Contractor dossier
19 projects on file, including joint ventures this contractor is part of.
Total projects
19
Total budget
₱2.3B
Average progress
93.7%
Completion rate
57.9%
Below 70%
Average risk score
63.8
High risk on average, out of 100
Flagged as unusual
4
21.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 19 | ₱2.3B | 63.8 | 4 | 93.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 10 | ₱1.2B | 57.2 | 0 | 94.1% |
| OTHER | 3 | ₱415.7M | 76.0 | 2 | 94.4% |
| Buildings and Facilities | 3 | ₱278.3M | 52.3 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱189.5M | 95.4 | 2 | 78.3% |
| Bridges | 1 | ₱140.7M | 64.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25K00328CONSTRUCTION OF JCT. SAYRE HIGHWAY TO BARANGAY MIARAY - BARANGAY DOLOROSA, DANGCAGAN - BARANGAY BALOCBOCAN ROAD (PACKAGE 4), KITAOTAO, BUKIDNON | Region X | Region X | On-Going | ₱94.8M | 75% | High risk95 | Flagged0.017 |
| 25K00042CONSTRUCTION OF JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY-COTABATO BDRY) TO BARANGAY MIARAY-BARANGAY DOLOROSA, DANGCAGAN-BARANGAY BALOCBOCAN ROAD, PACKAGE 3, BUKIDNON | Region X | Region X | On-Going | ₱94.8M | 82% | High risk95 | Flagged0.014 |
| 23K00240CLUSTER RO-1 -CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON | Region X | Region X | Completed | ₱288.7M | 100% | High risk78 | Flagged0.010 |
| 24K00405CONSTRUCTION OF JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY RD.- COTABATO BDRY) TO JCT SAYRE HIGHWAY LOURDES-MC ARTHUR ROAD-BRGY. KITAIHON ROAD, DANGCAGAN, BUKIDNON | Region X | Region X | On-Going | ₱74.9M | 100% | High risk75 | —-0.006 |
| 24KB0112CONSTRUCTION OF JCT SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY-COTABATO BDRY) TO BRGY. POCOPOCO TO BRGY KITINGTING TO BRGY LAGANDANG TO BRGY ALUDAS TO SITIO KILAOLAO TO BRGY. MIGCAWAYAN ROAD (POCOPOCO & KITINGTING SECTIONS), DAMULOG, BUKIDNON (POCOPOCO- AND | Region X | Bukidnon 2nd DEO | On-Going | ₱52.1M | 83% | High risk74 | Flagged0.005 |
| 22K00314CONSTRUCTION OF BRIDGE ALONG SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY RD-COTABATO BDRY) - BRGY. MACAPARI, DAMULOG -SITIO TALASAN, BRGY. PINAMANGGUHAN ROAD, KADINGILAN, BUKIDNON (PACKAGE III) | Region X | Region X | Completed | ₱140.7M | 100% | High risk64 | —-0.030 |
| 22K00340CLUSTER RO-O3 CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON | Region X | Region X | Completed | ₱243.9M | 100% | High risk63 | —-0.047 |
| 23K00279CLUSTER RO-6 -CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON 1. CONSTRUCTION OF JCT. SAYRE HIGHWAY TO BRGY. MIARAY-BRGY. DOLOROSA, DANGCAGAN-BRGY. BALOCBOCAN ROAD, KITAOTAO, BUKIDNON (PACKAGE I) 2. CONSTRUCTION OF JCT. DON CARLOS-KADINGILAN ROAD TO BR | Region X | Region X | Completed | ₱192.5M | 100% | High risk63 | —-0.058 |
| 24K00095CONST. OF JCT.DON CARLOS-KADINGILAN ROAD TO BRGY. CALAO-CALAO-BRGY.BERSHIBA-BRGY.BOBONG-BRGY.KAUYONAN-BRGY. STO.ROSARIO-BRGY. OSMEÑA RD, DANGCAGAN, BUKIDNON, PACKAGE 2 | Region X | Region X | On-Going | ₱142.1M | 100% | High risk63 | —-0.033 |
