Opening the dossier…
Opening the dossier…
Contractor dossier
88 projects on file, including joint ventures this contractor is part of.
Total projects
88
Total budget
₱3.6B
Average progress
94.2%
Completion rate
61.4%
Below 70%
Average risk score
50.6
Medium risk on average, out of 100
Flagged as unusual
4
4.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 88 | ₱3.6B | 50.6 | 4 | 94.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 58 | ₱3.2B | 52.8 | 2 | 94.7% |
| Roads | 14 | ₱174M | 43.3 | 0 | 92.9% |
| Buildings and Facilities | 13 | ₱161.6M | 43.7 | 0 | 99.1% |
| GAA 2025 SSP | 1 | ₱47.2M | 95.4 | 1 | 46.0% |
| OTHER | 1 | ₱9.8M | 73.5 | 1 | 60.6% |
| Bridges | 1 | ₱24.3M | 48.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AJ0123CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MARUSAY RIVER, POBLACION EAST, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 46% | High risk95 | Flagged0.029 |
| 23AI0140CONCRETING/IMPROVEMENT OF SOLAR POTABLE WATER SYSTEM AT UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱9.8M | 61% | High risk74 | Flagged0.017 |
| 23A00438CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG MARUSAY RIVER AND TRIBUTARIES, CALASIAO, PANGASINAN (PACKAGE 2) | Region I | Region I | On-Going | ₱96.5M | 0% | High risk72 | Flagged0.080 |
| 23A00439CONSTRUCTION OF CALASIAO RIVERSIDE DIVERSION ROAD PROJECT, CALASIAO, PANGASINAN | Region I | Region I | Completed | ₱96.5M | 100% | High risk70 | Flagged0.025 |
| 25AI0154CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DEPALO RIVER, SAN QUINTIN, PANGASINAN (PACKAGE 1) | Region I | Pangasinan 3rd DEO | On-Going | ₱93.6M | 71% | High risk64 | —-0.022 |
| 25AI0155CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DEPALO RIVER, SAN QUINTIN, PANGASINAN (PACKAGE 2) | Region I | Pangasinan 3rd DEO | On-Going | ₱93.6M | 71% | High risk64 | —-0.022 |
| 25AI0032CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANILA RIVER, BALUNGAO-UMINGAN, PANGASINAN (PACKAGE 3) | Region I | Pangasinan 3rd DEO | On-Going | ₱95.4M | 100% | High risk64 | —-0.036 |
| 25AI0026CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MATABLANG RIVER, BALUNGAO, PANGASINAN (PACKAGE 3) | Region I | Pangasinan 3rd DEO | On-Going | ₱95.4M | 100% | High risk64 | —-0.036 |
| 25AI0025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MATABLANG RIVER, BALUNGAO, PANGASINAN (PACKAGE 2) | Region I | Pangasinan 3rd DEO | On-Going | ₱95.4M | 100% | High risk64 | —-0.036 |
| 25AI0027CONSTRUCTION OF FLOOD CO0NTROL STRUCTURE ALONG MATABLANG RIVER, BALUNGAO PANGASINAN (PACKAGE 4) | Region I | Pangasinan 3rd DEO | On-Going | ₱95.4M | 100% | High risk64 | —-0.036 |
| 24AI0147CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LAGASIT RIVER, PACKAGE A, BALUNGAO - SANTA MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱96.4M | 100% | High risk63 | —-0.060 |
| 24AI0148CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LAGASIT RIVER, PACKAGE B, BALUNGAO-SANTA MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱96.4M | 100% | High risk63 | —-0.060 |
| 25A00472CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BUED RIVER, SAN JACINTO, PANGASINAN (PACKAGE 2) | Region I | Region I | On-Going | ₱140.4M | 62% | High risk63 | —-0.008 |
| 25A00471CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BUED RIVER, SAN JACINTO, PANGASINAN (PACKAGE 1) | Region I | Region I | On-Going | ₱140.4M | 82% | High risk63 | —-0.017 |
| 25A00473CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BUED RIVER, SAN JACINTO, PANGASINAN (PACKAGE 3) | Region I | Region I | On-Going | ₱93.6M | 67% | High risk62 | —-0.020 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23A00438CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG MARUSAY RIVER AND TRIBUTARIES, CALASIAO, PANGASINAN (PACKAGE 2) | Region I | Region I | On-Going | ₱96.5M | 0% | High risk72 | Flagged0.080 |
| 25AJ0123CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MARUSAY RIVER, POBLACION EAST, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 46% | High risk95 | Flagged0.029 |
| 23A00439CONSTRUCTION OF CALASIAO RIVERSIDE DIVERSION ROAD PROJECT, CALASIAO, PANGASINAN | Region I | Region I | Completed | ₱96.5M | 100% | High risk70 | Flagged0.025 |
| 23AI0140CONCRETING/IMPROVEMENT OF SOLAR POTABLE WATER SYSTEM AT UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱9.8M | 61% | High risk74 | Flagged0.017 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23AI0150CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. KITA-KITA, BALUNGAO, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.089 |
