Opening the dossier…
Opening the dossier…
Contractor dossier
145 projects on file, including joint ventures this contractor is part of.
Total projects
145
Total budget
₱5.6B
Average progress
89.1%
Completion rate
73.1%
Average risk score
50.6
Medium risk on average, out of 100
Flagged as unusual
13
9.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 142 | ₱5.4B | 50.6 | 13 | 89.1% |
| National Capital Region | 3 | ₱117.7M | 49.8 | 0 | 89.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 87 | ₱3.7B | 50.8 | 5 | 91.3% |
| Buildings and Facilities | 19 | ₱207.2M | 42.6 | 0 | 91.5% |
| Flood Control and Drainage | 17 | ₱802.2M | 52.5 | 3 | 85.3% |
| Bridges | 10 | ₱304.6M | 46.9 | 0 | 88.3% |
| Water Provision and Storage | 4 | ₱37.7M | 30.6 | 0 | 100.0% |
| OTHER | 3 | ₱264.5M | 81.4 | 2 | 67.9% |
| GAA 2025 SSP | 2 | ₱64M | 95.6 | 2 | 48.9% |
| Bridges, Roads | 2 | ₱58.4M | 48.4 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱105.1M | 94.5 | 1 | 2.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IH0068CONSTRUCTION (COMPLETION) OF FLOOD CONTROL STRUCTURES, BARANGAY SAN LORENZO, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱39.5M | 24% | High risk96 | Flagged0.025 |
| 25IH0030CONSTRUCTION/IMPROVEMENT OF OCAD-SIGAD ROAD, BRGY. OCAD, LAVEZARES NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱24.5M | 74% | High risk96 | Flagged0.012 |
| 25IH0039REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-ALLEN-CATARMAN RD- K0737+360 - K0738+523, CATARMAN & BOBON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱105.1M | 3% | High risk95 | Flagged0.025 |
| 24IH0111CONSTRUCTION OF SEAWALL, VICTORIA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 76% | High risk91 | Flagged0.059 |
| 24IH0065CONSTRUCTION OF ROAD FROM LAVEZARES PORT TO NATIONAL HIGHWAY, LAVEZARES, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.4M | 28% | High risk77 | Flagged0.026 |
| 17I00030ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES,TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS)-TERTIARY ROADS,SAN ANTONIO CIRCUM. ROAD,KO020+710-KO022+760;KO022+920-KO023+805, SAN ANTONIO, N. SAMAR | Region VIII | Region VIII | Completed | ₱71.7M | 100% | High risk76 | —-0.034 |
| 24IH0106CONSTRUCTION OF RIVERBANK PROTECTION, CATARMAN-BOBON IRRIGATION PROJECT, BARANGAY TURA, BOBON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 53% | High risk75 | Flagged0.056 |
| 24IH0112REHABILITATION OF FLOOD CONTROL, CARANGIAN CREEK, BARANGAY SOUTH - BARANGAY WEST, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 0% | High risk74 | Flagged0.064 |
| 25IH0043CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, SAN ISIDRO, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱9.9M | 30% | High risk68 | —-0.015 |
| 24IH0031CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SOMOGE, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱139.9M | 97% | High risk66 | —-0.021 |
| 22I00041CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS - ACCESS ROAD LEADING TO PINIPISAKAN FALLS, LAS NAVAS, NORTHERN SAMAR | Region VIII | Region VIII | On-Going | ₱158.7M | 90% | High risk65 | —-0.012 |
| 23I00022CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TRIP) - ACCESS ROAD LEADING TO PINIPISAKAN FALLS, LAS NAVAS, NORTHERN SAMAR | Region VIII | Region VIII | On-Going | ₱152.5M | 94% | High risk65 | —-0.024 |
| 23I00094NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - PANGPANG - PALAPAG - MAPANAS - GAMAY - LAPINIG RD - K0835+554 - K0836+060, K0836+160 - K0836+220, K0836+260 - K0837+750, K0838+000 - K0839+090, K0839+660 - K0839+800, K0839+965 - K0840+052.50, NORTHE | Region VIII | Region VIII | On-Going | ₱193M | 92% | High risk64 | —-0.015 |
| 25IH0092CONSTRUCTION OF CAG-ABACA - CULARIMA - GENERAL MALVAR ROAD, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱98M | 0% | High risk63 | Flagged0.007 |
| 17IJ0104IMPROVEMENT/WIDENING OF CALBAYOG DIVERSION ROAD K0729+400-K0732+400, SAMAR 1ST LD | Region VIII | Samar 1st DEO | Completed | ₱100.4M | 100% | High risk62 | —-0.047 |
| 25IH0081CONSTRUCTION OF SAN ISIDRO-LOPE DE VEGA ROAD, SAN ISIDRO AND LOPE DE VEGA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱73.1M | 18% | High risk61 | —-0.002 |
