Contractor dossier
36 projects on file, including joint ventures this contractor is part of.
Total projects
36
Total budget
₱1.3B
Average progress
92.0%
Completion rate
69.4%
Below 70%
Average risk score
56.5
Medium risk on average, out of 100
Flagged as unusual
9
25.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 36 | ₱1.3B | 56.5 | 9 | 92.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 20 | ₱629.8M | 45.1 | 0 | 97.8% |
| OTHER | 7 | ₱311.4M | 69.6 | 4 | 89.8% |
| GAA 2025 SSP | 4 | ₱313M | 95.5 | 4 | 60.9% |
| Buildings and Facilities | 3 | ₱29.6M | 43.4 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱30.7M | 91.9 | 1 | 84.1% |
| Flood Control and Drainage | 1 | ₱19.6M | 41.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HB0123CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BRGY. UPPER BONBON TO BRGY. BUGHO, LOBOC, BOHOL | Region VII | Bohol 3rd DEO | On-Going | ₱96M | 20% | High risk96 | Flagged0.043 |
| 25HC0071CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY LAPACAN SUR (INABANGA, BOHOL) TO BRGY PANG | Region VII | Bohol 2nd DEO | On-Going | ₱98.9M | 58% | High risk96 | Flagged0.029 |
| 25HC0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY. BATUAN TO BRGY OVERLAND, BUENAVISTA, BOHO | Region VII | Bohol 2nd DEO | On-Going | ₱98.9M | 70% | High risk96 | Flagged0.027 |
| 25HC0089CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, INABANGA, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱19.2M | 97% | High risk95 | Flagged0.010 |
| 25HB0004OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - THE PRES. CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0233+007 - K0233+350, K0234+375 - K0234+949 | Region VII | Bohol 3rd DEO | On-Going | ₱30.7M | 84% | High risk92 | Flagged0.004 |
| 21HB0182CONCRETING OF BRGY. LUNGSODAAN FMR, BRGY. LUNGSODAAN, CANDIJAY, BOHOL STA.0+622.00-STA.1+110.00 | Region VII | Bohol 3rd DEO | Completed | ₱9.9M | 100% | High risk79 | Flagged0.011 |
| 24HB0134CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BAGUMBAYAN-TIGBAO | Region VII | Bohol 3rd DEO | On-Going | ₱96.4M | 58% | High risk77 | Flagged0.023 |
| 24HC0076CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE LEADING TO UBAY PORT | Region VII | Bohol 2nd DEO | On-Going | ₱77.1M | 89% | High risk74 | Flagged0.010 |
| 25HC0079CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM- KATUPARAN)- ACCESS ROAD LEADING TO UBAY PORT VIA RECLAMATION AREA, UBAY, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱79.6M | 81% | High risk74 | Flagged0.006 |
| 21HB0162LOCAL PROGRAM-CONSTRUCTION/ REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES -LOCAL ROADS - CONCRETING OF ROAD, BAGUMBAYAN-BUGHO, LOBOC, BOHOL STA.0+000 - STA.0+523.99; STA.0+561.42 - STA.1+223.2 | Region VII | Bohol 3rd DEO | Completed | ₱25.7M | 100% | High risk62 | —-0.030 |
| 21HB0078CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), POB. ONDOL, TAYTAY, CAMBANE ROAD LEADING TO CRUZ DAKO, BRGY. POBLACION ONDOL, LOBOC, BOHOL, | Region VII | Bohol 3rd DEO | Completed | ₱17.9M | 100% | High risk62 | —-0.030 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HB0123CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BRGY. UPPER BONBON TO BRGY. BUGHO, LOBOC, BOHOL | Region VII | Bohol 3rd DEO | On-Going | ₱96M | 20% | High risk96 | Flagged0.043 |
| 25HC0071CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY LAPACAN SUR (INABANGA, BOHOL) TO BRGY PANG | Region VII | Bohol 2nd DEO | On-Going | ₱98.9M | 58% | High risk96 | Flagged0.029 |
