Contractor dossier
75 projects on file, including joint ventures this contractor is part of.
Total projects
75
Total budget
₱3.7B
Average progress
93.4%
Completion rate
82.7%
Average risk score
52.1
Medium risk on average, out of 100
Flagged as unusual
3
4.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 75 | ₱3.7B | 52.1 | 3 | 93.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 39 | ₱1.9B | 50.8 | 0 | 94.9% |
| Flood Control and Drainage | 23 | ₱1.1B | 49.8 | 0 | 93.7% |
| Bridges | 7 | ₱323.5M | 48.5 | 0 | 100.0% |
| Buildings and Facilities | 3 | ₱60.5M | 52.3 | 0 | 100.0% |
| GAA 2025 OO-1 | 2 | ₱161.6M | 95.3 | 2 | 52.7% |
| GAA 2025 OO-2 | 1 | ₱114.4M | 93.7 | 1 | 39.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GI0041WIDENING OF BRIDGE - TALAUGIS BR. (B00475PN) ALONG ILOILO CITY-LEGANES-DUMANGAS COASTAL RD | Region VI | Iloilo 4th DEO | On-Going | ₱75.2M | 66% | High risk95 | Flagged0.011 |
| 25G00080ROXAS CITY CIRCUMFERENTIAL ROAD, C2 SECTION, CAPIZ | Region VI | Region VI | On-Going | ₱86.4M | 39% | High risk95 | Flagged0.019 |
| 25G00058CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, PACKAGE 7, BAROTAC NUEVO, ILOILO | Region VI | Region VI | On-Going | ₱114.4M | 39% | High risk94 | Flagged0.012 |
| 24GJ0059CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - ILOILO CITY FLOOD CONTROL PROJECT SECTION 9 | Region VI | Iloilo City DEO | On-Going | ₱39.5M | 100% | High risk70 | —-0.010 |
| 25G00061CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER IN SAN ENRIQUE, ILOILO (PACKAGE 6) | Region VI | Region VI | On-Going | ₱144.3M | 53% | High risk67 | —-0.009 |
| 17GG0003IMPROVEMENT/WIDENING OF NATIONAL ROADS - WIDENING OF BANGA POLOT-AN - POTOTAN POBLACION ROAD INCLUDING DRAINAGE, BRGY. DAPITAN SECTION, POTOTAN, ILOILO, K0280+000 - K0281+427 (NET LENGTH = 1.374 KM.) | Region VI | Iloilo 2nd DEO | Completed | ₱34.2M | 100% | High risk67 | —-0.055 |
| 17GG0036IMPROVEMENT/WIDENING OF NATIONAL ROADS, ROAD WIDENING INCLUDING DRAINAGE & RROW ACQUISITION OF POTOTAN-TINA-LAMBUNAO ROAD, BRGYS. BAGACAY & NASLO SECTION, POTOTAN, ILOILO, K0031+805 - K0033+250, | Region VI | Iloilo 2nd DEO | Completed | ₱29.7M | 100% | High risk67 | —-0.056 |
| 17GG0027REHAB/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4, CONCRETE RECONSTRUCTION OF POTOTAN-TINA-LAMBUNAO ROAD, K0032+060 - K0032+237 ; K0032+381-K0032+426 ; K0 | Region VI | Iloilo 2nd DEO | Completed | ₱34.5M | 100% | High risk67 | —-0.056 |
| 24GJ0013CONSTRUCTION OF JALANDONI ROAD LEADING TO NELLY GARDEN, JARO CATHEDRAL AND ESPLANADE, ILOILO CITY | Region VI | Iloilo City DEO | On-Going | ₱43.4M | 97% | High risk67 | —-0.021 |
| 24G00010KALIBO CIRCUMFERENTIAL ROAD (NALOOK-LAMBINGAN SECTION), AKLAN | Region VI | Region VI | On-Going | ₱156.9M | 94% | High risk64 | —-0.026 |
| 19GJ0209CONSTRUCTION OF DRAINAGE STRUCTURE - CONSTRUCTION/REHABILITATION OF DRAINAGE SYSTEM WITHIN THE VICINITY OF MANDURRIAO DISTRICT, ILOILO CITY | Region VI | Iloilo City DEO | Completed | ₱96.5M | 100% | High risk63 | —-0.039 |