| 25IH0065REHABILITATION AND IMPROVEMENT OF CARANGIAN CREEK FLOOD CONTROL, SAN JOSE NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱39.1M | 0% | High risk61 | Flagged0.003 |
| 19IJ0065001: ENSURE SAFE AND RELIABLE ROAD SYSTEM - NETWORK DEVELOPMENT, CONSTRUCTION OF BY - PASS AND DIVERSION ROADS, CALBAYOG CITY, COASTAL ROAD, PACKAGE 1A, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱93.7M | 100% | High risk60 | —-0.083 |
| 19IJ0066001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT, CONSTRUCTION OF BY - PASS AND DIVERSION ROADS, CALBAYOG CITY, COASTAL ROAD, PACKAGE B, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱93.6M | 100% | High risk60 | —-0.084 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IH0112REHABILITATION OF FLOOD CONTROL, CARANGIAN CREEK, BARANGAY SOUTH - BARANGAY WEST, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 0% | High risk74 | Flagged0.064 |
| 24IH0111CONSTRUCTION OF SEAWALL, VICTORIA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 76% | High risk91 | Flagged0.059 |
| 24IH0106CONSTRUCTION OF RIVERBANK PROTECTION, CATARMAN-BOBON IRRIGATION PROJECT, BARANGAY TURA, BOBON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 53% | High risk75 | Flagged0.056 |
| 24IH0065CONSTRUCTION OF ROAD FROM LAVEZARES PORT TO NATIONAL HIGHWAY, LAVEZARES, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.4M | 28% | High risk77 | Flagged0.026 |
| 25IH0068CONSTRUCTION (COMPLETION) OF FLOOD CONTROL STRUCTURES, BARANGAY SAN LORENZO, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱39.5M | 24% | High risk96 | Flagged0.025 |
| 25IH0039REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-ALLEN-CATARMAN RD- K0737+360 - K0738+523, CATARMAN & BOBON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱105.1M | 3% | High risk95 | Flagged0.025 |
| 23IH0133CONCRETING OF BRGY. SAN ISIDRO TO BRGY. SAN JUAN FMR, BRGY. SAN ISIDRO AND BRGY. SAN JUAN, LAVEZARES, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱29.8M | 74% | Medium risk52 | Flagged0.013 |
| 25IH0030CONSTRUCTION/IMPROVEMENT OF OCAD-SIGAD ROAD, BRGY. OCAD, LAVEZARES NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱24.5M | 74% | High risk96 | Flagged0.012 |
| 24IH0110CONCRETING OF BRGY. SAN MIGUEL TO MAWO RIVER FMR, VICTORIA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱18.9M | 46% | Medium risk52 | Flagged0.010 |
| 25IH0092CONSTRUCTION OF CAG-ABACA - CULARIMA - GENERAL MALVAR ROAD, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱98M | 0% | High risk63 | Flagged0.007 |
| 23IH0113CONCRETING OF BRGY. LIGAYA TO BRGY. BUENAVISTA FMR, BRGY. LIGAYA AND BRGY. BUENAVISTA, ROSARIO, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱11.9M | 96% | Medium risk46 | Flagged0.005 |
| 25IH0065REHABILITATION AND IMPROVEMENT OF CARANGIAN CREEK FLOOD CONTROL, SAN JOSE NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱39.1M | 0% | High risk61 | Flagged0.003 |
| 25IH0049CONCRETING OF BRGY. POLANGI - PATICUA FMR PHASE IV, BRGY. POLANGI AND BRGY. PATICUA, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱24.8M | 82% | Medium risk51 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25IH0068CONSTRUCTION (COMPLETION) OF FLOOD CONTROL STRUCTURES, BARANGAY SAN LORENZO, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱39.5M | 24% | High risk96 | Flagged0.025 |
| 2 | 25IH0030CONSTRUCTION/IMPROVEMENT OF OCAD-SIGAD ROAD, BRGY. OCAD, LAVEZARES NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱24.5M | 74% | High risk96 | Flagged0.012 |
| 3 | 25IH0039REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-ALLEN-CATARMAN RD- K0737+360 - K0738+523, CATARMAN & BOBON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱105.1M | 3% | High risk95 | Flagged0.025 |
| 4 | 24IH0111CONSTRUCTION OF SEAWALL, VICTORIA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 76% | High risk91 | Flagged0.059 |
| 5 | 24IH0065CONSTRUCTION OF ROAD FROM LAVEZARES PORT TO NATIONAL HIGHWAY, LAVEZARES, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.4M | 28% | High risk77 | Flagged0.026 |
| 6 | 17I00030ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES,TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS)-TERTIARY ROADS,SAN ANTONIO CIRCUM. ROAD,KO020+710-KO022+760;KO022+920-KO023+805, SAN ANTONIO, N. SAMAR | Region VIII | Region VIII | Completed | ₱71.7M | 100% | High risk76 | —-0.034 |
