRIES ECONOMIC ZONES(ROADS LEVERAGING FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT) MINUHANG (BALUARTE) -BALUD AND BALUD-DUKA ROAD CON | Region VIII | Leyte 2nd DEO | On-Going | ₱144.7M | 100% | High risk83 | Flagged0.021 |
| 25IF0098CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, KANANGA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱29.7M | 46% | High risk96 | Flagged0.021 |
| 22IF0101CONSTRUCTION OF PALOMPON LEYTE PORT | Region VIII | Leyte 4th DEO | On-Going | ₱19.5M | 0% | Medium risk53 | Flagged0.020 |
| 24IF0123REPAIR/REHABILITATION/IMPROVEMENT OF EXISTING CROSS DRAIN & DRAINAGE SYSTEM STRUCTURE ALONG PALO - CARIGARA - ORMOC ROAD - K0988+588 - K0989+073 | Region VIII | Leyte 4th DEO | On-Going | ₱19.2M | 0% | High risk78 | Flagged0.020 |
| 22IE0023ACCESS ROAD LEADING TO SILAD PORT, VILLABA, LEYTE (NEW ROUTE) VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱47.8M | 84% | High risk80 | Flagged0.017 |
| 22IE0041REHABILITATION OF ROAD ALONG RAILES-ENAGE-ANISLAGAN-CASIONGAN (CALUBIAN) VIA SITIO AIRPORT-SITIO CROSSING-SITIO LIMITE (DAJA DAKU) AND SITIO CROSSING-CALUBIAN, LEYTECALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱48M | 77% | High risk80 | Flagged0.017 |
| 24I00370BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO TAB-OK, BARANGAY NALIBUNAN, ABUYOG, LEYTE | Region VIII | Region VIII | On-Going | ₱69.2M | 36% | High risk82 | Flagged0.015 |
| 17IE0062OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, CALUBIAN JCT.-SAN ISIDRO-TABANGO-VILLABA-PALOMPON ROAD, K1005+(-346)-K1005+644; K1005+662-K1006+429; K1006+450-K1008+074; K1008+089-K1008+574; K1008+713-K1010+857; K1015+000-K1016+595; K1016+610-K1017+560; K | Region VIII | Leyte 3rd DEO | On-Going | ₱91.6M | 100% | High risk60 | Flagged0.015 |
| 25IE0059CONCRETING OF BRGY. VILLAHERMOSA TO BRGY. GARRIDO FMR, BRGY. VILLAHERMOSA AND BRGY. GARRIDO, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱14.9M | 30% | Medium risk52 | Flagged0.010 |
| 22IE0048CONSTRUCTION OF CALUBIAN-JUBAY-DAJA RD. (MISSING GAP), CALUBIAN, LEYTECALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱38.4M | 100% | High risk77 | Flagged0.009 |
| 25IF0088CONCRETING OF BRGY. MALAZARTE - BRGY. CAMBADBAD FMR, BRGY. MALAZARTE AND BRGY. CAMBADBAD, MATAG-OB, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱47.8M | 59% | Medium risk55 | Flagged0.007 |
| 23H00124CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG GARING-PANAS ROAD, PHASE II, CONSOLACION, CEBU | Region VII | Region VII | On-Going | ₱72.3M | 91% | High risk68 | Flagged0.003 |
| 21I00028BRIDGE - CONSTRUCTION OF NEW BRIDGES - CALAGUISE BR. ALONG SAMBULAWAN JCT. - CALAGUISE - CALUBIAN RD., BRGY. CALAGUISE, LEYTE, LEYTE | Region VIII | Region VIII | On-Going | ₱45.8M | 93% | Medium risk50 | Flagged0.002 |
| 22I00028BRIDGE - CONSTRUCTION OF NEW BRIDGES, CALAGUISE BR. (B00093LT) ALONG SAMBULAWAN JCT. - CALAGUISE - CALUBIAN RD., LEYTE 3RD LD | Region VIII | Region VIII | On-Going | ₱28.9M | 67% | Medium risk50 | Flagged0.002 |
| 25IF0034CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), LAKE DANAO - GAAS - SITIO MAGLAHOG - QUEZON JR. ROAD LEADING TO LAKE DANAO AND LAKE KASUDSURAN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱32.7M | 74% | High risk78 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 301 | 21IF0023RECONSTRUCTION TO CONCRETE PAVEMENT-PALOMPON-ISABEL-MERIDA-ORMOC ROAD K1088+050-K1088+068 (B); K1088+202-K1088+220(B); K1088+329-K1088+409(R); K1088+655-K1088+673(B); K1089+000-K1089+027(B); K1089+027-K1089+045(L); K1089+045-K1089+392(B); K1089+392-K1089+ | Region VIII | Leyte 4th DEO | Completed | ₱17.9M | 100% | Medium risk48 | —-0.095 |
| 302 | 23IE0054ROAD CONCRETING TO HIBULANGAN TO CAPINAHAN, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱6.8M | 100% | Medium risk48 | —-0.093 |
| 303 | 25HN0132SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF REVETMENT WALL ALONG BUTUANON RIVER, BARANGAY TABOK (PHASE 7), MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱25M | 100% | Medium risk48 | —-0.060 |
| 304 | 20IE0068CONSTRUCTION OF SUBA SEAWALL, SUBA, VILLABA, LEYTEVILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱46.8M | 100% | Medium risk48 | —-0.083 |
