535 projects on file, including joint ventures this contractor is part of.
Total projects
535
Total budget
₱17.2B
Average progress
97.1%
Completion rate
82.8%
Average risk score
45.5
Medium risk on average, out of 100
Flagged as unusual
21
3.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 524 | ₱16.7B | 45.4 | 20 | 97.2% |
| Negros Island Region | 7 | ₱325.2M | 52.5 | 0 | 94.0% |
| Region VII | 4 | ₱150.5M | 46.5 | 1 | 97.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 196 | ₱7.8B | 48.3 | 3 | 96.6% |
| Buildings and Facilities | 119 | ₱1.5B | 34.9 | 1 | 98.6% |
| Flood Control and Drainage | 106 | ₱4.2B | 48.4 | 0 | 99.2% |
| Water Provision and Storage | 41 | ₱604.7M | 30.7 | 0 | 100.0% |
| Bridges | 40 | ₱944.6M | 40.3 | 2 | 98.7% |
| OTHER | 27 | ₱1.6B | 79.4 | 13 | 84.9% |
| GAA 2025 OO-2 | 4 | ₱457M | 93.6 | 0 | 92.0% |
| GAA 2025 SSP | 2 | ₱39.5M | 95.6 | 2 | 41.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IF0098CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, KANANGA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱29.7M | 46% | High risk96 | Flagged0.021 |
| 25IF0095CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF ORMOC, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱9.8M | 37% | High risk95 | Flagged0.023 |
| 25IF0010CONSTRUCTION OF LEONDONI FLOOD CONTROL STRUCTURE, BARANGAY LEONDONI, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱96M | 99% | High risk94 | —-0.013 |
| 25IF0009CONSTRUCTION OF SANTO NIÑO FLOOD CONTROL STRUCTURE, BARANGAY SANTO NIÑO, KANANGA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱96M | 99% | High risk94 | —-0.013 |
| 25IF0025CONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTURE, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱129M | 78% | High risk93 | —-0.002 |
| 25IG0031CONSTRUCTION OF MACAHILA FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, MACAHILA RIVER BASIN, BAYBAY CITY, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱136M | 92% | High risk93 | —-0.002 |
| 25IF0078CONCRETING OF BRGY. DOMONAR - BRGY. CAMBACBAC FMR, BRGY. DOMONAR, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱49.7M | 75% | High risk91 | Flagged0.050 |
| 25IF0077CONCRETING OF BRGY. LIBAS - BRGY. CALUNASAN FMR, BRGY. LIBAS AND BRGY. CALUNASAN, MERIDA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱49.7M | 54% | High risk91 | Flagged0.058 |
| 25IF0084CONCRETING OF BRGY. NASUNOGAN TO BRGY. AIRPORT AND LILO-AN FMR (PHASE I), BRGY. NASUNOGAN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱14.9M | 99% | High risk90 | Flagged0.037 |
| 24I00415CONSTRUCTION OF INNOVATION INCUBATION CENTER BUILDING - PALOMPON INSTITUTE OF TECHNOLOGY | Region VIII | Region VIII | On-Going | ₱34.6M | 11% | High risk90 | Flagged0.067 |
| 23ID0103CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP) -CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES,INDUSTRIES ECONOMIC ZONES(ROADS LEVERAGING FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT) MINUHANG (BALUARTE) -BALUD AND BALUD-DUKA ROAD CON | Region VIII | Leyte 2nd DEO | On-Going | ₱144.7M | 100% | High risk83 | Flagged0.021 |
| 18IE0082CONSTRUCTION OF CALUBIAN-JUBAY-DAJA ROAD INCLUDING BRIDGES, CALUBIAN AND SAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱160.2M | 100% | High risk83 | —-0.015 |
| 24I00370BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO TAB-OK, BARANGAY NALIBUNAN, ABUYOG, LEYTE | Region VIII | Region VIII | On-Going | ₱69.2M | 36% | High risk82 | Flagged0.015 |
| 18IE0070NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT TERTIARY ROADS, TABANGO-CATMON-LA FORTUNA-MANLAWAAN-GIMARCO RD., K1036+800 - K1038+000 TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱91.6M | 100% | High risk82 | —-0.025 |