| 7 | 24IH0106CONSTRUCTION OF RIVERBANK PROTECTION, CATARMAN-BOBON IRRIGATION PROJECT, BARANGAY TURA, BOBON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 53% | High risk75 | Flagged0.056 |
| 8 | 24IH0112REHABILITATION OF FLOOD CONTROL, CARANGIAN CREEK, BARANGAY SOUTH - BARANGAY WEST, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.5M | 0% | High risk74 | Flagged0.064 |
| 9 | 25IH0043CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, SAN ISIDRO, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱9.9M | 30% | High risk68 | —-0.015 |
| 10 | 24IH0031CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SOMOGE, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱139.9M | 97% | High risk66 | —-0.021 |
| 11 | 22I00041CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS - ACCESS ROAD LEADING TO PINIPISAKAN FALLS, LAS NAVAS, NORTHERN SAMAR | Region VIII | Region VIII | On-Going | ₱158.7M | 90% | High risk65 | —-0.012 |
| 12 | 23I00022CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TRIP) - ACCESS ROAD LEADING TO PINIPISAKAN FALLS, LAS NAVAS, NORTHERN SAMAR | Region VIII | Region VIII | On-Going | ₱152.5M | 94% | High risk65 | —-0.024 |
| 13 | 23I00094NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - PANGPANG - PALAPAG - MAPANAS - GAMAY - LAPINIG RD - K0835+554 - K0836+060, K0836+160 - K0836+220, K0836+260 - K0837+750, K0838+000 - K0839+090, K0839+660 - K0839+800, K0839+965 - K0840+052.50, NORTHE | Region VIII | Region VIII | On-Going | ₱193M | 92% | High risk64 | —-0.015 |
| 14 | 25IH0092CONSTRUCTION OF CAG-ABACA - CULARIMA - GENERAL MALVAR ROAD, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱98M | 0% | High risk63 | Flagged0.007 |
| 15 | 17IJ0104IMPROVEMENT/WIDENING OF CALBAYOG DIVERSION ROAD K0729+400-K0732+400, SAMAR 1ST LD | Region VIII | Samar 1st DEO | Completed | ₱100.4M | 100% | High risk62 | —-0.047 |
| 16 | 25IH0081CONSTRUCTION OF SAN ISIDRO-LOPE DE VEGA ROAD, SAN ISIDRO AND LOPE DE VEGA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱73.1M | 18% | High risk61 | —-0.002 |
| 17 | 25IH0065REHABILITATION AND IMPROVEMENT OF CARANGIAN CREEK FLOOD CONTROL, SAN JOSE NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱39.1M | 0% | High risk61 | Flagged0.003 |
| 18 | 19IJ0065001: ENSURE SAFE AND RELIABLE ROAD SYSTEM - NETWORK DEVELOPMENT, CONSTRUCTION OF BY - PASS AND DIVERSION ROADS, CALBAYOG CITY, COASTAL ROAD, PACKAGE 1A, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱93.7M | 100% | High risk60 | —-0.083 |
| 19 | 19IJ0066001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT, CONSTRUCTION OF BY - PASS AND DIVERSION ROADS, CALBAYOG CITY, COASTAL ROAD, PACKAGE B, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱93.6M | 100% | High risk60 | —-0.084 |
| 20 | 19IJ0067001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT, CONSTRUCTION OF BY- PASS AND DIVERSION ROADS, CALBAYOG CITY, COASTAL ROAD, PACKAGE C, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱94.5M | 100% | Medium risk60 | —-0.083 |
| 21 | 18I00052REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS, ALLEN-CATARMAN ROAD, KO714+000 -KO714+687; KO714+699.50 - KO714+900; KO715+300 - KO717+000; KO717+140 - KO717+458.70; KO719+000 - KO721+000; KO725+500 - KO727+000, NORTHERN SAMAR 1ST LD | Region VIII | Region VIII | Completed | ₱93.3M | 100% | Medium risk60 | —-0.078 |
| 22 | 24IH0066CONSTRUCTION OF SAN ISIDRO-LOPE DE VEGA ROAD, SAN ISIDRO AND LOPE DE VEGA NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96.4M | 54% | Medium risk60 | —-0.033 |
| 23 | 22IH0103CONSTRUCTION OF SAN ISIDRO-LOPE DE VEGA ROAD, SAN ISIDRO, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱96M | 81% | Medium risk60 | —-0.024 |
| 24 | 21IJ0035CONSRUCTION OF BY-PASS AND DIVERSION ROADS, CALBAYOG CITY COASTAL ROAD, PACKAGE 3A, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱95.7M | 100% | Medium risk60 | —-0.084 |
| 25 | 21IJ0036CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CALBAYOG COASTAL ROAD, PACKAGE 4A, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱95.7M | 100% | Medium risk60 | —-0.084 |