| 27 | 25AI0039CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVERS, BALUNGAO-SANTA MARIA, PANGASINAN (PACKAGE 3) | Region I | Pangasinan 3rd DEO | On-Going | ₱47.7M | 100% | Medium risk51 | —-0.045 |
| 28 | 25AI0040CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVERS, BALUNGAO-SANTA MARIA, PANGASINAN (PACKAGE 4) | Region I | Pangasinan 3rd DEO | On-Going | ₱47.7M | 100% | Medium risk51 | —-0.045 |
| 29 | 25AI0041CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVERS, BALUNGAO-SANTA MARIA, PANGASINAN (PACKAGE 5) | Region I | Pangasinan 3rd DEO | On-Going | ₱47.7M | 100% | Medium risk51 | —-0.045 |
| 30 | 25AI0070CONSTRUCTION OF RIVERBANK SLOPE PROTECTION STRUCTURE, LAGASIT RIVER, PACKAGE 1, BALUNGAO, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱48.5M | 100% | Medium risk51 | —-0.046 |
| 31 | 24AI0074CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVER, UMINGAN, PANGASINAN (PACKAGE 1) | Region I | Pangasinan 3rd DEO | Completed | ₱49.4M | 100% | Medium risk51 | —-0.072 |
| 32 | 24AI0075CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVER, UMINGAN, PANGASINAN (PACKAGE II) | Region I | Pangasinan 3rd DEO | Completed | ₱49.4M | 100% | Medium risk51 | —-0.072 |
| 33 | 25AI0205CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 5) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 34 | 25AI0203CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 3) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 35 | 25AI0206CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 6) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 36 | 25AI0204CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 4) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 37 | 25AI0209CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG AGNO AND ALLIED RIVERS, STA. MARIA, PANGASINAN (PACKAGE 1) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 38 | 25AI0210CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG AGNO AND ALLIED RIVERS, STA. MARIA, PANGASINAN (PACKAGE 2) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 39 | 22AI0060CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANILA RIVER, BARANGAY LA PAZ - SAN LEON, UMINGAN, PANGASINAN, (PACKAGE 1) | Region I | Pangasinan 3rd DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.073 |
| 40 | 25AI0211CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG AGNO AND ALLIED RIVERS, STA. MARIA, PANGASINAN (PACKAGE 3) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 41 | 25AI0208CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LAGASIT AND ALLIED RIVERS, STA. MARIA, PANGASINAN (PACKAGE 3) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 42 | 25AI0207CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LAGASIT AND ALLIED RIVERS, STA. MARIA, PANGASINAN (PACKAGE 2) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 43 | 25AI0212CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LAGASIT AND ALLIED RIVERS, STA. MARIA, PANGASINAN (PACKAGE 4) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.7M | 100% | Medium risk51 | —-0.046 |
| 44 | 21AI0017CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANILA RIVER, BARANGAY LA PAZ, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱47M | 100% | Medium risk51 | —-0.066 |
| 45 | 25AI0068CONSTRUCTION OF FLOOD CONTROL ALONG CABULANDAYAN RIVERS, SAN NICOLAS, PANGASINAN (PACKAGE 2) | Region I | Pangasinan 3rd DEO | On-Going | ₱47.7M | 99% | Medium risk51 | —-0.041 |
| 46 | 24AI0073CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LAGASIT AND ALLIED RIVER, STA. MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱49M | 100% | Medium risk51 | —-0.037 |
| 47 | 24AI0072CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVER, BALUNGAO, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱49.4M | 100% | Medium risk50 | —-0.070 |
| 48 | 22AI0076CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANILA RIVER, BRGY. LA PAZ - SAN LEON, UMINGAN, PANGASINAN (PACKAGE 2) | Region I | Pangasinan 3rd DEO | Completed | ₱49M | 100% | Medium risk50 | —-0.073 |
| 49 | 22AI0077CONSTRUCTION OF RIVER WALL AT BARANGAY RAJAL, BALUNGAO, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱49M | 100% | Medium risk50 | —-0.069 |
| 50 | 24AI0064CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CABALANCIAN RIVER, KITA-KITA, BALUNGAO, PANGASINAN (PHASE I) | Region I | Pangasinan 3rd DEO | Completed | ₱48.9M | 100% | Medium risk50 | —-0.072 |