Opening the dossier…
Opening the dossier…
Contractor dossier
3 projects on file, including joint ventures this contractor is part of.
Total projects
3
Total budget
₱25.7M
Average progress
70.1%
Completion rate
66.7%
Below 70%
Average risk score
51.4
Medium risk on average, out of 100
Flagged as unusual
1
33.3% of their projects
Risk mix
Exhibit A
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 2 | ₱15.8M | 41.7 | 0 | 100.0% |
| Buildings and Facilities | 1 | ₱9.9M | 70.9 | 1 | 10.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25GD0042CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MAAYON, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱9.9M | 10% | High risk71 | Flagged0.006 |
| 2 | 24BF0094CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, PUROK RANG-AYAN, BARANGA | Region II | Isabela 2nd DEO | Completed | ₱5.9M | 100% | Medium risk43 | —-0.086 |
| 3 | 18GI0085CONCRETING OF BRGY. GINES - INAGDANGAN SUR - INAGDANGAN NORTE FMR, BRGYS. GINES, INAGDANGAN SUR AND INAGDANGAN NORTE, ZARRAGA, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱9.9M | 100% | Medium risk41 | —-0.036 |