| 22GH0034CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BAROTAC VIEJO RIVER, (STA. 4+337.60 - STA. 3+528.6), BRGY. POBLACION ILAWOD, BAROTAC VIEJO, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱96.5M | 100% | High risk63 | —-0.052 |
| 17GG0209COMPLETION OF UPGRADING FROM LEVEL I TO LEVEL II AND INCREASE IN BED CAPACITY OF ILOILO PROVINCIAL HOSPITAL, POTOTAN ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱26.5M | 100% | High risk63 | —-0.012 |
| 22G00136REHABILITATION OF CONCIENCIA - TINIGBAN PROVINCIAL ROAD (PORTION), PANITAN, CAPIZ | Region VI | Region VI | Completed | ₱120.6M | 100% | High risk60 | —-0.062 |
| 21G00126ROXAS CITY CIRCUMFERENTIAL ROAD, C2, CAPIZ | Region VI | Region VI | On-Going | ₱120.5M | 56% | High risk60 | —-0.007 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25G00080ROXAS CITY CIRCUMFERENTIAL ROAD, C2 SECTION, CAPIZ | Region VI | Region VI | On-Going | ₱86.4M | 39% | High risk95 | Flagged0.019 |
| 25G00058CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, PACKAGE 7, BAROTAC NUEVO, ILOILO | Region VI | Region VI | On-Going | ₱114.4M | 39% | High risk94 | Flagged0.012 |
| 25GI0041WIDENING OF BRIDGE - TALAUGIS BR. (B00475PN) ALONG ILOILO CITY-LEGANES-DUMANGAS COASTAL RD | Region VI | Iloilo 4th DEO | On-Going | ₱75.2M | 66% | High risk95 | Flagged0.011 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25GI0041WIDENING OF BRIDGE - TALAUGIS BR. (B00475PN) ALONG ILOILO CITY-LEGANES-DUMANGAS COASTAL RD | Region VI | Iloilo 4th DEO | On-Going | ₱75.2M | 66% | High risk95 | Flagged0.011 |
| 2 | 25G00080ROXAS CITY CIRCUMFERENTIAL ROAD, C2 SECTION, CAPIZ | Region VI | Region VI | On-Going | ₱86.4M | 39% | High risk95 | Flagged0.019 |
| 3 | 25G00058CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, PACKAGE 7, BAROTAC NUEVO, ILOILO | Region VI | Region VI | On-Going | ₱114.4M | 39% | High risk94 | Flagged0.012 |
| 4 | 24GJ0059CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - ILOILO CITY FLOOD CONTROL PROJECT SECTION 9 | Region VI | Iloilo City DEO | On-Going | ₱39.5M | 100% | High risk70 | —-0.010 |
| 5 | 25G00061CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER IN SAN ENRIQUE, ILOILO (PACKAGE 6) | Region VI | Region VI | On-Going | ₱144.3M | 53% | High risk67 | —-0.009 |
| 6 | 17GG0003IMPROVEMENT/WIDENING OF NATIONAL ROADS - WIDENING OF BANGA POLOT-AN - POTOTAN POBLACION ROAD INCLUDING DRAINAGE, BRGY. DAPITAN SECTION, POTOTAN, ILOILO, K0280+000 - K0281+427 (NET LENGTH = 1.374 KM.) | Region VI | Iloilo 2nd DEO | Completed | ₱34.2M | 100% | High risk67 | —-0.055 |
| 7 | 17GG0036IMPROVEMENT/WIDENING OF NATIONAL ROADS, ROAD WIDENING INCLUDING DRAINAGE & RROW ACQUISITION OF POTOTAN-TINA-LAMBUNAO ROAD, BRGYS. BAGACAY & NASLO SECTION, POTOTAN, ILOILO, K0031+805 - K0033+250, | Region VI | Iloilo 2nd DEO | Completed | ₱29.7M | 100% | High risk67 | —-0.056 |
| 8 | 17GG0027REHAB/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4, CONCRETE RECONSTRUCTION OF POTOTAN-TINA-LAMBUNAO ROAD, K0032+060 - K0032+237 ; K0032+381-K0032+426 ; K0 | Region VI | Iloilo 2nd DEO | Completed | ₱34.5M | 100% | High risk67 | —-0.056 |