| 18IE0069NETWORK DEVELOPMENT PROGRAM OFF-CARRIAGEWAY IMPROVEMENT SECONDARY ROADS, SAMBULAWAN JCT.-CALAGUISE-CALUBIAN RD., K0984+(-300)-K0984+766, K0984+838-K0985+505 LEYTE, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱92.6M | 100% | High risk82 | —-0.027 |
| 23IF0065CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ORMOC CITY DIVERSION ROAD (NAUNGAN - LINAO - ALEGRIA - POBLACION), OMOC CITY | Region VIII | Leyte 4th DEO | Completed | ₱105.5M | 100% | High risk82 | —-0.019 |
| 24I00168FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL (BARANGAY ZONE 5 SECTION SEGMENT 3), SOGOD, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱48.2M | 96% | High risk82 | Flagged0.000 |
| 24I00167FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL (BARANGAY ZONE 5 SECTION SEGMENT 2), SOGOD, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱48.2M | 97% | High risk82 | —-0.001 |
| 20IF0011WIDENING OF PERMANENT BRIDGES, BACAN BR. (B00582LT) ALONG ORMOC-BAYBAY SOUTHERN LEYTE BDRY. ROAD | Region VIII | Leyte 4th DEO | Completed | ₱69.6M | 100% | High risk81 | —-0.035 |
| 18IE0072NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT- SECONDARY ROADS, CALUBIAN JCT-SAN ISIDRO-TABANGO-VILLABA-PALOMPON ROAD, K1011+952 - K1013+700 SAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱91.7M | 100% | High risk81 | —-0.028 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24I00415CONSTRUCTION OF INNOVATION INCUBATION CENTER BUILDING - PALOMPON INSTITUTE OF TECHNOLOGY | Region VIII | Region VIII | On-Going | ₱34.6M | 11% | High risk90 | Flagged0.067 |
| 25IF0077CONCRETING OF BRGY. LIBAS - BRGY. CALUNASAN FMR, BRGY. LIBAS AND BRGY. CALUNASAN, MERIDA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱49.7M | 54% | High risk91 | Flagged0.058 |
| 25IF0078CONCRETING OF BRGY. DOMONAR - BRGY. CAMBACBAC FMR, BRGY. DOMONAR, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱49.7M | 75% | High risk91 | Flagged0.050 |
| 25IF0084CONCRETING OF BRGY. NASUNOGAN TO BRGY. AIRPORT AND LILO-AN FMR (PHASE I), BRGY. NASUNOGAN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱14.9M | 99% | High risk90 | Flagged0.037 |
| 25IF0095CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF ORMOC, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱9.8M | 37% | High risk95 | Flagged0.023 |
| 23ID0103CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP) -CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES,INDUSTRIES ECONOMIC ZONES(ROADS LEVERAGING FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT) MINUHANG (BALUARTE) -BALUD AND BALUD-DUKA ROAD CON | Region VIII | Leyte 2nd DEO | On-Going | ₱144.7M | 100% | High risk83 | Flagged0.021 |
| 25IF0098CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, KANANGA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱29.7M | 46% | High risk96 | Flagged0.021 |
| 22IF0101CONSTRUCTION OF PALOMPON LEYTE PORT | Region VIII | Leyte 4th DEO | On-Going | ₱19.5M | 0% | Medium risk53 | Flagged0.020 |
| 24IF0123REPAIR/REHABILITATION/IMPROVEMENT OF EXISTING CROSS DRAIN & DRAINAGE SYSTEM STRUCTURE ALONG PALO - CARIGARA - ORMOC ROAD - K0988+588 - K0989+073 | Region VIII | Leyte 4th DEO | On-Going | ₱19.2M | 0% | High risk78 | Flagged0.020 |
| 22IE0023ACCESS ROAD LEADING TO SILAD PORT, VILLABA, LEYTE (NEW ROUTE) VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱47.8M | 84% | High risk80 | Flagged0.017 |
| 22IE0041REHABILITATION OF ROAD ALONG RAILES-ENAGE-ANISLAGAN-CASIONGAN (CALUBIAN) VIA SITIO AIRPORT-SITIO CROSSING-SITIO LIMITE (DAJA DAKU) AND SITIO CROSSING-CALUBIAN, LEYTECALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱48M | 77% | High risk80 | Flagged0.017 |