| 305 | 19IG0002NETWORK DEVELOPMENT IMPROVEMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - BATO-BONTOC RD - K1111+000 TO K1112+234, K1112+301 TO K1113+105, K1114+172 TO K1114+457, K1114+466 - K1114+740, BATO, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱15.9M | 100% | Medium risk48 | —-0.094 |
| 306 | 18IF0024CONSTRUCTION OF BRGY. SAN DIONISIO ROAD, MATAG-OB, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱5.6M | 100% | Medium risk48 | —-0.095 |
| 307 | 23IF0069REHABILITATION OF THE ORMOC WATER SYSTEM, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱19.6M | 100% | Medium risk48 | —-0.061 |
| 308 | 22IG0019PREVENTIVE MAINTENANCE(ASPHALT OVERLAY) ALONG ORMOC-BAYBAY-SOUTHERN LEYTE BDRY.RD- K1053+151-K1053+305,K1053+382-K1053+829,K1054+000-K1055+019 | Region VIII | Leyte 5th DEO | Completed | ₱23.3M | 100% | Medium risk47 | —-0.093 |
| 309 | 23IG0055EMERGENCY REPAIR/REHABILITATION/IMPROVEMENT OF OFF-CARRIAGEWAY ALONG ORMOC - BAYBAY - SOUTHERN LEYTE BDRY. RD. - K1100+700 - K1101+000, K1102+700 - K1105+500, HILONGOS, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱24.1M | 100% | Medium risk47 | —-0.094 |
| 310 | 18IG0032CONSTRUCTION OF POTABLE WATER RESERVOIR, MUNICIPALITIES OF HILONGOS AND HINDANG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱23.3M | 100% | Medium risk47 | —-0.061 |
| 311 | 18IF0047CONSTRUCTION OF BRGY. MANLILINAO - BRGY. SAN SEBASTIAN, MATAG-OB ROAD, BRGY. MANLILINAO, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.096 |
| 312 | 23IF0100CONSTRUCTION OF SOLAR WATER SYSTEM, ALBUERA, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.061 |
| 313 | 23IE0062REPAIR/REHAB. OF THE DESTROYED SLOPE PROTECTION ALONG THE PROJECT CAUSED BY TYPHON AGATON, SAN ANTONIO HOMES, BRGY. LINAO, SAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱37.4M | 100% | Medium risk47 | —-0.083 |
| 314 | 23I00137CLUSTER 22: 1. BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PRES QUEZON, LILOAN, SOUTHERN LEYTE; 2. BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOS | Region VIII | Region VIII | On-Going | ₱8.8M | 100% | Medium risk47 | —-0.050 |
| 315 | 21IF0073CONSTRUCTION OF WATER SUPPLY (LEVEL III), KANANGA, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱18.6M | 100% | Medium risk47 | —-0.062 |
| 316 | 21IF0025CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO LIBERTY TERRESTRIAL ECO ADVENTURE PARK, PALOMPON, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱9.3M | 100% | Medium risk47 | —-0.095 |
| 317 | 22IF0028CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS, ORMOC - BAYBAY - SO. LEYTE BRDY. RD., K1013+744 - K1014+276 | Region VIII | Leyte 4th DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.089 |
| 318 | 23IF0096CONSTRUCTION OF SOLAR WATER SYSTEM, MERIDA, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.063 |
| 319 | 18IC0016REHAB./IMPROVEMENT OF FLOOD CONTROL WALL ALONG BINAHAAN RIVER, TANAUAN SECTION BOTH SIDES STA. 10+250 - STA. 10+477, TANAUAN, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱41.4M | 100% | Medium risk47 | —-0.081 |
| 320 | 20IE0045CONSTRUCTION OF LINAO FLOOD CONTROL, SAN ISIDRO, LEYTESAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱18.9M | 100% | Medium risk47 | —-0.082 |
| 321 | 21IF0063OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/ CONSTRUCTION- ORMOC- BAYBAY SOUTHERN LEYTE BDRY RD K1013+710-K1014-249 | Region VIII | Leyte 4th DEO | Completed | ₱8.4M | 100% | Medium risk47 | —-0.095 |
| 322 | 21IF0030CONSTRUCTION OF DRAINAGE STRUCTURE ALONG PALO-CARIGARA-ORMOC RD, K0998+952.05-K1000+126,K1002+303-K1002+520 | Region VIII | Leyte 4th DEO | Completed | ₱9.3M | 100% | Medium risk47 | —-0.095 |
| 323 | 21IF0035ROAD WIDENING - PALOMPON-ISABEL-MERIDA-ORMOC RD, K1114+523 - K1115+000 | Region VIII | Leyte 4th DEO | Completed | ₱12.6M | 100% | Medium risk47 | —-0.094 |
| 324 | 18IE0037CONSTRUCTION OF FLOOD CONTROL ALONG CAMPOKPOK RIVER, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱18.9M | 100% | Medium risk47 | —-0.081 |
| 325 | 19IE0029CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF FLOOD CONTROL ALONG CAMPOKPOK RIVERBRGY. CAMPOKPOK, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱19M | 100% | Medium risk47 | —-0.083 |