| 24K00048CONST. OF JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY-COTABATO BDRY)TO BRGY. MIARAY-BRGY. DOLOROSA, DANGCAGAN-BRGY. BALOCBOCAN ROAD, KITAOTAO, BUKIDNON (PACKAGE 2) | Region X | Region X | Completed | ₱142.1M | 100% | High risk63 | —-0.069 |
| 21K00309CLUSTER RO-O4 CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON | Region X | Region X | Completed | ₱175.7M | 100% | High risk63 | —-0.062 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25K00328CONSTRUCTION OF JCT. SAYRE HIGHWAY TO BARANGAY MIARAY - BARANGAY DOLOROSA, DANGCAGAN - BARANGAY BALOCBOCAN ROAD (PACKAGE 4), KITAOTAO, BUKIDNON | Region X | Region X | On-Going | ₱94.8M | 75% | High risk95 | Flagged0.017 |
| 25K00042CONSTRUCTION OF JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY-COTABATO BDRY) TO BARANGAY MIARAY-BARANGAY DOLOROSA, DANGCAGAN-BARANGAY BALOCBOCAN ROAD, PACKAGE 3, BUKIDNON | Region X | Region X | On-Going | ₱94.8M | 82% | High risk95 | Flagged0.014 |
| 23K00240CLUSTER RO-1 -CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON | Region X | Region X | Completed | ₱288.7M | 100% | High risk78 | Flagged0.010 |
| 24KB0112CONSTRUCTION OF JCT SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY-COTABATO BDRY) TO BRGY. POCOPOCO TO BRGY KITINGTING TO BRGY LAGANDANG TO BRGY ALUDAS TO SITIO KILAOLAO TO BRGY. MIGCAWAYAN ROAD (POCOPOCO & KITINGTING SECTIONS), DAMULOG, BUKIDNON (POCOPOCO- AND | Region X | Bukidnon 2nd DEO | On-Going | ₱52.1M | 83% | High risk74 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25K00328CONSTRUCTION OF JCT. SAYRE HIGHWAY TO BARANGAY MIARAY - BARANGAY DOLOROSA, DANGCAGAN - BARANGAY BALOCBOCAN ROAD (PACKAGE 4), KITAOTAO, BUKIDNON | Region X | Region X | On-Going | ₱94.8M | 75% | High risk95 | Flagged0.017 |
| 2 | 25K00042CONSTRUCTION OF JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY-COTABATO BDRY) TO BARANGAY MIARAY-BARANGAY DOLOROSA, DANGCAGAN-BARANGAY BALOCBOCAN ROAD, PACKAGE 3, BUKIDNON | Region X | Region X | On-Going | ₱94.8M | 82% | High risk95 | Flagged0.014 |
| 3 | 23K00240CLUSTER RO-1 -CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON | Region X | Region X | Completed | ₱288.7M | 100% | High risk78 | Flagged0.010 |
| 4 | 24K00405CONSTRUCTION OF JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY RD.- COTABATO BDRY) TO JCT SAYRE HIGHWAY LOURDES-MC ARTHUR ROAD-BRGY. KITAIHON ROAD, DANGCAGAN, BUKIDNON | Region X | Region X | On-Going | ₱74.9M | 100% | High risk75 | —-0.006 |
| 5 | 24KB0112CONSTRUCTION OF JCT SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY-COTABATO BDRY) TO BRGY. POCOPOCO TO BRGY KITINGTING TO BRGY LAGANDANG TO BRGY ALUDAS TO SITIO KILAOLAO TO BRGY. MIGCAWAYAN ROAD (POCOPOCO & KITINGTING SECTIONS), DAMULOG, BUKIDNON (POCOPOCO- AND | Region X | Bukidnon 2nd DEO | On-Going | ₱52.1M | 83% | High risk74 | Flagged0.005 |
| 6 | 22K00314CONSTRUCTION OF BRIDGE ALONG SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY RD-COTABATO BDRY) - BRGY. MACAPARI, DAMULOG -SITIO TALASAN, BRGY. PINAMANGGUHAN ROAD, KADINGILAN, BUKIDNON (PACKAGE III) | Region X | Region X | Completed | ₱140.7M | 100% | High risk64 | —-0.030 |