| 9 | 24GJ0013CONSTRUCTION OF JALANDONI ROAD LEADING TO NELLY GARDEN, JARO CATHEDRAL AND ESPLANADE, ILOILO CITY | Region VI | Iloilo City DEO | On-Going | ₱43.4M | 97% | High risk67 | —-0.021 |
| 10 | 24G00010KALIBO CIRCUMFERENTIAL ROAD (NALOOK-LAMBINGAN SECTION), AKLAN | Region VI | Region VI | On-Going | ₱156.9M | 94% | High risk64 | —-0.026 |
| 11 | 19GJ0209CONSTRUCTION OF DRAINAGE STRUCTURE - CONSTRUCTION/REHABILITATION OF DRAINAGE SYSTEM WITHIN THE VICINITY OF MANDURRIAO DISTRICT, ILOILO CITY | Region VI | Iloilo City DEO | Completed | ₱96.5M | 100% | High risk63 | —-0.039 |
| 12 | 22GH0034CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BAROTAC VIEJO RIVER, (STA. 4+337.60 - STA. 3+528.6), BRGY. POBLACION ILAWOD, BAROTAC VIEJO, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱96.5M | 100% | High risk63 | —-0.052 |
| 13 | 17GG0209COMPLETION OF UPGRADING FROM LEVEL I TO LEVEL II AND INCREASE IN BED CAPACITY OF ILOILO PROVINCIAL HOSPITAL, POTOTAN ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱26.5M | 100% | High risk63 | —-0.012 |
| 14 | 22G00136REHABILITATION OF CONCIENCIA - TINIGBAN PROVINCIAL ROAD (PORTION), PANITAN, CAPIZ | Region VI | Region VI | Completed | ₱120.6M | 100% | High risk60 | —-0.062 |
| 15 | 21G00126ROXAS CITY CIRCUMFERENTIAL ROAD, C2, CAPIZ | Region VI | Region VI | On-Going | ₱120.5M | 56% | High risk60 | —-0.007 |
| 16 | 22G00124KALIBO CIRCUMFERENTIAL ROAD, AKLAN | Region VI | Region VI | Completed | ₱110.8M | 100% | Medium risk59 | —-0.064 |
| 17 | 21GE0097CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - AT SPECIFIC LOCATIONS ALONG GUIMARAS CIRCUMFERENTIAL RD (S00028GR) K0047+732 - K0048+000 | Region VI | Guimaras DEO | Completed | ₱96.4M | 100% | Medium risk59 | —-0.074 |
| 18 | 22GG0062WIDENING OF BRIDGE, ULIAN BRIDGE (B00066PN) ALONG ILOILO CAPIZ ROAD (OLD ROUTE) | Region VI | Iloilo 2nd DEO | Completed | ₱89.3M | 100% | Medium risk54 | —-0.032 |
| 19 | 20GD0017ROAD WIDENING AT SPECIFIC LOCATIONS ALONG ROXAS CITY BDRY-PANITAN-BAILAN RD (S00312PN) KO118+998 - KO123+013 | Region VI | Capiz 1st DEO | Completed | ₱72.4M | 100% | Medium risk54 | —-0.077 |
| 20 | 22G00018ROXAS CITY CIRCUMFERENTIAL ROAD, C2 SECTION, CAPIZ | Region VI | Region VI | On-Going | ₱83.8M | 86% | Medium risk54 | —-0.019 |
| 21 | 24G00006ROXAS CITY CIRCUMFERENTIAL ROAD, C2 SECTION, CAPIZ | Region VI | Region VI | On-Going | ₱67.2M | 92% | Medium risk54 | —-0.043 |
| 22 | 18GG0049RECONSTRUCTION FROM PAVED TO CONCRETE OF ILOILO - CAPIZ (NEW ROUTE) INCLUDING ROW, K0024 + 880 - K0026 + 903, K0030 + 230 - K0030 + 407, K0025 + 911 - K0026 + 671 | Region VI | Iloilo 2nd DEO | Completed | ₱65.8M | 100% | Medium risk52 | —-0.081 |
| 23 | 22GG0063CONSTRUCTION OF FLOOD CONTROL STRUCTURE / SLOPE PROTECTION STRUCTURE ALONG SUAGE RIVER, POTOTAN, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱62.4M | 100% | Medium risk52 | —-0.056 |
| 24 | 25G00034KALIBO CIRCUMFERENTIAL ROAD, KALIBO, AKLAN | Region VI | Region VI | On-Going | ₱52.8M | 71% | Medium risk51 | —-0.046 |
| 25 | 20GG0104WIDENING OF BRIDGE, SAPAO BRIDGE (B00020PN) ALONG ILOILO CITY - LEGANES - DUMANGAS COASTAL ROAD | Region VI | Iloilo 2nd DEO | Completed | ₱51.7M | 100% | Medium risk50 | —-0.046 |