| 25HC0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY. BATUAN TO BRGY OVERLAND, BUENAVISTA, BOHO | Region VII | Bohol 2nd DEO | On-Going | ₱98.9M | 70% | High risk96 | Flagged0.027 |
| 24HB0134CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BAGUMBAYAN-TIGBAO | Region VII | Bohol 3rd DEO | On-Going | ₱96.4M | 58% | High risk77 | Flagged0.023 |
| 21HB0182CONCRETING OF BRGY. LUNGSODAAN FMR, BRGY. LUNGSODAAN, CANDIJAY, BOHOL STA.0+622.00-STA.1+110.00 | Region VII | Bohol 3rd DEO | Completed | ₱9.9M | 100% | High risk79 | Flagged0.011 |
| 25HC0089CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, INABANGA, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱19.2M | 97% | High risk95 | Flagged0.010 |
| 24HC0076CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE LEADING TO UBAY PORT | Region VII | Bohol 2nd DEO | On-Going | ₱77.1M | 89% | High risk74 | Flagged0.010 |
| 25HC0079CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM- KATUPARAN)- ACCESS ROAD LEADING TO UBAY PORT VIA RECLAMATION AREA, UBAY, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱79.6M | 81% | High risk74 | Flagged0.006 |
| 25HB0004OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - THE PRES. CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0233+007 - K0233+350, K0234+375 - K0234+949 | Region VII | Bohol 3rd DEO | On-Going | ₱30.7M | 84% | High risk92 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25HB0123CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BRGY. UPPER BONBON TO BRGY. BUGHO, LOBOC, BOHOL | Region VII | Bohol 3rd DEO | On-Going | ₱96M | 20% | High risk96 | Flagged0.043 |
| 2 | 25HC0071CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY LAPACAN SUR (INABANGA, BOHOL) TO BRGY PANG | Region VII | Bohol 2nd DEO | On-Going | ₱98.9M | 58% | High risk96 | Flagged0.029 |
| 3 | 25HC0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY. BATUAN TO BRGY OVERLAND, BUENAVISTA, BOHO | Region VII | Bohol 2nd DEO | On-Going | ₱98.9M | 70% | High risk96 | Flagged0.027 |
| 4 | 25HC0089CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, INABANGA, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱19.2M | 97% | High risk95 | Flagged0.010 |
| 5 | 25HB0004OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - THE PRES. CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0233+007 - K0233+350, K0234+375 - K0234+949 | Region VII | Bohol 3rd DEO | On-Going | ₱30.7M | 84% | High risk92 | Flagged0.004 |
| 6 | 21HB0182CONCRETING OF BRGY. LUNGSODAAN FMR, BRGY. LUNGSODAAN, CANDIJAY, BOHOL STA.0+622.00-STA.1+110.00 | Region VII | Bohol 3rd DEO | Completed | ₱9.9M | 100% | High risk79 | Flagged0.011 |
| 7 | 24HB0134CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BAGUMBAYAN-TIGBAO | Region VII | Bohol 3rd DEO | On-Going | ₱96.4M | 58% | High risk77 | Flagged0.023 |
| 8 | 24HC0076CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE LEADING TO UBAY PORT | Region VII | Bohol 2nd DEO | On-Going | ₱77.1M | 89% | High risk74 | Flagged0.010 |
| 9 | 25HC0079CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM- KATUPARAN)- ACCESS ROAD LEADING TO UBAY PORT VIA RECLAMATION AREA, UBAY, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱79.6M | 81% | High risk74 | Flagged0.006 |
| 10 | 21HB0162LOCAL PROGRAM-CONSTRUCTION/ REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES -LOCAL ROADS - CONCRETING OF ROAD, BAGUMBAYAN-BUGHO, LOBOC, BOHOL STA.0+000 - STA.0+523.99; STA.0+561.42 - STA.1+223.2 | Region VII | Bohol 3rd DEO | Completed | ₱25.7M | 100% | High risk62 | —-0.030 |