| 24I00370BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO TAB-OK, BARANGAY NALIBUNAN, ABUYOG, LEYTE | Region VIII | Region VIII | On-Going | ₱69.2M | 36% | High risk82 | Flagged0.015 |
| 17IE0062OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, CALUBIAN JCT.-SAN ISIDRO-TABANGO-VILLABA-PALOMPON ROAD, K1005+(-346)-K1005+644; K1005+662-K1006+429; K1006+450-K1008+074; K1008+089-K1008+574; K1008+713-K1010+857; K1015+000-K1016+595; K1016+610-K1017+560; K | Region VIII | Leyte 3rd DEO | On-Going | ₱91.6M | 100% | High risk60 | Flagged0.015 |
| 25IE0059CONCRETING OF BRGY. VILLAHERMOSA TO BRGY. GARRIDO FMR, BRGY. VILLAHERMOSA AND BRGY. GARRIDO, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱14.9M | 30% | Medium risk52 | Flagged0.010 |
| 22IE0048CONSTRUCTION OF CALUBIAN-JUBAY-DAJA RD. (MISSING GAP), CALUBIAN, LEYTECALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱38.4M | 100% | High risk77 | Flagged0.009 |
| 25IF0088CONCRETING OF BRGY. MALAZARTE - BRGY. CAMBADBAD FMR, BRGY. MALAZARTE AND BRGY. CAMBADBAD, MATAG-OB, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱47.8M | 59% | Medium risk55 | Flagged0.007 |
| 23H00124CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG GARING-PANAS ROAD, PHASE II, CONSOLACION, CEBU | Region VII | Region VII | On-Going | ₱72.3M | 91% | High risk68 | Flagged0.003 |
| 21I00028BRIDGE - CONSTRUCTION OF NEW BRIDGES - CALAGUISE BR. ALONG SAMBULAWAN JCT. - CALAGUISE - CALUBIAN RD., BRGY. CALAGUISE, LEYTE, LEYTE | Region VIII | Region VIII | On-Going | ₱45.8M | 93% | Medium risk50 | Flagged0.002 |
| 22I00028BRIDGE - CONSTRUCTION OF NEW BRIDGES, CALAGUISE BR. (B00093LT) ALONG SAMBULAWAN JCT. - CALAGUISE - CALUBIAN RD., LEYTE 3RD LD | Region VIII | Region VIII | On-Going | ₱28.9M | 67% | Medium risk50 | Flagged0.002 |
| 25IF0034CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), LAKE DANAO - GAAS - SITIO MAGLAHOG - QUEZON JR. ROAD LEADING TO LAKE DANAO AND LAKE KASUDSURAN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱32.7M | 74% | High risk78 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 18IE0042NETWORK DEVELOPMENT-OFF-CARRIAGEWAY IMPROVEMENT-TERTIARY ROADS, STO. ROSARIO-VILLABA ROAD, S00127L, K1003+(-306) - K1003+(-158), K1003+(-158)-K1003+000, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱17.3M | 100% | High risk77 | —-0.039 |
| 27 | 24IE0073CONSTRUCTION OF ROAD, BARANGAY CONSUEGRA TO BARANGAY TAPOL LEYTE, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱39.6M | 100% | High risk77 | —-0.041 |
| 28 | 22IE0048CONSTRUCTION OF CALUBIAN-JUBAY-DAJA RD. (MISSING GAP), CALUBIAN, LEYTECALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱38.4M | 100% | High risk77 | Flagged0.009 |
| 29 | 18IE0039CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION, ACCESS ROAD LEADING TO BUGA-BUGA HILLS BRGY. BUGA-BUGA, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱46.5M | 100% | High risk77 | —-0.040 |
| 30 | 18IE0063CONSTRUCTION OF CALBUGOS-ILIGAY-CAGNOCOT-LAYOG ROAD,VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱46.3M | 100% | High risk77 | —-0.040 |
| 31 | 23H00124CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG GARING-PANAS ROAD, PHASE II, CONSOLACION, CEBU | Region VII | Region VII | On-Going | ₱72.3M | 91% | High risk68 | Flagged0.003 |
| 32 | 24IF0114CONSTRUCTION OF MULTI-PURPOSE BUILDING, COMMUNITY COLLEGE BUILDING, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱24.7M | 100% | High risk68 | —-0.038 |
| 33 | 17I00078CONSTRUCTION OF EVACUATION CENTER, BARANGAY SUBA, VILLABA, LEYTE | Region VIII | Region VIII | Completed | ₱33M | 100% | High risk66 | —-0.065 |
