57 projects on file, including joint ventures this contractor is part of.
Total projects
57
Total budget
₱483.9M
Average progress
97.7%
Completion rate
94.7%
Average risk score
37.3
Medium risk on average, out of 100
Flagged as unusual
2
3.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 57 | ₱483.9M | 37.3 | 2 | 97.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 22 | ₱225M | 32.6 | 0 | 100.0% |
| Roads | 18 | ₱117.2M | 33.0 | 0 | 100.0% |
| Water Provision and Storage | 8 | ₱52M | 36.1 | 0 | 100.0% |
| Bridges | 6 | ₱58.2M | 44.7 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱28.8M | 95.2 | 2 | 34.1% |
| OTHER | 1 | ₱2.7M | 65.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BE0117CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUTURE PROGRAM (BIP) -BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ANNANUMAN BRIDGE, BARANGAY ANNANUMAN, SAN PABLO | Region II | Isabela 1st DEO | On-Going | ₱19.2M | 44% | High risk96 | Flagged0.026 |
| 25BE0116CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AND INSTALLATION OF RC PIPES IN BARANGAY CAM | Region II | Isabela 1st DEO | On-Going | ₱9.6M | 24% | High risk94 | Flagged0.029 |
| 17BE0040MFO 1: NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT-IMPROVEMENT / WIDENING OF NATIONAL ROADS-SECONDARY ROADS, CABAGAN-STA. MARIA RD-KO452+282-KO452+400 ROAD WIDENING AND RECONSTRUCTION OF EXISTING PCCP (THK.=0.15M) STA. MARIA, ISABELA | Region II | Isabela 1st DEO | Completed | ₱2.7M | 100% | High risk66 | —-0.028 |
| 17BE0033CONCRETING OF LOCAL ROADS OF BRGY. CALIGAYAN TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.4M | 100% | High risk64 | —-0.051 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BE0116CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AND INSTALLATION OF RC PIPES IN BARANGAY CAM | Region II | Isabela 1st DEO | On-Going | ₱9.6M | 24% | High risk94 | Flagged0.029 |
| 25BE0117CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUTURE PROGRAM (BIP) -BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ANNANUMAN BRIDGE, BARANGAY ANNANUMAN, SAN PABLO | Region II | Isabela 1st DEO | On-Going | ₱19.2M | 44% | High risk96 | Flagged0.026 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25BE0117CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUTURE PROGRAM (BIP) -BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ANNANUMAN BRIDGE, BARANGAY ANNANUMAN, SAN PABLO | Region II | Isabela 1st DEO | On-Going | ₱19.2M | 44% | High risk96 | Flagged0.026 |
| 2 | 25BE0116CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AND INSTALLATION OF RC PIPES IN BARANGAY CAM | Region II | Isabela 1st DEO | On-Going | ₱9.6M | 24% | High risk94 | Flagged0.029 |
| 3 | 17BE0040MFO 1: NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT-IMPROVEMENT / WIDENING OF NATIONAL ROADS-SECONDARY ROADS, CABAGAN-STA. MARIA RD-KO452+282-KO452+400 ROAD WIDENING AND RECONSTRUCTION OF EXISTING PCCP (THK.=0.15M) STA. MARIA, ISABELA | Region II | Isabela 1st DEO | Completed | ₱2.7M | 100% | High risk66 | —-0.028 |
| 4 | 17BE0033CONCRETING OF LOCAL ROADS OF BRGY. CALIGAYAN TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.4M | 100% | High risk64 | —-0.051 |
| 5 | 22BE0068CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY SAN PEDRO, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱15.8M | 100% | Medium risk54 | —-0.082 |
| 6 | 18BE0097CONSTRUCTION OF MULTI-PURPOSE BUILDING (SATELITE BAGSAKAN PUBLIC MARKET) STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.4M | 100% | Medium risk51 | —-0.083 |
| 7 | 23BE0084REHABILITATION OF BUNGAD BUNGAD BRIDGE, BRGY. BUNGAD, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | Completed | ₱6.9M | 100% | Medium risk49 | —-0.047 |
| 8 | 20BE0075CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CAMP SAMAL LEISURE PARK AND RESORT BRGY. ARCON, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.4M | 100% | Medium risk48 | —-0.082 |
| 9 | 24BE0040CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BRIDGE, BARANGAY COLUNGUAN, SANTO TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.8M | 100% | Medium risk48 | —-0.020 |
| 10 | 18BE0080COMPLETION OF MULTI-PURPOSE BUILDING TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.4M | 100% | Medium risk48 | —-0.082 |
| 11 | 24BE0098CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG LAGUNDAY-ROMA ROAD BOUNDARY, SANTA MARIA, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.084 |
| 12 | 23BE0142CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. CAMASI, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.052 |
| 13 | 23BE0070ASSET PRESERVATION- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS - SANTIAGO-TUGUEGARAO RD- KO419+(-100)- KO419+000, STA. MARIA, ISABELA | Region II | Isabela 1st DEO | Completed | ₱14.1M | 100% | Medium risk47 | —-0.084 |
| 14 | 18BE0038REBLOCKING/REPLACEMENT OF BRGY. LUQUILU-BRGY. CASIBARAG SUR TO CASIBARAG NORTE ROAD CABAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.083 |
| 15 | 23BE0144CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. ABRA-DY, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.050 |
| 16 | 23BE0076CONSTRUCTION OF BRIDGE, KAPAYAKAN, BARANGAY BLISS VILLAGE, ILAGAN CITY, ISABELA | Region II | Isabela 1st DEO | Completed | ₱14.8M | 100% | Medium risk46 | —-0.045 |
| 17 | 23BE0143CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. BANTUG, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.052 |
| 18 | 23BE0141CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. CALIGAYAN, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.051 |
| 19 | 22BE0037CONSTRUCTION OF NANAGUAN BRIDGE- PHASE II ILAGAN CITY, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.045 |
| 20 | 23BE0017REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - STA. ISABEL BR. (B02685LZ) ALONG ILAGAN - DELFIN ALBANO - MALLIG RD, CITY OF ILAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱7.3M | 100% | Medium risk46 | —-0.046 |
| 21 | 17BE0038COMPLETION OF MULTI-PURPOSE BUILDING BRGY. CALINAOAN CENTRO, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | Completed | ₱2.8M | 100% | Medium risk46 | —-0.058 |
| 22 | 17BE0039COMPLETION OF MULTI-PURPOSE BUILDING BRGY. SAN RAFAEL-ALTO, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | Completed | ₱2.8M | 100% | Medium risk45 | —-0.058 |
| 23 | 18BD0152CONSTRUCTION OF THREE (3) STOREY TWELVE (12) CLASSROOM (TWO (2) SCIENCE LABORATORY/TWO (2) CLASSROOM ICT & TWO (2) CLASSROOMREGULAR WORKSHOP BUILDING), ENRILE VOCATIONAL HIGH SCHOOL, ENRILE, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱27.2M | 100% | Medium risk45 | —-0.032 |
| 24 | 23BE0077REHABILITATION OF ROAD ALONG BRGY. AGA-BRGY. VILLA PEREDA, DELFIN ALBANO, ISABELA | Region II | Isabela 1st DEO | Completed | ₱24.5M | 100% | Medium risk44 | —-0.082 |
| 25 | 22BC0036CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TRIP) -ACCESS ROAD FROM OUR LADY OF PIAT SHRINE LEADING TO CAGAYAN STATE UNIVERSITY PIAT CAMPUS INTEGRATED AGRI-ECOTOURISM PARK, BRGY. BAUNG, PIAT, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱9.3M | 100% | Medium risk44 | —-0.079 |