| 11 | 21HB0078CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), POB. ONDOL, TAYTAY, CAMBANE ROAD LEADING TO CRUZ DAKO, BRGY. POBLACION ONDOL, LOBOC, BOHOL, | Region VII | Bohol 3rd DEO | Completed | ₱17.9M | 100% | High risk62 | —-0.030 |
| 12 | 21HB0027CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT TO ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM), JCT. (DIMIAO-BILAR) OAC-OMJON ROAD IN SUPPORT OF | Region VII | Bohol 3rd DEO | Completed | ₱4.8M | 100% | Medium risk59 | —-0.032 |
| 13 | 24HC0056BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. RUFO HILL TO BARGU, BUENAVISTA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱99M | 100% | Medium risk57 | —-0.080 |
| 14 | 23HC0064ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS: CONSTRUCTION OF DIVERSION ROAD, BRGY POBLACION TO BRGY FATIMA, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱97.8M | 100% | Medium risk57 | —-0.083 |
| 15 | 24HB0104CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF TIGBAO CIRCUMFERENTIAL ROAD, TIGBAO, LOBOC, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱98.9M | 100% | Medium risk57 | —-0.078 |
| 16 | 23HB0010ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS SECONDARY ROADS TAGBILARAN EAST RD (TAGBILARAN-JAGNA) - K0224 + 210.32 - K02 | Region VII | Bohol 3rd DEO | Completed | ₱50.6M | 100% | Medium risk50 | —-0.093 |
| 17 | 24HC0125REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY BONBON, CLARIN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.093 |
| 18 | 23HB0108CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION (CONCRETING) OF ROAD AT BARANGAY POBLACION IBABAO TO BARA | Region VII | Bohol 3rd DEO | Completed | ₱24.7M | 100% | Medium risk46 | —-0.095 |
| 19 | 22HA0012CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - M. CAPAYAS STREET CONNECTING RAMON ENERIO ST. TO CPG EAST AVENUE IN SUPPORT TO THE GIFTS AND HOUSEWARES AND AGRIBUSINESS INDUSTRIES, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱9.5M | 100% | Medium risk45 | —-0.097 |
| 20 | 24HA0035CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - BITAUGAN-BUNGAHAN-TUPAS (ANTEQUERA) ROAD LEADING TO LAKE TUPAS, ANTEQUERA, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱7.8M | 100% | Medium risk45 | —-0.097 |
| 21 | 24HB0151CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, BILAR, BOHOL STA. 0+000.00 - STA. 1+080.00 | Region VII | Bohol 3rd DEO | Completed | ₱34.6M | 100% | Medium risk45 | —-0.087 |
| 22 | 24HB0030ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS TAGBILARAN EAST RD (TAGBILARAN-JAGNA) - K0177 + 583 - K0177 + | Region VII | Bohol 3rd DEO | Completed | ₱29.4M | 100% | Medium risk45 | —-0.093 |
| 23 | 22HB0107CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF JCT. (TER) GUINDULMAN - CA | Region VII | Bohol 3rd DEO | Completed | ₱29.4M | 100% | Medium risk45 | —-0.093 |
| 24 | 22HB0141REHABILITATION/RECONSTRUCTION OF BAYWALK DRAINAGE (BOX CULVERT) AND CANAL LINING FROM EXISTING CATCH BASIN ALONG NATIONAL ROAD GOING TO CALMAYON BRIDGE TO PANGDAN BRIDGE, JAGNA, BOHOL KO196+536.20-KO197+700 | Region VII | Bohol 3rd DEO | Completed | ₱30.1M | 100% | Medium risk44 | —-0.093 |
| 25 | 23HB0007ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM -REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS- TAGBILARAN EAST RD (TAGBILARAN-JAGNA) - K0206 + 000 - K0206 + 321, K | Region VII | Bohol 3rd DEO | Completed | ₱34M | 100% | Medium risk44 | —-0.093 |