45 projects on file, including joint ventures this contractor is part of.
Total projects
45
Total budget
₱732.7M
Average progress
100.0%
Completion rate
100.0%
Average risk score
39.7
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 45 | ₱732.7M | 39.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 29 | ₱519.8M | 37.7 | 0 | 100.0% |
| Flood Control and Drainage | 11 | ₱186.3M | 47.0 | 0 | 100.0% |
| Roads | 4 | ₱24.7M | 38.7 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱1.9M | 24.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 17AI0421CONSTN OF TWO STRY SIX CL SB SALUD-SAN EUGENIO NATIONAL HIGH SCHOOL, NATIVIDAD, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱12.6M | 100% | Medium risk38 | —-0.020 |
| 27 | 17AI0339CONSTN OF TWO STRY FOUR CL SB (WITH MICROPILE) AT TALINGKAPOR E/S, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱11.3M | 100% | Medium risk38 | —-0.020 |
| 28 | 17AI0392CONSTN OF TWO STRY FOUR CL SB SALUD E/S, NATIVIDAD, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.7M | 100% | Medium risk38 | —-0.020 |
| 29 | 17AI0553CONSTN OF TWO STRY FOUR CL SB AT TRENCHERA E/S, TAYUG, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.6M | 100% | Medium risk38 | —-0.020 |
| 30 | 17AI0628CONSTN OF TWO STRY FOUR CL SB AT CALLITANG E/S, STA. MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.8M | 100% | Medium risk38 | —-0.019 |
| 31 | 17AI0394CONSTN OF TWO STRY FOUR CL SB (W/ MICROPILE) SAMON E/S, STA. MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱11.4M | 100% | Medium risk38 | —-0.020 |
| 32 | 17AI0642CONSTN OF TWO STRY EIGHT CL SB AT STA. MARIA E/S, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱18.2M | 100% | Medium risk38 | —-0.017 |
| 33 | 17AI0625CONSTN OF TWO STRY FOUR CL SB AT PASTORAN E/S, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.5M | 100% | Medium risk38 | —-0.020 |
| 34 | 17AI0574CONSTN OF TWO STRY FOUR CL SB CABITNONGAN E/S, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.5M | 100% | Medium risk38 | —-0.020 |
| 35 | 17AI0543CONSTN OF TWO STRY FOUR CLSB AT CACABUGAOAN NHS, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.6M | 100% | Medium risk38 | —-0.020 |
| 36 | 17AI0382CONSTN OF TWO STRY EIGHT CL SB (W/ MICROPILE) AT SAN QUINTIN C/S, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱22M | 100% | Medium risk37 | —-0.011 |
| 37 | 17AI0629CONSTN OF TWO STRY FOUR CL SB AT SAN NARCISO SUR E/S, NATIVIDAD, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.6M | 100% | Medium risk37 | —-0.020 |
| 38 | 17AI0599CONSTN OF TWO STRY FOUR CL SB C. LICHAUCO E/S, TAYUG, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.6M | 100% | Medium risk37 | —-0.020 |
| 39 | 17AI0502CONSTN OF TWO STRY FOUR CL SB AT SAN MACARIO SUR E/S, NATIVIDAD, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.6M | 100% | Medium risk37 | —-0.018 |
| 40 | 17AI0639CONSTN OF THREE STRY SIX CL SB (W/ MICROPILE) AT LAGASIT NHS, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱17.6M | 100% | Medium risk37 | —-0.016 |
| 41 | 17AI0343CONSTN OF TWO STRY FOUR CL SB LAGASIT E/S, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.6M | 100% | Medium risk37 | —-0.020 |
| 42 | 17AI0340CONSTN OF TWO STRY FOUR CL SB AT SAN PEDRO E/S, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.5M | 100% | Medium risk37 | —-0.020 |
| 43 | 21AI0116CONSTRUCTION/IMPROVEMENT OF WATER SYSTEM, BARANGAY BATCHELOR EAST, NATIVIDAD, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk24 | —-0.046 |
| 44 | 18AI0173CONCRETING OF ROADS AT SILAG-LUNA, NATIVIDAD, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.088 |
| 45 | 17AI0589CONSTN OF ONE STRY TWO CL SB W/ TOILET ATTACHED CABITNONGAN E/S AT SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱2.7M | 100% | Low risk11 | —-0.019 |