| 34 | 24I00150SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF (RCDG) REINFORCED CONCRETE DECK GIRDER BRIDGE FROM BARANGAY MAHAGN | Region VIII | Region VIII | On-Going | ₱144.7M | 88% | High risk65 | —-0.002 |
| 35 | 21I00069CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - REHABILITATION/IMPROVEMENT OF ROAD ALONG RAILES - ENAGE - ANISLAGAN - CASIONGAN (CALUBIAN) VIA SITIO AIRPORT - SITIO CROSSING - SITIO ....SAN ISIDRO, LEYTE | Region VIII | Region VIII | Completed | ₱189.6M | 100% | High risk65 | —-0.052 |
| 36 | 24I00096NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROAD - DAANG MAHARLIKA (LT), K0981+000 - K0982+200, K0983+139 - K0983+214, K0983+453 - K0983+915, K0996+155 - K0997+455, K1001+466 - K1002+085, LEYTE 5TH LD | Region VIII | Region VIII | On-Going | ₱259.7M | 89% | High risk65 | —-0.011 |
| 37 | 24I00072SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE AS PER RA 11239 - PREVENTIVE MAINTENNCE ALONG DAANG MAHARLIKA (LT) K0965+000 - K0966+100, K0974+800 - K0974+907, K0977+198 - K0977+995, K1002+085 - K1002+939, K1002+1013 - K1003+912, LEYTE 5TH | Region VIII | Region VIII | On-Going | ₱246.2M | 89% | High risk65 | —-0.016 |
| 38 | 18IF0061CONSTRUCTION OF CONCRETE ROAD - MILAGRO-CAMBANTOG-CABINGTAN-ALTO PEAK ROAD LEADING TO LAKE JANAGDAN, ALTO PEAK ORMOC VEGETABLE FARM, BRGY. MILAGRO, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱153.1M | 100% | High risk64 | —-0.074 |
| 39 | 17I00056CONSTRUCTION OF EVACUATION CENTER, BARANGAY MACABUG, ORMOC CITY | Region VIII | Region VIII | Completed | ₱33M | 100% | High risk64 | —-0.065 |
| 40 | 25IF0029CONSTRUCTION OF DANHUG FLOOD CONTROL STRUCTURE, BARANGAY DANHUG, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱129.3M | 75% | High risk64 | —-0.023 |
| 41 | 19I00041NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS, ORMOC-BAYBAY-SOUTHERN LEYTE BOUNDARY ROAD, K1067+000-K1067+731, K1067+756-K1070+073, K1070+091-K1071+000, LEYTE 5TH LD | Region VIII | Region VIII | Completed | ₱144.7M | 100% | High risk63 | —-0.070 |
| 42 | 18IG0065ROAD WIDENING-TERTIARY-LA PAZ-JAVIER-BITO ROAD,K0966+000-K0967+841,K0967+856.60-K0969+650,K0969+660.74-K0970+317 | Region VIII | Leyte 5th DEO | Completed | ₱144.8M | 100% | High risk63 | —-0.074 |
| 43 | 24IG0075CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAGBANGANAN RIVER, BARANGAY MAKINHAS, BAYBAY, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱116.4M | 100% | High risk63 | —-0.064 |
| 44 | 22I00056BRIDGE - WIDENING OF PERMANENT BRIDGES, BAGONGBONG BR. (B00569LT) ALONG ORMOC - BAYBAY - SOUTHERN LEYTE BDRY. RD., LEYTE 4TH LD | Region VIII | Region VIII | Completed | ₱120.8M | 100% | High risk62 | —-0.035 |
| 45 | 24IF0028CONSTRUCTION OF MACATOL FLOOD CONTROL, MERIDA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱95.5M | 100% | High risk62 | —-0.029 |
| 46 | 23IF0049CONSTRUCTION OF BAO FLOOD CONTROL (DOWNSTREAM), KANANGA, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱96.3M | 100% | High risk62 | —-0.070 |
| 47 | 23IF0047CONSTRUCTION OF PAGSANGA-AN FLOOD CONTROL, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱104M | 100% | High risk62 | —-0.060 |
| 48 | 23IF0045CONSTRUCTION OF PAGSANGA-AN FLOOD CONTROL, (PACKAGE 1), ORMOC CITY, | Region VIII | Leyte 4th DEO | Completed | ₱106.1M | 100% | High risk62 | —-0.063 |
| 49 | 23IF0085CONSTRUCTION OF MATLANG FLOOD CONTROL (UPSTREAM), ISABEL, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.070 |
| 50 | 23IF0048CONSTRUCTION OF NAGHALIN FLOOD CONTROL, KANANGA, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.069 |