| 7 | 22K00340CLUSTER RO-O3 CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON | Region X | Region X | Completed | ₱243.9M | 100% | High risk63 | —-0.047 |
| 8 | 23K00279CLUSTER RO-6 -CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON 1. CONSTRUCTION OF JCT. SAYRE HIGHWAY TO BRGY. MIARAY-BRGY. DOLOROSA, DANGCAGAN-BRGY. BALOCBOCAN ROAD, KITAOTAO, BUKIDNON (PACKAGE I) 2. CONSTRUCTION OF JCT. DON CARLOS-KADINGILAN ROAD TO BR | Region X | Region X | Completed | ₱192.5M | 100% | High risk63 | —-0.058 |
| 9 | 24K00095CONST. OF JCT.DON CARLOS-KADINGILAN ROAD TO BRGY. CALAO-CALAO-BRGY.BERSHIBA-BRGY.BOBONG-BRGY.KAUYONAN-BRGY. STO.ROSARIO-BRGY. OSMEÑA RD, DANGCAGAN, BUKIDNON, PACKAGE 2 | Region X | Region X | On-Going | ₱142.1M | 100% | High risk63 | —-0.033 |
| 10 | 24K00048CONST. OF JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY-COTABATO BDRY)TO BRGY. MIARAY-BRGY. DOLOROSA, DANGCAGAN-BRGY. BALOCBOCAN ROAD, KITAOTAO, BUKIDNON (PACKAGE 2) | Region X | Region X | Completed | ₱142.1M | 100% | High risk63 | —-0.069 |
| 11 | 21K00309CLUSTER RO-O4 CONSTRUCTION OF VARIOUS ROAD PROJECTS IN BUKIDNON | Region X | Region X | Completed | ₱175.7M | 100% | High risk63 | —-0.062 |
| 12 | 25K00308CONSTRUCTION OF JCT. BUKIDNON-DAVAO CITY RD TO JCT. KIBURIAO-KITAOTAO RD (SAN JOSE-MINSALIRAC-SAN ISIDRO-MANUTO-MINSAMONGAN-KIBURIAO SECTION), PACKAGE 4, BUKIDNON | Region X | Region X | On-Going | ₱94.8M | 56% | Medium risk58 | —-0.037 |
| 13 | 21K00308CONSTRUCTION OF MULTI-PURPOSE BUILDING (AQUATIC CENTER), BRGY. LAGUITAS, MALAYBALAY BUKIDNON | Region X | Region X | Completed | ₱144M | 100% | Medium risk58 | —-0.066 |
| 14 | 24K00026CONST. OF JCT. BUKIDNON-DAVAO CITY ROAD TO JCT. KIBURIAO-KITAOTAO ROAD(SAN JOSE-MINSALIRAC-SAN ISIDRO-MANUTO-MINSAMONGAN-KIBURIAO SECTION), QUEZON, BUKIDNON, PACKAGE 2 | Region X | Region X | Completed | ₱104.2M | 100% | Medium risk57 | —-0.078 |
| 15 | 22K00339CLUSTER RO-O4 CONSTRUCTION OF BUILDING PROJECTS IN BUKIDNON | Region X | Region X | Completed | ₱124.4M | 100% | Medium risk56 | —-0.063 |
| 16 | 24K00356CONSTRUCTION OF ROAD, JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY ROAD-COTABATO BOUNDARY) BARANGAY PAGOMPONG-SITIO BULUAN-SITIO KINAPAT-SITIO KIRAON-SITIO KILAOLAO-SITIO MIGCAWAYAN, BUKIDNON (PACKAGE 1) | Region X | Region X | On-Going | ₱73.9M | 85% | Medium risk52 | —-0.044 |
| 17 | 24KB0196CONSTRUCTION OF JCT. SAYRE HIGHWAY (JCT.BUKIDNON-DAVAO CITY - COTABATO BDRY), BRGY. SAMPAGAR-PUROK 6 (SITIO LAGASAN), BRGY. SAMPAGAR ROAD, DAMULOG, BUKIDNON (PACKAGE 1), SAMPAGAR, DAMULOG, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱34.3M | 100% | Medium risk46 | —-0.092 |
| 18 | 24K00412CONSTRUCTION OF JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY RD.- COTABATO BDRY) TO PUROK 2, POBLACION TO PUROK 1 POBLACION, BRGY. SAGBAYAN ROAD, DANGCAGAN, BUKIDNON | Region X | Region X | On-Going | ₱38.9M | 100% | Medium risk46 | —-0.056 |
| 19 | 21KB0191CONSTRUCTION OF MULTI-PURPOSE FACILITY (GYMNASIUM), BRGY PANADTALAN, MARAMAG, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱9.9M | 100% | Medium risk43 | —-0.089 |